PM in Practice Schedule MSP Week 7 assesses key project management skills, focusing on project control, task dependencies, and scheduling techniques. It evaluates understanding of crucial concepts like clear requirements, lag, milestones, fast-tracking, and mandatory dependencies.
Lag
Lead
Float
Slack
Rate this question:
Activities of zero duration
Significant events in the project lifecycle
Measures of acheivement for expenditures of money or time
Best utilized when denoting start and finish of all activities.
Rate this question:
Concurrent Engineering
Fast - tracking
Leveling
Crashing
Rate this question:
Discretionary
Soft
Preferential
Mandatory
Rate this question:
Resource Capabilities
The number of resources assigned to a task
Historical data if available
Overhead rates
Rate this question:
The schedule change control system
Change requests
The schedule management plan
Performance reports
Rate this question:
Scheduled start or completion of major deliverables and key events
Activity start and end dates
Expected durations
Dependencies
Rate this question:
The cost and time slope for each critical activity that can be expedited
The cost of additional resources to be added to the projects critical path
The time that will be saved in the overall schedule when tasks are expedited on the critical path
Three probabilistic time estimates of PERT for each critical path activity.
Rate this question:
Schedule baseline
Number of change requests
Difference between planned and actual events and activities
Technical baseline
Rate this question:
Master schedule
Budget
WBS
Gantt Chart
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
A team of resources that are all considered subject matter experts.
The amounts of specific resources that are scheduled for use on specific activities.
Assiging excessive resources to a project in order to increse costs
Assigning multiple resources to a task in order to expedite that task
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
General
Predecessor
Procurement
Resources
Rate this question:
File
Edit
View
Insert
Rate this question:
2 days
4 days
1 days
1 hour
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question:
True
False
Rate this question: