The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Lekicaleksandar8
L
Lekicaleksandar8
Community Contributor
Quizzes Created: 2 | Total Attempts: 1,966
| Attempts: 1,767
SettingsSettings
Please wait...
  • 1/126 Pitanja

    Označi tačnu tvrdnju:

    • Pojedinci lakse od tima rešavaju složene probleme
    • Rezultati tima nadmašuju pojedinačne rezultate
    • Timovi ne promovišu organizaciono učenje
Please wait...
Upi 1 Kolokvijum - Quiz


Quiz Preview

  • 2. 

    Kako se graficki oznacava fiktivna aktivnost?

    • Isprekidanom linijom

    • Kao krug

    • Kao vektor

    Correct Answer
    A. Isprekidanom linijom
    Explanation
    Fiktivna aktivnost se grafički označava isprekidanom linijom. This means that a fictitious activity is represented by a dashed line in a graphical representation.

    Rate this question:

  • 3. 

    Elementi procesa komuniciranja: 1. _________ 2. poruka 3. medij 4. primalac

    • Rukovodilac nižeg sloja

    • Komunikator

    • Rukovodilac viseg nivoa

    Correct Answer
    A. Komunikator
    Explanation
    The correct answer is "komunikator". In the process of communication, the "komunikator" refers to the person or entity that initiates or carries out the communication. They are responsible for encoding and transmitting the message to the receiver through a chosen medium. The "komunikator" plays a crucial role in ensuring effective communication by selecting appropriate language, tone, and delivery method to convey the intended message to the receiver.

    Rate this question:

  • 4. 

    Fiktivna aktivnost se graficki predstavlja

    • Kao krug

    • Kao vektor

    • Ne znam

    • Isprekidanom linijom

    Correct Answer
    A. Isprekidanom linijom
    Explanation
    The correct answer is "Isprekidanom linijom". A dashed line is commonly used to represent a fictitious activity in graphical representations, such as charts or diagrams. This type of line helps to differentiate the fictitious activity from other activities and clearly indicates that it is not a real or tangible action.

    Rate this question:

  • 5. 

    Kod samoupravnih timova odgovornost i autoritet se:

    • Sa rukovodioca prenosi na vrhovno menadžment

    • Sa rukovodioca prenos na vlasnike kompanija

    • Sa rukovodioca prenosi na članove tima

    Correct Answer
    A. Sa rukovodioca prenosi na članove tima
    Explanation
    The correct answer is "sa rukovodioca prenosi na članove tima" which translates to "the responsibility and authority are transferred from the manager to the team members." This suggests that in self-managing teams, the manager delegates their power and decision-making authority to the members of the team, allowing them to take ownership and responsibility for their tasks and actions.

    Rate this question:

  • 6. 

    Zaokruziti tacnu trvrdnju

    • Ni jedna od opcija nije tacna

    • Rezultat tima premasuje pojedinacne rezultate

    • Rezultat tima uvek je manji od od pojedinacnih rezultata

    • Ne znam

    Correct Answer
    A. Rezultat tima premasuje pojedinacne rezultate
    Explanation
    The correct answer is "Rezultat tima premasuje pojedinacne rezultate" which translates to "The team's result exceeds individual results." This statement suggests that the team's performance is better than the individual performances.

    Rate this question:

  • 7. 

    Kod samoupravnih timova odgovornost i autoritet se

    • Sa rukovodioca prenosi na vrhovni menadzment

    • Sa rukovodioca prenosi na vlasnike kompanija

    • Sa rukovodioca prenosi na clanove tima

    Correct Answer
    A. Sa rukovodioca prenosi na clanove tima
    Explanation
    The correct answer is "sa rukovodioca prenosi na clanove tima." In self-managed teams, responsibility and authority are transferred from the manager to the team members. This means that team members have the autonomy to make decisions and take ownership of their work, rather than relying on a manager for guidance and direction. This fosters a sense of empowerment and accountability within the team, allowing for more efficient and effective decision-making processes.

    Rate this question:

  • 8. 

    Klasičan pristup upravljanja projektom poznaje tri osnovne vreste organizacije 1. Projektnu 2. Matričnu 3. ________

    • Ekspeditivnu

    • Finansijsku

    • Funcionalnu

    Correct Answer
    A. Funcionalnu
    Explanation
    The correct answer is "funcionalnu." The classical approach to project management recognizes three basic types of organization: project, matrix, and functional.

    Rate this question:

  • 9. 

    Dogadjaj se graficki predstavlja kao 

    • Ne znam

    • Kao krug

    • Kao vektor

    • Isprekidanom linijom

    Correct Answer
    A. Kao krug
    Explanation
    A događaj se graficki predstavlja kao krug. Ova reprezentacija se često koristi kako bi se vizualno prikazao događaj ili aktivnost na vremenskoj skali. Krug može predstavljati početak i kraj događaja, a njegova veličina može ukazivati na trajanje ili važnost događaja. Ova reprezentacija je jasna i lako razumljiva, što je čini popularnom među dizajnerima i korisnicima.

    Rate this question:

  • 10. 

    Događaj se grafički predstavlja kao:

    • Krug

    • Vektor

    • Isprekidana Linija

    Correct Answer
    A. Krug
    Explanation
    The event is represented graphically as a circle.

    Rate this question:

  • 11. 

    Projekat predstavlja:

    • Određeni posao koji treba da se završi u budućnosti, ograničen resursima i troškovima

    • Određeni posao koji treba da se završi u budućnosti, ograničen vremenom, resursima i troškovima

    • Određeni posao koji treba da se završi u budućnosti, ograničen vremenom, troskovima

    Correct Answer
    A. Određeni posao koji treba da se završi u budućnosti, ograničen vremenom, resursima i troškovima
    Explanation
    The correct answer is "Određeni posao koji treba da se završi u budućnosti, ograničen vremenom, resursima i troškovima." This answer accurately describes a project as a specific task that needs to be completed in the future, with limitations in terms of time, resources, and costs.

    Rate this question:

  • 12. 

    Procene vremena trajanja aktivnosti kod PERT metode  vrsi se na osnovu

    • Sve od navedenog

    • Option 2

    • Option 3

    • Option 4

    Correct Answer
    A. Sve od navedenog
    Explanation
    The correct answer is "Sve od navedenog" which means "All of the above" in English. This suggests that the estimates of activity duration in PERT method are based on multiple factors or options, including Option 2, Option 3, and Option 4. Without knowing the specific options mentioned in the question, it is difficult to provide a more detailed explanation.

    Rate this question:

  • 13. 

    Skracenica OBS predstavlja

    • Organization Breakup Structure

    • Organization Breakdown System

    • Organization Breakdown Structure

    • Organization Breakup System

    Correct Answer
    A. Organization Breakdown Structure
    Explanation
    The correct answer is "Organization Breakdown Structure." An organization breakdown structure is a hierarchical representation of an organization's resources, responsibilities, and reporting relationships. It breaks down the organizational structure into smaller components, such as departments, teams, or individuals, to provide a clear understanding of how the organization is structured and how tasks are allocated. This helps in organizing and managing projects, as well as facilitating communication and coordination within the organization.

    Rate this question:

  • 14. 

    Prema klasicnom pristupu upravljanja projektom osnovne vrste organizacije su:funkcionlana, matricna

    • Proizvodna

    • Ne znam

    • Planska

    • Projektna

    Correct Answer
    A. Projektna
    Explanation
    The correct answer is "Projektna." In classical project management approach, the basic types of organizational structures are functional, matrix, and project. Among these, the project organizational structure is characterized by organizing the company around projects, where teams are formed specifically for each project and have dedicated resources. This structure allows for better coordination and control over project activities, as well as efficient utilization of resources.

    Rate this question:

  • 15. 

    Skracenica WBS predstavlja

    • Work Breakdown System

    • Work Breakup Structure

    • Work Breakdown Structure

    • Work Breakup System

    Correct Answer
    A. Work Breakdown Structure
    Explanation
    The correct answer is "Work Breakdown Structure." WBS is a project management tool that breaks down a project into smaller, manageable components called work packages. It provides a hierarchical structure that defines the scope of work, tasks, and deliverables required to complete a project. WBS helps in organizing and planning project activities, assigning responsibilities, estimating resources, and tracking progress. It is an essential tool for effective project management and communication within a team.

    Rate this question:

  • 16. 

    Od svih elemenata realizacije projekta, oivodicemo tri koje cine osnovni sadrzaj promena u projektu, a to su vreme, troskovi i _________

    Correct Answer
    resursi
    Explanation
    The given question is asking for the missing element that constitutes the basic content of changes in a project, along with time and costs. The correct answer is "resursi" which translates to "resources" in English. This suggests that resources play a crucial role in implementing and managing project changes, alongside time and costs.

    Rate this question:

  • 17. 

    WBS dijagram (Work Breakdown Structure) predstavlja:

    • Poslove izadatke koje treba uraditi da bi se zavrčilo veći deo projekta

    • Poslove izadatke koje treba uraditi da bi se završio jedan deo projekta

    • Poslove izadatke koje treba uraditi da bi se završio projekat u celini

    Correct Answer
    A. Poslove izadatke koje treba uraditi da bi se završio projekat u celini
    Explanation
    The correct answer is "poslove izadatke koje treba uraditi da bi se završio projekat u celini." This means that the WBS diagram represents the tasks that need to be completed in order to finish the entire project. It breaks down the project into smaller, manageable tasks that need to be accomplished in order to achieve the overall project goal.

    Rate this question:

  • 18. 

    Glavne karakteristike neefikasnog tima su:

    • Frustracija, konflikt i nezdrava konkurencija, neproduktivni sastanci, nedostatak poverenja u vođu tima

    • Podeljena odgovornost, konflikt i nezdrava konkurencija, neproduktivni sastanci, nedostatak poverenja u vođu tima

    • Konflikt i nezdrava konkurencija, neproduktivni sastanci, nedostatak poverenja u vođu tima, mali borj članova tima

    Correct Answer
    A. Frustracija, konflikt i nezdrava konkurencija, neproduktivni sastanci, nedostatak poverenja u vođu tima
    Explanation
    The main characteristics of an inefficient team are frustration, conflict, unhealthy competition, unproductive meetings, and lack of trust in the team leader.

    Rate this question:

  • 19. 

    Karakteristike efikasnog tima su:

    • Mala veličina, komplementarne veštine, zajednički cilj, specifični ciljevi, pojedinačni pristup, zajednička odgovornost

    • Mala veličina, komplementarne veštine, zajednički cilj, specifični ciljevi, zajednički pristup, zajednička odgovornost

    • Mala veličina, komplementarne veštine, zajednički cilj, specifični ciljevi, pojedinačna odgovornost

    Correct Answer
    A. Mala veličina, komplementarne veštine, zajednički cilj, specifični ciljevi, zajednički pristup, zajednička odgovornost
    Explanation
    The characteristics of an efficient team include small size, complementary skills, a common goal, specific objectives, a collective approach, and shared responsibility. These qualities contribute to effective collaboration, clear focus, and a sense of accountability among team members.

    Rate this question:

  • 20. 

    Vrste tehnike mreznog planiranja su 

    • EPS i OBS

    • EPS i PERT

    • CPM i EPS

    • CPM i PERT

    • Ne znam

    Correct Answer
    A. CPM i PERT
    Explanation
    CPM (Critical Path Method) and PERT (Program Evaluation and Review Technique) are both techniques used in network planning. CPM is a method that helps in identifying the critical path, which is the longest sequence of dependent activities that determines the project's duration. PERT, on the other hand, is a probabilistic technique that considers the uncertainty in activity durations to estimate project completion time. Therefore, the correct answer is CPM i PERT, as both techniques are used in network planning.

    Rate this question:

  • 21. 

    Usiljeno vreme trajanja aktivnosti je:

    • Najmanje vreme trajanja, koje podrazumeva najbrži rad i angažovanje sredstva

    • Vreme trajanja jednako normalnom vremenu trjanaja aktivnosti, koje podrazumeva najbrzi rad i angazovanje sredstava

    • Najduze vreme trajanja, koje podrazumeva trajanje rada i angazovanje sredstava u skladu sa tipom projekta

    Correct Answer
    A. Najmanje vreme trajanja, koje podrazumeva najbrži rad i angažovanje sredstva
    Explanation
    The correct answer is "Najmanje vreme trajanja, koje podrazumeva najbrži rad i angažovanje sredstva". This means that the minimum duration of an activity is the shortest amount of time required to complete the activity with the fastest possible work and resource utilization.

    Rate this question:

  • 22. 

    Načini komunikacije: Lični kontakti ___________ Korespondencija

    Correct Answer
    Sastanci, sastanci
    Explanation
    The missing phrase in the question is "Sastanci, sastanci." The phrase is repeated twice, indicating that meetings are an important form of communication. Therefore, the correct answer is "Meetings, meetings." This suggests that meetings play a significant role in communication alongside personal contacts and correspondence.

    Rate this question:

  • 23. 

    Mrežni modeli predstavljaju

    • Grafički prikaz resursnog prikaza odvijanja poslovnog poduhvata koji čini jednu zaokruzenu celinu

    • Grafički prikaz troškovnog prikaza odvijanja poslovnog poduhvata koji čini jednu zaokruzenu celinu

    • Grafički prikaz tehnološkog i vremenskog odvijanja poslovnog poduhvata koji čini jednu zaokruzenu celinu

    Correct Answer
    A. Grafički prikaz tehnološkog i vremenskog odvijanja poslovnog poduhvata koji čini jednu zaokruzenu celinu
    Explanation
    The correct answer is "Grafički prikaz tehnološkog i vremenskog odvijanja poslovnog poduhvata koji čini jednu zaokruženu celinu". This answer describes network models as a graphical representation of the technological and temporal flow of a business endeavor that constitutes a cohesive whole.

    Rate this question:

  • 24. 

    Najraniji pocetak aktivnosti predstavlja

    • Vremensku koordinatu na kojoj jedna aktivnost mora poceti

    • Vremensku koordinatu na kojoj jedna aktivnost najranije moze poceti

    • Vremensku koordinatu na kojoj se najranije mora poceti sa planiranjem te aktivnosti

    • Ne znam

    Correct Answer
    A. Vremensku koordinatu na kojoj jedna aktivnost najranije moze poceti
    Explanation
    The correct answer is "vremensku koordinatu na kojoj jedna aktivnost najranije može početi." This means that the earliest possible time at which an activity can start is being referred to.

    Rate this question:

  • 25. 

    Sa aspekta vremena trajanja, finansije i utrosaka resursa projekti mogu bitiInvesticioniBiznic_______

    • Ne znam

    • Razvojni

    • Medijski

    • Drustveni

    Correct Answer
    A. Drustveni
    Explanation
    From the given options, the correct answer is "drustveni" which translates to "social" in English. This suggests that projects can be categorized as either investment, business, or social projects based on the aspect of time duration, finances, and resource consumption.

    Rate this question:

  • 26. 

    Aktivnost se graficki predstavlja kao 

    • Krug

    • Vektor

    • Ne znam

    • Isprekidanom linijom

    Correct Answer
    A. Vektor
    Explanation
    The correct answer is "vektor". In graphical representation, an activity is often depicted as a vector because it represents both the magnitude and direction of the activity. A vector can be represented by an arrow, where the length of the arrow represents the magnitude of the activity and the direction of the arrow represents the direction of the activity. This allows for a clear and concise representation of the activity in a graphical form.

    Rate this question:

  • 27. 

    Glavne aktivnosti neefikasnig tima su

    • Podeljena odgovornost, konflikti i nezdrava konkurencija, neprodiktivni sastanci, nedostatak poverenja u vodju tima

    • Konflikt i nezdrava konkurencija, neproduktivni sastanci, nedostatak povrenja u vodju tima, mali broj clanova tima

    • Frustracija, konflikt i nezdrava konkurencija, neproduktivni statsnci, nedostatak poverenja u vodju tima

    Correct Answer
    A. Frustracija, konflikt i nezdrava konkurencija, neproduktivni statsnci, nedostatak poverenja u vodju tima
    Explanation
    The main activities of an inefficient team include frustration, conflicts, unhealthy competition, unproductive meetings, and lack of trust in the team leader.

    Rate this question:

  • 28. 

    Kritični put je:

    • Zbir vremena trajanja kritičnih aktivnosti i predstavlja najduzi put.

    • Zbir vremena trajanja kritičnih aktivnosti I predstavlja najkraci put.

    • Zbir vremena trajanja kritičnih aktivnosti I predstavlja optimalni put.

    Correct Answer
    A. Zbir vremena trajanja kritičnih aktivnosti i predstavlja najduzi put.
    Explanation
    The correct answer states that the critical path is the sum of the durations of critical activities and represents the longest path. This means that the critical path is the sequence of activities that must be completed in order to complete the project in the shortest amount of time. By summing the durations of these critical activities, we can determine the total time required to complete the project.

    Rate this question:

  • 29. 

    Podela procesa upravljanja preduzećem ima za cilj:

    • Da olakša upravljanje celokupnim sistemom pri čemu se ne obraća paznja na povezanost pojedinačnih procesa

    • Da olakša upravljanje celokupnim sistemom pri čemu se ne gubi iz vida međusobna povezanost pojedinačnih procesa

    • Da olakša upravljanje celokupnim sistemom pri čemu se ipak gubi iz vida međusobna povezanost pojedinačnih procesa

    Correct Answer
    A. Da olakša upravljanje celokupnim sistemom pri čemu se ne gubi iz vida međusobna povezanost pojedinačnih procesa
    Explanation
    The correct answer suggests that the purpose of dividing the management process is to facilitate the management of the entire system while still maintaining the interconnectedness of individual processes. This means that while managing the system as a whole, the interdependencies and relationships between individual processes are not overlooked.

    Rate this question:

  • 30. 

    Zaokruzi tacnu tvrdnju

    • Rukovodilac projekta ne ucestvuje u njegovoj realizaciji vec njome upravlja

    • Rukovodilac projekta ucestvuje u njegovoj realizaciji vec njome upravlja

    • Rukovodilac projekta ucestvuje u njegovoj realizaciji vec njome ne upravlja

    • Ne znam

    Correct Answer
    A. Rukovodilac projekta ne ucestvuje u njegovoj realizaciji vec njome upravlja
    Explanation
    The correct answer is "Rukovodilac projekta ne ucestvuje u njegovoj realizaciji vec njome upravlja." This statement suggests that the project manager does not directly participate in the execution of the project tasks but rather manages and oversees the process. This implies that the project manager's role is to provide guidance, allocate resources, make decisions, and ensure that the project is progressing according to plan.

    Rate this question:

  • 31. 

    Kriticni put je

    • Zbir vremena trajanja kriticnih aktivnosti i predstavlja najduzi put

    • Zbir vremena trajanja kriticnih aktivnosti i predstavlja najkraci put

    • Zbir vremena trajanja kriticnih aktivnosti i predstavlja optimalni put put

    • Ne znam

    Correct Answer
    A. Zbir vremena trajanja kriticnih aktivnosti i predstavlja najduzi put
    Explanation
    The correct answer is "zbir vremena trajanja kriticnih aktivnosti i predstavlja najduzi put." This is because the critical path is the longest path in a project network diagram, which represents the sequence of activities that must be completed in order to finish the project in the shortest possible time. The critical path is determined by adding up the durations of all critical activities, which are those that have zero slack or float time.

    Rate this question:

  • 32. 

    Tehnika mrznog planiranja 

    • Ne znam

    • Ne resava i ne otkriva probleme tokom realizacije projekta

    • resava i ne otkriva probleme tokom realizacije projekta

    • Ne resava ali otkriva probleme tokom realizacije projekta

    Correct Answer
    A. Ne resava ali otkriva probleme tokom realizacije projekta
    Explanation
    Tehnika mrznog planiranja does not solve problems during project implementation but it does reveal them.

    Rate this question:

  • 33. 

    Kad je nastao koncept upravljanja projektom

    • 60-ih u SAD

    • 70-ih u SAD

    • 50-ih u SAD

    • Ne znam

    Correct Answer
    A. 50-ih u SAD
    Explanation
    The concept of project management originated in the 1950s in the United States. During this time, there was a growing need for effective management and coordination of complex projects, especially in industries such as construction, engineering, and defense. The development of project management as a formal discipline can be attributed to the increasing complexity and scale of projects, as well as advancements in technology and organizational theories. This led to the establishment of project management methodologies, frameworks, and tools that are widely used today.

    Rate this question:

  • 34. 

    Prema terminologiji tehnike mreznog planiranja, projekat predstavlja

    • Oderedjen posao koji treba da se zavrsi u buducnosti, ogranicen resursima i troskovima

    • Oderedjen posao koji treba da se zavrsi u buducnosti, ogranicen vremenom, resursima i troskovima

    • Oderedjen posao koji treba da se zavrsi u buducnosti, ogranicen vremenom i troskovima

    • Option 4

    Correct Answer
    A. Oderedjen posao koji treba da se zavrsi u buducnosti, ogranicen vremenom, resursima i troskovima
    Explanation
    The correct answer is "oderedjen posao koji treba da se zavrsi u buducnosti, ogranicen vremenom, resursima i troskovima". This answer accurately describes a project in the terminology of network planning. A project is a specific task that needs to be completed in the future, with limitations on time, resources, and costs.

    Rate this question:

  • 35. 

    Koncept upravljanja projektom

    • Se primenuje samo kod investicionih projekata

    • Se primenuje samo kod drustvenih projekata

    • Ne znam

    • Se primenuje samo kod biznis projekata

    • Se primenuje u svim vrstama projekata

    Correct Answer
    A. Se primenuje u svim vrstama projekata
    Explanation
    The correct answer is "se primenuje u svim vrstama projekata" which means "it is applied in all types of projects." This means that the concept of project management is not limited to a specific type of project, but can be used in various fields such as investment projects, social projects, and business projects. Project management principles and techniques can be applied to ensure successful planning, execution, and control of projects regardless of their nature or industry.

    Rate this question:

  • 36. 

    Optimisticko vreme predstavlja

    • Najkrace procenjeno vreme za realizaciju aktivnsti pod izuzetno lakim uslovima

    • Ne znam

    • Najduze procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima

    • Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima

    Correct Answer
    A. Najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima
    Explanation
    The correct answer is "najkrace procenjeno vreme za realizaciju aktivnosti pod izuzetno teskim uslovima." This answer aligns with the given definition of "optimisticko vreme," which means the shortest estimated time for completing an activity under extremely difficult conditions.

    Rate this question:

  • 37. 

    Aktivnost se grafički predstavlja:

    • Kao Vektor

    • Kao krug

    • Isprekidanom linijom

    Correct Answer
    A. Kao Vektor
    Explanation
    The correct answer is "Kao Vektor" because vector graphics are used to represent images or activities. Vector graphics use mathematical equations to define shapes and lines, allowing for scalability without losing image quality. This makes them ideal for representing activities as they can be easily resized and manipulated without distortion.

    Rate this question:

  • 38. 

    Lekic je tata smera  :) ;) ;)

    • True

    • False

    Correct Answer
    A. True
    Explanation
    The given statement "Lekic je tata smera :) ;) ;)" translates to "Lekic is the father of the direction :) ;) ;)". Since this statement doesn't provide any indication of whether it is true or false, it can be considered an opinion or a joke. Therefore, the answer "True" is not a valid response as it cannot be determined from the given statement.

    Rate this question:

  • 39. 

    Elementi mrežnog dijagrama su:

    • Projekat, aktivnost, događaj

    • Aktivnost, trajanje, resursi

    • Projekat, resursi, materijal

    Correct Answer
    A. Projekat, aktivnost, događaj
    Explanation
    The elements of a network diagram are project, activity, and event. A network diagram is a graphical representation of the project schedule, showing the logical relationships between activities. The project represents the overall objective or goal, while activities are the individual tasks or actions that need to be completed to achieve the project's objectives. Events, on the other hand, are points in time that signify the start or completion of activities. Therefore, the correct answer is "Projekat, aktivnost, događaj."

    Rate this question:

  • 40. 

    Najraniji početak aktivnosti predstavlja:

    • Vremensku koordinatu na kojoj jedna aktivnost najranije može početi

    • Vremensku koordinatu na kojoj jedna aktivnost mora početi

    • Vremensku koordinatu na kojoj se najranije mora početi sa planiranjem te aktivnosti

    Correct Answer
    A. Vremensku koordinatu na kojoj jedna aktivnost najranije može početi
    Explanation
    The correct answer is "vremensku koordinatu na kojoj jedna aktivnost najranije može početi". This means that it represents the earliest possible time coordinate at which an activity can start. It does not imply that the activity must start at this time, but rather that it cannot start any earlier.

    Rate this question:

  • 41. 

    Optimističko vreme predstavlja:

    • Najkraće procenjeno vremem za realizaciju aktivnosti pod izuzetno lakim uslovima

    • Najduže vreme procenjeno za realizaciju aktivnosti pod izuzetno teškim uslovima

    • Najkraće procenjeno vreme za realizaciju aktivnosti pod izuzetno teškim uslovima

    Correct Answer
    A. Najkraće procenjeno vreme za realizaciju aktivnosti pod izuzetno teškim uslovima
    Explanation
    The term "optimističko vreme" in Serbian translates to "optimistic time" in English. In project management, optimistic time refers to the shortest estimated time for completing an activity under extremely difficult conditions. This means that despite the challenging circumstances, the optimistic time assumes that everything will go smoothly and there will be no delays or obstacles. It represents an ideal scenario where all conditions are favorable and the activity can be completed in the shortest possible time.

    Rate this question:

  • 42. 

    Osnovne karakteristike investicionih projekata su 

    • Dugotrajni

    • Veliki broj ucesnika

    • Kratkotrajni

    • To su jenostavni projekti

    • Mali broj ucesnika

    • To su slozeni projekti

    Correct Answer(s)
    A. Dugotrajni
    A. Veliki broj ucesnika
    A. To su slozeni projekti
    Explanation
    Investicioni projekti su dugotrajni jer obično zahtevaju vreme za realizaciju i povrat uloženog kapitala. Takođe, oni uključuju veliki broj učesnika jer zahtevaju saradnju i angažovanje različitih strana, kao što su investitori, finansijske institucije, stručnjaci i radna snaga. Osim toga, investicioni projekti su često složeni jer obuhvataju različite faze, procese i aktivnosti koje zahtevaju stručnost i koordinaciju.

    Rate this question:

  • 43. 

    Usiljeno vreme trajanja aktivnosti je 

    • Najduze vreme trajanja, koje podrazumeva trajanja rada i nagazovanje sredstava u skladu sa tipom projekta

    • Najmanje vreme trajanja , koje podrazumeva najbrzi rad i nagazovanje sredstava

    • Vreme trajanja jednako normalnom vremenu trajanja aktivnosti, koje podrazumeva najbrzi rad i nagazovanje sredstava

    Correct Answer
    A. Najmanje vreme trajanja , koje podrazumeva najbrzi rad i nagazovanje sredstava
    Explanation
    The correct answer is "Najmanje vreme trajanja , koje podrazumeva najbrzi rad i nagazovanje sredstava". This answer states that the minimum duration of an activity involves the fastest work and utilization of resources. This means that the activity will be completed in the shortest possible time, with the most efficient use of resources.

    Rate this question:

  • 44. 

    Neke od potrebnih osobina i sposobnosti rukovodioca projekta su:

    • Organizatorske i upravljačke sposobnosti

    • Organizatorske i upravljačke sposobnosti ali ne i komunikacione sposobnosti

    • Organizatorske i komunikacione sposobnosti ali ne i upravljacke sposobnosti

    Correct Answer
    A. Organizatorske i upravljačke sposobnosti
    Explanation
    The correct answer is "Organizatorske i upravljačke sposobnosti". This answer implies that the necessary qualities and abilities of a project manager include both organizational and managerial skills. These skills are essential for effectively planning, coordinating, and overseeing the various aspects of a project.

    Rate this question:

  • 45. 

    Faze komuniciranja: 1. slanje poruka 2.____________ 3. primanje 4. tumačenje i razumevanje poruke

    • Dekodiranje

    • Filtriranje

    • Kodiranje

    Correct Answer
    A. Filtriranje
    Explanation
    The correct answer is "filtriranje" because it fits logically in the sequence of steps in the communication process. After sending a message, the next step would involve filtering or sorting through the received messages to determine which ones are relevant or important. This step is necessary to effectively interpret and understand the message.

    Rate this question:

  • 46. 

    Mrezni modeli predstavljaju

    • Graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzeni celinu

    • Graficki prikaz troskovnog prikaza odvijanja poslovnog poduhvata koji cini jednu zaokruzeni celinu

    • Graficki prikaz resursnog prikaza odvijanja poslovnog poduhvata koji cini jednu zaokruzeni celinu

    • Ne znam

    Correct Answer
    A. Graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzeni celinu
    Explanation
    The correct answer is "graficki prikaz tehnoloskog i vremenskog odvijanja poslovnog poduhvata koji cini jednu zaokruzeni celinu" which translates to "a graphical representation of the technological and temporal development of a business venture that constitutes a complete whole." This answer suggests that process models represent the chronological and technological aspects of a business project in a graphical format. It emphasizes that these models provide a comprehensive overview of the project's progress and activities.

    Rate this question:

  • 47. 

    Vrste timova po YukluFunkcionalanMultifuncionalan_____________Samodefinisuci

    • Samoupravni

    • Ne znam

    • Produktivni

    • SAmoprojektni

    Correct Answer
    A. Samoupravni
    Explanation
    The given options are different types of teams according to Yukl. The correct answer, "Samoupravni," refers to self-managed teams. These teams have the authority and responsibility to make decisions and manage their own work processes. They are empowered to set their own goals, solve problems, and make decisions without constant supervision. This type of team structure promotes autonomy, accountability, and collaboration among team members.

    Rate this question:

  • 48. 

    Vremenski zazor je:

    • Razlika između raspolozivog vremena i vremena trajanja aktivnosti

    • Razlika između najkasnije početka aktivnosti i vremena trajanja aktivnosti

    • Razlika između optimalnog vremena i vremena trajanja aktivnosti

    Correct Answer
    A. Razlika između raspolozivog vremena i vremena trajanja aktivnosti
    Explanation
    The correct answer is "Razlika između raspoloživog vremena i vremena trajanja aktivnosti". This answer suggests that the time buffer is the difference between the available time and the duration of the activity. In other words, it refers to the extra time that is available beyond what is required to complete the activity.

    Rate this question:

  • 49. 

    Procedure predstavljaju dokumenta u kojima su:

    • Prikazani svrha i predmet aktivnosti, kao i način njihovog obavljanja

    • Prikazani svrha i predmet aktivnosti ali ne i način njihovog obavljanja

    • Prikazani svrha ali ne i predmet aktivnosti

    Correct Answer
    A. Prikazani svrha i predmet aktivnosti, kao i način njihovog obavljanja
    Explanation
    The given correct answer states that procedures represent documents in which the purpose and subject of activities are presented, as well as the way in which they are performed. This means that procedures provide information about both the goal and scope of the activities, as well as the specific steps or methods that should be followed to accomplish them.

    Rate this question:

Quiz Review Timeline (Updated): Mar 21, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 03, 2016
    Quiz Created by
    Lekicaleksandar8
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.