Practice Management And Law

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Jaryng
J
Jaryng
Community Contributor
Quizzes Created: 3 | Total Attempts: 7,631
Questions: 14 | Attempts: 82

SettingsSettingsSettings
Practice Management And Law - Quiz


Questions and Answers
  • 1. 

    Who are  the members that make up the design team?

    • A.

      Client

    • B.

      Architect

    • C.

      Contractor

    • D.

      Structural Engineer

    • E.

      Quantity Surveyor

    • F.

      Building Services Engineer

    Correct Answer(s)
    A. Client
    B. Architect
    D. Structural Engineer
    E. Quantity Surveyor
    F. Building Services Engineer
    Explanation
    The members that make up the design team are the client, architect, structural engineer, quantity surveyor, and building services engineer. The client is the person or organization for whom the project is being designed. The architect is responsible for designing the overall concept and aesthetics of the project. The structural engineer ensures that the design is structurally sound and can withstand the required loads. The quantity surveyor estimates and manages the project costs. The building services engineer designs the mechanical, electrical, and plumbing systems of the building.

    Rate this question:

  • 2. 

    Who are the parties in the standard building contract?

    • A.

      The contractor and the architect

    • B.

      The client (employer) and the contractor

    • C.

      The client (employer) and the architect

    Correct Answer
    B. The client (employer) and the contractor
    Explanation
    The parties in a standard building contract are the client (employer) and the contractor. The client is the individual or organization that is responsible for initiating the construction project and will ultimately own the completed building. The contractor, on the other hand, is the party responsible for carrying out the construction work according to the specifications and requirements set by the client. They are typically hired by the client through a bidding or negotiation process. The architect, although important in the design and planning stages of the project, is not a direct party to the contract between the client and the contractor.

    Rate this question:

  • 3. 

    In the case of a simple contract, the period of limitation - i.e. the time period in which the remedies available for breach can be appliead - extends for __ years from the time of the breach.

    Correct Answer
    6
    six
    Explanation
    The period of limitation for a simple contract refers to the time period within which the remedies for breach can be applied. In this case, the correct answer is 6 years or six years. This means that the injured party has a time frame of 6 years from the time of the breach to seek legal remedies for the breach of the contract. After this period, the injured party may lose the right to enforce the contract and claim damages.

    Rate this question:

  • 4. 

    In the case of a deed, the period of limitation - i.e. the time period in which the remedies available for breach can be appliead - extends for __ years from the time of the breach.

    Correct Answer
    12
    twelve
    Explanation
    The period of limitation for a deed refers to the time period within which the remedies for breach can be applied. In this case, the correct answer is "12" or "twelve" years. This means that if a breach occurs in relation to a deed, the injured party has a period of 12 years from the time of the breach to seek legal remedies.

    Rate this question:

  • 5. 

    Partnering is one of the procurement routes.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
    Explanation
    Partnering is not one of the procurement routes. Procurement routes refer to the different methods or approaches used to obtain goods or services. Partnering, on the other hand, is a collaborative approach where two or more parties work together in a long-term relationship to achieve mutual goals. While partnering may be used within a procurement route, it is not a procurement route itself. Therefore, the correct answer is false.

    Rate this question:

  • 6. 

    _________ is the omission to do something which a reasonable man, guided upon those considerations which normally regulate the conduct of human affairs (or the profession) would do, or doing something, which a prudent and reasonable man would not do.

    Correct Answer
    Negligence
    Explanation
    Negligence refers to the failure to perform an action that a reasonable person, guided by common sense and standard practices, would have done, or the performance of an action that a prudent and reasonable person would not have done. In other words, negligence involves a breach of duty where a person fails to exercise the level of care expected in a given situation. This can result in harm or injury to others and can lead to legal consequences.

    Rate this question:

  • 7. 

    A ______ is an agreement conferring rights and imposing obligations each upon the other, made between two or more parties which is binding law. 

    Correct Answer
    contract
    Explanation
    A contract is a legally binding agreement between two or more parties that confers rights and imposes obligations on each party involved. It is a formal agreement that is enforceable by law, and it outlines the terms and conditions that the parties must adhere to. Contracts are used in various situations, such as business transactions, employment agreements, and rental agreements, to ensure that all parties involved are aware of their rights and responsibilities.

    Rate this question:

  • 8. 

    At which stage is the design frozen?

    • A.

      D-Scheme Design

    • B.

      E-Detailed Design

    • C.

      F-Final Proposal

    • D.

      H-Tender Documentation

    Correct Answer
    B. E-Detailed Design
    Explanation
    The design is frozen at the E-Detailed Design stage. This stage involves creating detailed drawings and specifications for the design, which are then used for construction or implementation. Once the detailed design is finalized, any further changes or modifications to the design are discouraged or limited, hence the term "frozen". This ensures that the design is well-defined and ready for implementation without any major alterations.

    Rate this question:

  • 9. 

    What percentage of the fee should be invoiced at the tender stage?

    • A.

      50%

    • B.

      65%

    • C.

      70%

    • D.

      75%

    Correct Answer
    D. 75%
    Explanation
    At the tender stage, it is common practice to invoice 75% of the fee. This allows the client to have a clear understanding of the majority of the financial commitment required before proceeding with the project. Invoicing a higher percentage also ensures that the client is financially invested in the project and reduces the risk of potential cancellations or delays.

    Rate this question:

  • 10. 

    Who are the members of the consultant team?

    • A.

      Architect

    • B.

      Client

    • C.

      Quantity Surveyor

    • D.

      Structural Engineer

    • E.

      Building Services Engineer

    • F.

      Design Co-ordinator

    • G.

      Contractor

    • H.

      Planning Consultant

    • I.

      Landscape Consultant

    • J.

      Specialist Consultants

    Correct Answer(s)
    A. Architect
    C. Quantity Surveyor
    D. Structural Engineer
    E. Building Services Engineer
    F. Design Co-ordinator
    H. Planning Consultant
    I. Landscape Consultant
    J. Specialist Consultants
    Explanation
    The members of the consultant team include the Architect, Quantity Surveyor, Structural Engineer, Building Services Engineer, Design Co-ordinator, Planning Consultant, Landscape Consultant, and Specialist Consultants. These individuals have specific expertise and roles within the construction project, working together to ensure the successful planning, design, and execution of the project.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Oct 25, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • May 19, 2012
    Quiz Created by
    Jaryng
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.