Test Execution And Closure

25 Questions | Total Attempts: 2738

SettingsSettingsSettings
Please wait...
Test Execution Quizzes & Trivia

Questions and Answers
  • 1. 
    The impact of the defect in the software is called _________
    • A. 

      Regression Testing

    • B. 

      Severity

    • C. 

      Priority

    • D. 

      None of the above

  • 2. 
    A non-critical incident, affecting a single user and the ability to provide the best service but there is a workaround.
    • A. 

      Showstopper

    • B. 

      High

    • C. 

      Medium

    • D. 

      Low

  • 3. 
    Priority of a defect is better determined by
    • A. 

      Tester

    • B. 

      Test Lead

    • C. 

      Delivery Manager

    • D. 

      Project Manager

  • 4. 
    When you logging the defect which of the following should be considered(choose the correct)
    • A. 

      Capture screenshot of the defect

    • B. 

      Defect status

    • C. 

      Test data used to identify the defect

    • D. 

      Version of the build in which the defect is identified

    • E. 

      Test environment details in which the defect occurred

  • 5. 
    A defect triage meeting happens every day during ____________
    • A. 

      Test closure

    • B. 

      Execution

  • 6. 
    The traceability matrix created during the requirements analysis and the test design phase is updated with the defect details
    • A. 

      True

    • B. 

      False

  • 7. 
    The status of the defect is changed to ___________ and is assigned to the developer if the application does not behave as desired, even after the fix.
    • A. 

      Open

    • B. 

      Re-open

    • C. 

      Closed

    • D. 

      None of these

  • 8. 
    Go / No Go decision is taken in
    • A. 

      Daily execution report

    • B. 

      Test summary report

    • C. 

      End of test report

    • D. 

      None of the above

  • 9. 
    % of  test cases executed = (No. of test cases executed/Total number of test cases written) * 100
    • A. 

      True

    • B. 

      False

  • 10. 
    Age of the defects is the
    • A. 

      Number and details of the defect grouped by the priority of the defect

    • B. 

      Number and the details of the defects grouped by the number of days it took to close a defect since then it was open

    • C. 

      Number and details of the defects in each module of the application

    • D. 

      Number and the details of the defects grouped by the status of the defect

  • 11. 
    Who will take decision to go the UAT
    • A. 

      Dev Manager

    • B. 

      Client

    • C. 

      Tester

    • D. 

      None of these

  • 12. 
    Which tracker is used for down times
    • A. 

      Down Time tracker

    • B. 

      Environment checklist

    • C. 

      Defect tracker

    • D. 

      None of these

  • 13. 
    What is need to validate if all the agreed activities within the scope of testing are completed successfully as per the Test Plan
    • A. 

      Test Execution

    • B. 

      Test Closure

    • C. 

      Test Strategy

    • D. 

      Defect Log

  • 14. 
    The test summary report is prepared after the completion of
    • A. 

      Test Execution

    • B. 

      Test Closure

    • C. 

      Test Log

    • D. 

      Defect Log

  • 15. 
    Criteria for determining the stability of the application a. Test Coverage Factor b. Test Case Success Factor c. Outstanding Defects Factor d. Failed Test Case Impact Factor e. Non Coverage Risk Factor
    • A. 

      A and b

    • B. 

      A, b and c

    • C. 

      Only d

    • D. 

      A, b, c, d and e

  • 16. 
    Test case success factor determines the amount of passed test cases that are executed. It can be calculated using the formula for
    • A. 

      Test Pass Percentage

    • B. 

      Test Coverage Ratio

    • C. 

      Test Fail Percentage

    • D. 

      Test cases executed

  • 17. 
    If the dependency test case is  failed, what will be the test case run status
    • A. 

      No Run

    • B. 

      Blocked

    • C. 

      Not completed

    • D. 

      Failed

  • 18. 
    If the Build Verification Test is passed with the desired results, build will be accepted the testing team will proceed with
    • A. 

      Test Log

    • B. 

      Test Execution

    • C. 

      Test Closure

    • D. 

      All the above

  • 19. 
    Process of test execution involves, (choose the correct)
    • A. 

      Review

    • B. 

      Defect triaging

    • C. 

      Generation of test script

    • D. 

      Test environment set up

  • 20. 
    In database set up the test environment should be as close to the production environment in terms of (choose the correct)
    • A. 

      Database set up

    • B. 

      Levels of users defined and the number of users defined for each level

    • C. 

      Volume of data in the database

    • D. 

      Type of documents

  • 21. 
    The number of rounds the testing will be conducted and the scope of testing at each level need   to be identified in the test plan and agreed upon by all the stake holders.
    • A. 

      Test case review

    • B. 

      Test case sign off

    • C. 

      Test cycles

    • D. 

      None of these

  • 22. 
    ___________ is an activity to check whether all the project related activities, starting from initiation till release or implementation, are performed for a particular project.
    • A. 

      Test Closure

    • B. 

      Test Report

    • C. 

      Summary Report

    • D. 

      Project Closure

  • 23. 
    The root causes for the leakage of the defects from one phase to another are identified using the techniques
    • A. 

      Fishbone Diagram

    • B. 

      Risk analysis

    • C. 

      80:20

    • D. 

      Peareto chart

  • 24. 
    _____________ is made based on the stability value and the outstanding defects count
    • A. 

      ‘Go / No-Go’ decision

    • B. 

      Overall System Stability

    • C. 

      Factor Weightage

    • D. 

      None of these

  • 25. 
    When 'End of test' report has to be sent
    • A. 

      As soon as it is ready

    • B. 

      Weekly once

    • C. 

      Depends on the test plan

    • D. 

      When the client asks for it