This Construction Documents Technology Exam evaluates key aspects of construction management, focusing on substitution requests, contract interpretation, industry standards, and project delays. It's designed for professionals seeking to validate their expertise in managing construction documents effectively.
True
False
Rate this question:
True
False
Rate this question:
Previous negative experience with adversarial project team relationships
Desire for reduction in project claims and disputes
Desire to utilize collaboratively-produced BIM as a facilities management asset
Expectation of benefit from innovation stemming from collaborative effort
All of the above
Rate this question:
Articles (the, an, a)Â
Symbols (#, $, &, ")Â
Abbreviations (conc., ptwd, aess)
All of the above
Rate this question:
True
False
Rate this question:
Relies upon the quality of their update processÂ
Requires knowledge of the conditions of the contract for which they were prepared
May be based upon a commercially-produced specification library
Requires practice knowledge in order to properly create project specifications
All of the above
Rate this question:
True
False
Rate this question:
Record drawings
Construction Documents
Shop Drawings
Details
Rate this question:
Be provided by manufacturer, contractor, or installer
Be longer or shorter than the correction period
Exclude abuse, misuse, and failure to maintain
All of the above
Rate this question:
True
False
Rate this question:
Industry foundation classes (IFCs)
OmniClass
Building information model (BIM)
Building information management (BIM)
Rate this question:
True
False
Rate this question:
Write Architect/Engineer protesting the changes
Notify his bonding company
Write the Architect/Engineer requesting a change order granting an extension of time
Stop the Work until Owner makes up his mind.
Rate this question:
Industry foundation classes (IFCs)Â
OmniClassÂ
Building Information Model (BIM)
Building Information Management (BIM) Â Building Information Management (BIM) Â Building Information Management (BIM)
Rate this question:
Complete, concise, and clear
Concise, clear, and correct
Clear, concise, correct, and complete
Concise, correct, coordinated, and complete
Rate this question:
Maintenance bond
Payment bond
Bid bond
Performance bond
Rate this question:
True
False
Rate this question:
Contract forms
Closeout submittals
Record drawings
As-builts
Not required for private work
Rate this question:
Write the specification section.
Review the specification section.
Supply information to the specification writer.
Not be consulted in order to avoid a conflict of interest.
Rate this question:
The Supplementary Conditions should state that the period last a specific additional length of time.
EJCDC and AIA documents state "correction period" instead of guaranty period.
The owner accepts any repairs after that date.
 the courts relieve the contractor of his responsibility.
Rate this question:
The supplementary conditions should state that the period last a specific additional length of time
EJCDC and AIA documents state correction period instead of guaranty period
The owner accepts any repairs after that date
The courts relieve the contractor of his responsibility
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
Decrease in Contract Sum
Extension of Contract Time
Change in Bid Date
Reduction in scope of work
Rate this question:
Selection
Payment
Award
Contract
Rate this question:
Trust-based collaboration between project team members
Maximized efficiency through design, fabrication, and construction
"Just as needed" team involvement to reduce owner's pre-construction expenses
Compensation structures supporting early engagement of team members in design and project planning
Development of virtual project model through input from a collaborative team
Rate this question:
Conceptualization
Criteria Design
Detailed DesignÂ
 Implementation Document
All of the above
Rate this question:
Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated.
Extent of work is known, but the owner desires a break-out cost for portions of the work.
It is anticipated that bidders will not examine soil bearing reports prior to submitting bid.
Bidding quantities of equipment.
Rate this question:
The Owner, the designer, and the builder.Â
The Owner, the Architect, and the ContractorÂ
The Owner and the construction managerÂ
The Owner and the design-builder
Rate this question:
Predesign
Planning
Commissioning
Programming
Rate this question:
A/E
Owner
Contractor
Varies - As stated in Division 01 General Requirements
None of the above
Rate this question:
A/E
Owner
Contractor
Varies - As stated in Division 01 General Requirements
None of the above
Rate this question:
Actual dimensions
Nominal dimensions
Modular dimensions
All of the above
Rate this question:
Increased productivity
Reduced project costs
Earlier project completion
Fewer meetings
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
Contractor's surety
Owner
Contractor
Financing agency
None of the above
Rate this question:
True
False
Rate this question:
Project insurance requirements
Liquidated damage amounts
Tax exempt status of owner
Submittal requirements
Rate this question:
The imperative mood
The indicative mood
The symbolic mood
The conflicting mood
Rate this question:
Contractor's surety
Owner
Contractor
Financing agencyÂ
None of the above
Rate this question:
As Builts
Addendums
Record Drawings
Mark ups
Rate this question:
True
False
Rate this question:
Unit price
Cost per measured unit
Systems
Component cost
Rate this question:
Insurance requirements
Liquidated damages
Tax exempt status of Owner
Submittal requirements
Rate this question:
True
False
Rate this question:
Owner and contractor
Architect/engineer and contractor
Owner and Subcontractors
Owner, contractor, and architect/engineer
Rate this question:
It is used to establish the proper location of information within the sixteen divisions
It contains a complete listing of topics covered in each division
It contains a key word index
All of the above
Rate this question:
Quiz Review Timeline (Updated): Oct 22, 2024 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.