Construction Documents Technology Exam: Quiz!

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Morganrae91
M
Morganrae91
Community Contributor
Quizzes Created: 1 | Total Attempts: 6,758
| Attempts: 6,881
SettingsSettings
Please wait...
  • 1/124 Questions

    What are the three parts of the SectionFormat?

    • General
    • Products
    • Execution
    • All of the above
Please wait...
About This Quiz

This Construction Documents Technology Exam evaluates key aspects of construction management, focusing on substitution requests, contract interpretation, industry standards, and project delays. It's designed for professionals seeking to validate their expertise in managing construction documents effectively.

Construction Documents Technology Exam: Quiz! - Quiz

Quiz Preview

  • 2. 

    True or False: Zoning is an example of a land development regulation. 

    • True

    • False

    Correct Answer
    A. True
    Explanation
    Zoning is indeed an example of a land development regulation. It refers to the process of dividing land into different zones or areas with specific regulations and restrictions regarding land use, building heights, density, and other factors. Zoning aims to promote orderly and efficient land development, protect property values, and ensure compatibility between different land uses within a community. It is commonly used by local governments to control and guide the growth and development of cities and towns.

    Rate this question:

  • 3. 

    True or False: By executing the contract, the Contractor confirms that the contract time is reasonable.  

    • True

    • False

    Correct Answer
    A. True
    Explanation
    By executing the contract, the Contractor confirms that they agree to the terms and conditions outlined in the contract, including the contract time. This implies that the Contractor believes the contract time is reasonable and feasible to complete the project within the specified timeframe. Therefore, the statement is true.

    Rate this question:

  • 4. 

    Experienced owners may require project teams to utilize integrated project delivery based upon:

    • Previous negative experience with adversarial project team relationships

    • Desire for reduction in project claims and disputes

    • Desire to utilize collaboratively-produced BIM as a facilities management asset

    • Expectation of benefit from innovation stemming from collaborative effort

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    Experienced owners may require project teams to utilize integrated project delivery for several reasons. Firstly, they may have had previous negative experiences with adversarial project team relationships, and integrating the team can help improve communication and collaboration. Secondly, they may desire a reduction in project claims and disputes, which can be achieved through a more collaborative approach. Additionally, they may want to utilize collaboratively-produced Building Information Modeling (BIM) as a facilities management asset, as it can provide valuable information for the long-term maintenance of the project. Lastly, they may expect to benefit from innovation stemming from the collaborative effort of the team. Therefore, all of the given reasons can be valid explanations for why experienced owners may require integrated project delivery.

    Rate this question:

  • 5. 

    Which of the following should be avoided in a specification?

    • Articles (the, an, a) 

    • Symbols (#, $, &, ") 

    • Abbreviations (conc., ptwd, aess)

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    All of the options mentioned (articles, symbols, and abbreviations) should be avoided in a specification. Articles can make the specification ambiguous, symbols can be confusing or misinterpreted, and abbreviations can lead to misunderstandings. It is important to use clear and concise language in a specification to ensure that it is easily understood by all parties involved.

    Rate this question:

  • 6. 

    True or False: There is no difference between the construction schedule and the project schedule.

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The statement is false because there is a difference between the construction schedule and the project schedule. The construction schedule specifically focuses on the timeline and activities related to the construction phase of a project, while the project schedule encompasses the entire project from start to finish, including planning, design, procurement, construction, and closeout. The project schedule is a broader and more comprehensive document that includes all the necessary tasks and milestones for the successful completion of the project, while the construction schedule is a subset of the project schedule that only pertains to the construction activities.

    Rate this question:

  • 7. 

    Use of master guide specifications:

    • Relies upon the quality of their update process 

    • Requires knowledge of the conditions of the contract for which they were prepared

    • May be based upon a commercially-produced specification library

    • Requires practice knowledge in order to properly create project specifications

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    The use of master guide specifications encompasses all of the given statements. The quality of the update process is crucial as it ensures that the specifications are up to date and accurate. Knowledge of the contract conditions is necessary to tailor the specifications accordingly. Utilizing a commercially-produced specification library can provide a standardized and comprehensive approach. Lastly, practice knowledge is required to effectively create project specifications that meet the specific requirements and standards. Therefore, all of the above statements are valid explanations for the correct answer.

    Rate this question:

  • 8. 

    True or False: There being no contractual relationship between the A/E and the contractor, there is also no contractual relationship between the A/E and the subcontractors and suppliers.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement is true because if there is no contractual relationship between the A/E (Architect/Engineer) and the contractor, it follows that there would also be no contractual relationship between the A/E and the subcontractors and suppliers. Without a contractual agreement, there would be no legal obligations or responsibilities between these parties.

    Rate this question:

  • 9. 

    Drawings prepared by the contractor, subcontractor, or material/equipment supplier that show how a particular aspect of the work is to be fabricated and installed, are called:

    • Record drawings

    • Construction Documents

    • Shop Drawings

    • Details

    Correct Answer
    A. Shop Drawings
    Explanation
    Shop drawings are detailed drawings prepared by the contractor, subcontractor, or material/equipment supplier to show how a specific aspect of the work is to be fabricated and installed. These drawings provide specific information about dimensions, materials, and installation methods, helping to ensure that the work is carried out accurately and according to the design intent. Shop drawings are typically used in construction projects to coordinate and communicate between different parties involved in the construction process. They are an essential tool for ensuring the quality and accuracy of the final construction.

    Rate this question:

  • 10. 

    Special warranties/guarantees can: 

    • Be provided by manufacturer, contractor, or installer

    • Be longer or shorter than the correction period

    • Exclude abuse, misuse, and failure to maintain

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    Special warranties/guarantees can be provided by the manufacturer, contractor, or installer. These warranties/guarantees can have different durations, meaning they can be longer or shorter than the correction period. Additionally, these warranties/guarantees often exclude coverage for abuse, misuse, and failure to maintain the product or service. Therefore, the correct answer is "All of the above."

    Rate this question:

  • 11. 

    True or False: Sustainability consultants can only be retained by the design team

    • True

    • False

    Correct Answer
    A. False
    Explanation
    Sustainability consultants are not limited to being retained only by the design team. They can be hired by any organization or individual who wants to incorporate sustainable practices into their operations. Sustainability consultants provide guidance and expertise in areas such as energy efficiency, waste reduction, and environmental impact assessment. They work with various stakeholders, including architects, engineers, facility managers, and business owners, to develop and implement sustainable strategies. Therefore, the statement that sustainability consultants can only be retained by the design team is false.

    Rate this question:

  • 12. 

    An information organizing framework for the design and construction industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as: 

    • Industry foundation classes (IFCs)

    • OmniClass

    • Building information model (BIM)

    • Building information management (BIM)

    Correct Answer
    A. OmniClass
    Explanation
    OmniClass is an information organizing framework for the design and construction industry that categorizes built environment data into 15 coordinated tables. These tables help in organizing project information and databases efficiently. It provides a standardized system for classifying and organizing information related to construction projects, making it easier for professionals in the industry to communicate and collaborate effectively. OmniClass is widely used in the industry as a classification system and is recognized for its ability to streamline project management and improve data interoperability.

    Rate this question:

  • 13. 

    True or False: If a portion of the work is covered contrary to requirements specifically expressed in the Contract Documents, it must if requested by the A/E, be uncovered for examination and at the Contractors expense without change in the contract time.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    If a portion of the work is covered in a way that goes against the requirements stated in the contract documents, the architect/engineer (A/E) has the right to request that it be uncovered for examination. The contractor would be responsible for the expense of uncovering the work, and this would not result in a change in the contract time.

    Rate this question:

  • 14. 

    If the contractor is delayed in the progress of the Work by Owner, he should: 

    • Write Architect/Engineer protesting the changes

    • Notify his bonding company

    • Write the Architect/Engineer requesting a change order granting an extension of time

    • Stop the Work until Owner makes up his mind.

    Correct Answer
    A. Write the Architect/Engineer requesting a change order granting an extension of time
    Explanation
    If the contractor is delayed in the progress of the work by the owner, it is appropriate for the contractor to write the architect/engineer requesting a change order granting an extension of time. This is because the contractor is not responsible for delays caused by the owner and may need additional time to complete the work due to the owner's actions. By requesting a change order, the contractor can formally document the delay and request an extension to the project timeline. This ensures that the contractor is not held accountable for delays that are beyond their control.

    Rate this question:

  • 15. 

    An information organizing framework for the A/E/C industry that assigns built environment data into 15 discrete, coordinated tables to facilitate the organization of project information and databases is known as:

    • Industry foundation classes (IFCs) 

    • OmniClass 

    • Building Information Model (BIM)

    • Building Information Management (BIM)   Building Information Management (BIM)   Building Information Management (BIM)

    Correct Answer
    A. OmniClass 
    Explanation
    OmniClass is an information organizing framework for the A/E/C industry that categorizes built environment data into 15 coordinated tables. It is designed to facilitate the organization of project information and databases, making it easier to manage and access relevant data. Unlike Industry Foundation Classes (IFCs) and Building Information Model (BIM), which are also used in the A/E/C industry but have different purposes, OmniClass specifically focuses on providing a structured framework for organizing information. Therefore, OmniClass is the correct answer in this context.

    Rate this question:

  • 16. 

    To be effective in communicating, specifications should be:

    • Complete, concise, and clear

    • Concise, clear, and correct

    • Clear, concise, correct, and complete

    • Concise, correct, coordinated, and complete

    Correct Answer
    A. Clear, concise, correct, and complete
    Explanation
    To be effective in communicating, specifications should be clear, meaning they should be easily understandable and free from ambiguity. They should also be concise, providing information in a succinct and to-the-point manner. Additionally, specifications should be correct, ensuring that the information provided is accurate and without errors. Lastly, specifications should be complete, covering all necessary details and leaving no important information out. Therefore, the answer "Clear, concise, correct, and complete" encompasses all the essential qualities required for effective communication of specifications.

    Rate this question:

  • 17. 

    Which bond protects the owner from losing the benefit of an accepted bid? 

    • Maintenance bond

    • Payment bond

    • Bid bond

    • Performance bond

    Correct Answer
    A. Bid bond
    Explanation
    A bid bond is a type of surety bond that protects the owner from financial loss if the bidder fails to fulfill their obligations after being awarded the contract. It ensures that the bidder will enter into a contract and provide the required performance and payment bonds if their bid is accepted. In other words, it guarantees that the owner will not lose the benefit of the accepted bid if the bidder backs out or fails to meet their contractual obligations.

    Rate this question:

  • 18. 

    True or False: The A/E may withhold certification for payment in whole or in part if in the A/E’s opinion representations to Owner cannot be made concerning the progress of the work.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The A/E (Architect/Engineer) has the authority to withhold certification for payment if they believe that they cannot make representations to the owner regarding the progress of the work. This means that if the A/E believes that the work is not progressing as it should be or if there are issues with the quality or completion of the work, they can choose to withhold certification for payment. This allows the A/E to ensure that the owner is not paying for work that is not up to standard or is not progressing as expected.

    Rate this question:

  • 19. 

    Marked-up or corrected contract drawings that indicate changes incorporated in the Work are:

    • Contract forms

    • Closeout submittals

    • Record drawings

    • As-builts

    • Not required for private work

    Correct Answer
    A. Record drawings
    Explanation
    Record drawings are marked-up or corrected contract drawings that indicate changes incorporated in the work. They are typically created during the construction process to document any modifications or alterations made to the original contract drawings. These drawings serve as a record of the as-built conditions and are often used for future reference, maintenance, or renovation purposes. Unlike contract forms, closeout submittals, and as-builts, record drawings are not required for private work, but they are commonly used in public projects to ensure accuracy and compliance.

    Rate this question:

  • 20. 

    Since he or she is most familiar with a product, the manufacturer's representative should:

    • Write the specification section.

    • Review the specification section.

    • Supply information to the specification writer.

    • Not be consulted in order to avoid a conflict of interest.

    Correct Answer
    A. Supply information to the specification writer.
    Explanation
    The manufacturer's representative should supply information to the specification writer because they have the most familiarity with the product. They can provide the necessary details and technical information that the specification writer may need to accurately describe the product in the specification section. This ensures that the specifications are accurate and meet the requirements of the product. Consulting the manufacturer's representative helps in avoiding any conflict of interest and ensures that the specification section is well-informed and comprehensive.

    Rate this question:

  • 21. 

    As a result of the widely held misconception that a contractor's responsibility for defective work lasts only for the one-year guaranty period: 

    • The Supplementary Conditions should state that the period last a specific additional length of time.

    • EJCDC and AIA documents state "correction period" instead of guaranty period.

    • The owner accepts any repairs after that date.

    •  the courts relieve the contractor of his responsibility.

    Correct Answer
    A. EJCDC and AIA documents state "correction period" instead of guaranty period.
    Explanation
    The correct answer is that EJCDC and AIA documents state "correction period" instead of guaranty period. This means that the contractor's responsibility for defective work extends beyond just the one-year guaranty period. The use of the term "correction period" implies that the contractor must correct any defects or issues with their work for a specific additional length of time, as stated in the Supplementary Conditions. This clarification helps to prevent any misconceptions or misunderstandings about the contractor's responsibilities and ensures that the owner can expect repairs or corrections even after the initial guaranty period has ended.

    Rate this question:

  • 22. 

    As a result of the widely held misconception that a contractor's responsibility for defective work lasts only for the one-year guaranty period:  

    • The supplementary conditions should state that the period last a specific additional length of time

    • EJCDC and AIA documents state correction period instead of guaranty period

    • The owner accepts any repairs after that date

    • The courts relieve the contractor of his responsibility

    Correct Answer
    A. EJCDC and AIA documents state correction period instead of guaranty period
    Explanation
    The correct answer is that EJCDC and AIA documents state correction period instead of guaranty period. This means that according to these documents, the contractor's responsibility for defective work lasts for a specific period of time called the correction period, rather than a guaranty period. This indicates that the contractor is responsible for making any necessary repairs or corrections during this specified time frame.

    Rate this question:

  • 23. 

    True or False: Shop drawings are not contract documents.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    Shop drawings are not contract documents because they are detailed drawings produced by the contractor, subcontractor, or supplier that show the specific installation and fabrication details of the project. While they are important for coordination and construction purposes, they are not considered part of the legal contract between the owner and the contractor. Contract documents typically include the agreement, general conditions, specifications, and drawings prepared by the architect or engineer. Shop drawings are considered supplementary to the contract documents and are used to provide more specific information about how certain elements of the project will be constructed.

    Rate this question:

  • 24. 

    True or False: The facility manager should not be involved in project closeout because the facility manager is not a party to the construction contract. 

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The statement is false because the facility manager should be involved in project closeout. While the facility manager may not be a party to the construction contract, they play a crucial role in ensuring that the project is completed successfully and that all necessary tasks are carried out during the closeout phase. The facility manager is responsible for overseeing the transition from construction to operations, ensuring that all systems are functioning properly, and addressing any outstanding issues or deficiencies before the project is considered complete.

    Rate this question:

  • 25. 

    All of the following may be accomplished through issuing of a Change Order EXCEPT: 

    • Decrease in Contract Sum

    • Extension of Contract Time

    • Change in Bid Date

    • Reduction in scope of work

    Correct Answer
    A. Change in Bid Date
    Explanation
    A Change Order is a written agreement between the owner and contractor that authorizes a change in the scope of work or other contract terms. It is used to document and approve changes to the original contract. A Change in Bid Date, however, does not involve a change in the scope of work or contract terms. It simply refers to a modification in the date by which bids must be submitted. Therefore, it is not accomplished through issuing a Change Order.

    Rate this question:

  • 26. 

    Lump Sum, Unit Price, or Cost-Plus-Fee constitute the basis of:

    • Selection

    • Payment

    • Award

    • Contract

    Correct Answer
    A. Payment
    Explanation
    The options Lump Sum, Unit Price, and Cost-Plus-Fee all refer to different methods of payment in a contract. Lump Sum refers to a fixed payment amount for the entire project, Unit Price refers to payment based on the quantity of units used or produced, and Cost-Plus-Fee refers to payment based on the actual cost of materials and labor plus an additional fee. Therefore, the correct answer is Payment.

    Rate this question:

  • 27. 

    Integrated projects are distinguished by all of the following characteristics EXCEPT:

    • Trust-based collaboration between project team members

    • Maximized efficiency through design, fabrication, and construction

    • "Just as needed" team involvement to reduce owner's pre-construction expenses

    • Compensation structures supporting early engagement of team members in design and project planning

    • Development of virtual project model through input from a collaborative team

    Correct Answer
    A. "Just as needed" team involvement to reduce owner's pre-construction expenses
    Explanation
    This answer is correct because all of the other characteristics mentioned (trust-based collaboration, maximized efficiency, compensation structures supporting early engagement, and development of virtual project model) are distinguishing features of integrated projects. However, "just as needed" team involvement to reduce owner's pre-construction expenses does not necessarily align with the collaborative and integrated nature of these projects.

    Rate this question:

  • 28. 

    The nationally-recognized California AIA "Integrated Project Delivery Guide" redefines the stages of a project to include which of the following: 

    • Conceptualization

    • Criteria Design

    • Detailed Design 

    •  Implementation Document

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    The correct answer is "All of the above". The California AIA "Integrated Project Delivery Guide" includes all of the mentioned stages of a project, which are conceptualization, criteria design, detailed design, and implementation document. This guide redefines the traditional stages of a project and emphasizes the importance of integrating various aspects throughout the entire project lifecycle.

    Rate this question:

  • 29. 

    A unit price contract or contract portion is used when:

    • Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated.

    • Extent of work is known, but the owner desires a break-out cost for portions of the work.

    • It is anticipated that bidders will not examine soil bearing reports prior to submitting bid.

    • Bidding quantities of equipment.

    Correct Answer
    A. Extent of work cannot be fully determined or where actual quantities cannot be accurately calculated.
    Explanation
    A unit price contract or contract portion is used when the extent of work cannot be fully determined or where actual quantities cannot be accurately calculated. This type of contract allows for flexibility in pricing based on the actual quantities of work performed or materials used. It is particularly useful in situations where the scope of work may change or where there is uncertainty in the quantities involved. By using unit prices, the contractor and owner can agree on a fair and reasonable price for each unit of work, which can then be multiplied by the actual quantities to determine the total cost.

    Rate this question:

  • 30. 

    The parties to an owner/design-builder contract are::

    • The Owner, the designer, and the builder. 

    • The Owner, the Architect, and the Contractor 

    • The Owner and the construction manager 

    • The Owner and the design-builder

    Correct Answer
    A. The Owner and the design-builder
    Explanation
    In an owner/design-builder contract, the parties involved are the owner and the design-builder. This means that the owner of the project and the entity responsible for both the design and construction of the project are the main parties in this type of contract. The owner/design-builder contract allows for a more streamlined and integrated approach to the project, as the design and construction aspects are handled by a single entity. This can lead to greater efficiency and cost savings for the owner. The other options provided in the question do not accurately represent the parties involved in an owner/design-builder contract.

    Rate this question:

  • 31. 

    All of the following activities are associated with the project conception stage except which one?

    • Predesign

    • Planning

    • Commissioning

    • Programming

    Correct Answer
    A. Commissioning
    Explanation
    The project conception stage involves activities such as predesign, planning, and programming. Predesign refers to the initial phase of gathering information and conducting feasibility studies. Planning involves creating a roadmap and determining the resources required for the project. Programming involves defining the project's objectives and requirements. Commissioning, on the other hand, is associated with the project's implementation and refers to the process of ensuring that all systems and components are installed, tested, and functioning correctly. Therefore, commissioning is not typically associated with the project conception stage.

    Rate this question:

  • 32. 

    Under AIA A201, who has the authority to stop the work, if nonconforming work fails to be corrected? 

    • A/E

    • Owner

    • Contractor

    • Varies - As stated in Division 01 General Requirements

    • None of the above

    Correct Answer
    A. Owner
    Explanation
    According to AIA A201, the owner has the authority to stop the work if nonconforming work fails to be corrected. This means that if the work being done does not meet the required standards or specifications, the owner has the power to halt the progress until the issues are resolved. The A/E (Architect/Engineer) and the contractor may also have some authority in this matter, but the ultimate decision-making power lies with the owner.

    Rate this question:

  • 33. 

    Under the AIA A201 and the EJCDC C-700, who has the authority to stop the Work, if nonconforming Work fails to be corrected?

    • A/E

    • Owner

    • Contractor

    • Varies - As stated in Division 01 General Requirements

    • None of the above

    Correct Answer
    A. Owner
    Explanation
    According to the AIA A201 and the EJCDC C-700, the owner has the authority to stop the work if nonconforming work fails to be corrected. This means that if the work being done does not meet the required standards or specifications, the owner has the power to halt the project until the issues are resolved. The A/E (Architect/Engineer), contractor, and any other parties involved do not have the authority to stop the work in this situation. The owner is ultimately responsible for ensuring that the work meets the necessary standards and can take action to address any nonconforming work.

    Rate this question:

  • 34. 

    Which of these types of dimensions are likely to be included on one drawing:

    • Actual dimensions

    • Nominal dimensions

    • Modular dimensions

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    All of the above types of dimensions are likely to be included on one drawing. Actual dimensions represent the precise measurements of the object being drawn, while nominal dimensions are approximate values used for general reference. Modular dimensions are standardized measurements that allow for easy assembly and interchangeability of components. Including all of these dimensions on a drawing ensures that all necessary information is provided for accurate manufacturing and assembly processes.

    Rate this question:

  • 35. 

    . One of the benefits of working as a team is not:

    • Increased productivity

    • Reduced project costs

    • Earlier project completion

    • Fewer meetings

    Correct Answer
    A. Fewer meetings
    Explanation
    Working as a team can lead to increased productivity, reduced project costs, and earlier project completion. However, it does not necessarily result in fewer meetings. In fact, working as a team often requires more frequent and regular meetings to ensure effective communication, coordination, and collaboration among team members. Meetings are essential for discussing progress, resolving issues, making decisions, and maintaining alignment within the team. Therefore, the statement "Fewer meetings" is not a benefit of working as a team.

    Rate this question:

  • 36. 

    True or False: AIA Design Phases include schematic design, design development, and construction documents.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The AIA Design Phases, which stands for American Institute of Architects Design Phases, include schematic design, design development, and construction documents. These phases are a systematic approach to the design and construction process, allowing for a clear progression from initial concepts to detailed plans and specifications. Schematic design involves creating rough sketches and conceptual ideas, design development refines these ideas into more detailed plans, and construction documents are the final set of drawings and specifications that guide the actual construction process.

    Rate this question:

  • 37. 

    True or False: Under a single-prime contract, the owner has a contractual relationship with suppliers and subcontractors

    • True

    • False

    Correct Answer
    A. False
    Explanation
    Under a single-prime contract, the owner does not have a contractual relationship with suppliers and subcontractors. In a single-prime contract, the owner only has a contractual relationship with the prime contractor, who is responsible for managing and coordinating all aspects of the project, including subcontractors and suppliers. The prime contractor is the one who enters into contracts with suppliers and subcontractors, not the owner. Therefore, the correct answer is false.

    Rate this question:

  • 38. 

    Under the AIA A201 and EJCDC C-700, who provides property insurance covering the Work?

    • Contractor's surety

    • Owner

    • Contractor

    • Financing agency

    • None of the above

    Correct Answer
    A. Owner
    Explanation
    According to the AIA A201 and EJCDC C-700, the owner is responsible for providing property insurance covering the work. This means that the owner is responsible for insuring the property during the construction process. The contractor's surety, contractor, financing agency, or any other party mentioned in the options is not responsible for providing this insurance.

    Rate this question:

  • 39. 

    True or False: The OmniClass construction specification system is based on the International Organization for Standards (ISO). 

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The statement is true. The OmniClass construction specification system is indeed based on the International Organization for Standards (ISO). This means that the system follows the guidelines and standards set by ISO, ensuring consistency and compatibility with other international standards.

    Rate this question:

  • 40. 

    The following are the types of clauses that might be included in Supplementary Conditions EXCEPT: 

    • Project insurance requirements

    • Liquidated damage amounts

    • Tax exempt status of owner

    • Submittal requirements

    Correct Answer
    A. Submittal requirements
    Explanation
    The given answer is "Submittal requirements". This is because submittal requirements are not a type of clause that would typically be included in Supplementary Conditions. Supplementary Conditions usually include clauses related to project insurance requirements, liquidated damage amounts, and the tax exempt status of the owner. Submittal requirements, on the other hand, are typically included in the General Conditions or in separate submittal documents.

    Rate this question:

  • 41. 

    The mood that is recommended for specifications is:

    • The imperative mood

    • The indicative mood

    • The symbolic mood

    • The conflicting mood

    Correct Answer
    A. The imperative mood
    Explanation
    The imperative mood is recommended for specifications because it is a grammatical mood that expresses commands, requests, or instructions. Specifications typically provide detailed instructions or requirements for a particular task or project, and using the imperative mood helps to convey these instructions clearly and directly. It creates a sense of authority and urgency, making it easier for the reader to understand and follow the specifications accurately.

    Rate this question:

  • 42. 

    Under the AIA A201 and EJCDC C-700, who provides property insurance covering the Work? 

    • Contractor's surety

    • Owner

    • Contractor

    • Financing agency 

    • None of the above

    Correct Answer
    A. Owner
    Explanation
    According to the AIA A201 and EJCDC C-700, the owner is responsible for providing property insurance covering the work. This means that the owner is required to obtain insurance coverage to protect against any damage or loss that may occur during the construction process. The contractor's surety, contractor, financing agency, or any other party mentioned in the options is not responsible for providing this insurance.

    Rate this question:

  • 43. 

    Marked up or corrected contract drawings that indicate changes incorporated in the Work are called:

    • As Builts

    • Addendums

    • Record Drawings

    • Mark ups

    Correct Answer
    A. Record Drawings
    Explanation
    Record Drawings are marked up or corrected contract drawings that indicate changes incorporated in the work. These drawings are typically created during the construction process to document any modifications or deviations from the original contract drawings. They serve as a record of the actual construction and are often used for reference and future maintenance or renovation purposes.

    Rate this question:

  • 44. 

    True or False: As a project proceeds through the project delivery process (time), the ability to influence the cost is high at the beginning, but decreases as the project advances through the various stages.

    • True

    • False

    Correct Answer
    A. True
    Explanation
    As a project progresses through the project delivery process, the ability to influence the cost is high at the beginning but decreases as the project advances through the various stages. This is because during the initial stages, there is more flexibility to make changes and adjustments that can impact the cost. However, as the project moves forward and more resources and activities are committed, the options for cost control become more limited. Therefore, it is important to address cost considerations early in the project to maximize the ability to influence and manage costs effectively.

    Rate this question:

  • 45. 

    If the construction budget of a 50,000 square foot project is $5,000,000 based on $100 per square foot, it is an example of which method of preparing the budget? 

    • Unit price

    • Cost per measured unit

    • Systems

    • Component cost

    Correct Answer
    A. Cost per measured unit
    Explanation
    The given scenario of a construction budget for a 50,000 square foot project being calculated based on $100 per square foot indicates the use of the "Cost per measured unit" method. In this method, the budget is prepared by determining the cost of each measured unit (in this case, the cost per square foot) and multiplying it by the quantity required (in this case, the total square footage of the project).

    Rate this question:

  • 46. 

    All of the following subjects are usually included in Supplementary Conditions EXCEPT

    • Insurance requirements

    • Liquidated damages

    • Tax exempt status of Owner

    • Submittal requirements

    Correct Answer
    A. Submittal requirements
    Explanation
    Supplementary conditions are additional contract provisions that modify or supplement the general conditions of a construction contract. They typically address specific project requirements or conditions. Insurance requirements, liquidated damages, and tax exempt status of the owner are all common subjects that may be included in supplementary conditions. However, submittal requirements are not typically included in supplementary conditions. Submittal requirements are usually addressed in the contract documents or project specifications, rather than in supplementary conditions.

    Rate this question:

  • 47. 

    True or False: The A/E is required to determine the project delivery method

    • True

    • False

    Correct Answer
    A. False
    Explanation
    The A/E (Architect/Engineer) is not required to determine the project delivery method. The project delivery method is typically determined by the owner or client in consultation with the A/E and other stakeholders. The A/E's role is to provide expertise and recommendations regarding the various delivery methods available, but the final decision rests with the owner or client. Therefore, the statement is false.

    Rate this question:

  • 48. 

    The contractual relationship governed by the Conditions of the Contract is between:

    • Owner and contractor

    • Architect/engineer and contractor

    • Owner and Subcontractors

    • Owner, contractor, and architect/engineer

    Correct Answer
    A. Owner and contractor
    Explanation
    The correct answer is Owner and contractor. This is because the Conditions of the Contract govern the contractual relationship between the owner of the project and the contractor hired to carry out the construction work. The owner is responsible for providing the necessary funds and specifications, while the contractor is responsible for executing the project according to the agreed terms and conditions. The architect/engineer may be involved in the project as a consultant or advisor, but the primary contractual relationship is between the owner and the contractor.

    Rate this question:

  • 49. 

    Which is true concerning MasterFormat?

    • It is used to establish the proper location of information within the sixteen divisions

    • It contains a complete listing of topics covered in each division

    • It contains a key word index

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    MasterFormat is a standardized system used in the construction industry to organize and classify information related to construction projects. It is used to establish the proper location of information within the sixteen divisions, which helps in efficient communication and coordination among various stakeholders. Additionally, it contains a complete listing of topics covered in each division, ensuring that all aspects of a project are properly addressed. Furthermore, MasterFormat includes a keyword index, making it easier to locate specific information. Therefore, all the given statements about MasterFormat are true.

    Rate this question:

Quiz Review Timeline (Updated): Oct 22, 2024 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Oct 22, 2024
    Quiz Edited by
    ProProfs Editorial Team
  • Oct 24, 2016
    Quiz Created by
    Morganrae91
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.