Operations Research MCQ Quiz!

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Juanahernande
J
Juanahernande
Community Contributor
Quizzes Created: 1 | Total Attempts: 2,150
Questions: 10 | Attempts: 2,150

SettingsSettingsSettings
Operations Research MCQ Quiz! - Quiz

Can you crack down all the questions of this "Operations Research MCQ Quiz!?" Try your luck, buddy! Operations research (OR) is meant by an analytical method that is used for problem-solving and decision-making that is also useful in the management of organizations. In operations research, problems have to be broken down into basic components, and then these problems are solved in defined steps by mathematical analysis. So, should we proceed with the quiz as you have understood the basics? Let's go!


Questions and Answers
  • 1. 

    CPM is:

    • A.

      Critical Project Management

    • B.

      Critical Path Management

    • C.

      Critical Path Method

    • D.

      Crash Project Method

    Correct Answer
    C. Critical Path Method
    Explanation
    The correct answer is Critical Path Method. CPM is a project management technique that helps in identifying the most critical tasks and determining the shortest possible duration to complete a project. It involves identifying the critical path, which is the longest sequence of dependent tasks that determines the project's overall duration. By focusing on the critical path, project managers can prioritize resources and activities to ensure timely completion of the project.

    Rate this question:

  • 2. 

    Which of these is not correct?

    • A.

      PERT is probabilistic in nature.

    • B.

      CPM is deterministic in nature.

    • C.

      CPM is event-oriented.

    • D.

      CPM and PERT use similar terminology but were developed independently.

    Correct Answer
    C. CPM is event-oriented.
    Explanation
    The given statement is true as CPM (Critical Path Method) is not event-oriented. CPM is a project management technique that focuses on determining the critical path, which is the longest sequence of activities that determines the project's duration. It does not explicitly consider events or milestones in its methodology. On the other hand, PERT (Program Evaluation and Review Technique) is event-oriented as it emphasizes the identification and sequencing of events or milestones in a project. Both CPM and PERT are project management techniques but differ in their approach and focus.

    Rate this question:

  • 3. 

    Point out what is not required While considering precedence relationships.

    • A.

      All the predecessor(s) of an activity should be focused on.

    • B.

      Only immediate predecessor(s) should be focussed on.

    • C.

      Redundant predecessors should be dropped.

    • D.

      Care must be taken that there is no logical fault in it as may result in the formation of a loop.

    Correct Answer
    A. All the predecessor(s) of an activity should be focused on.
    Explanation
    The correct answer is "redundant predecessors should be dropped." This means that while considering precedence relationships, it is important to eliminate any unnecessary or redundant predecessors. This is because including redundant predecessors can lead to confusion and potential logical faults, such as the formation of a loop in the project schedule. Therefore, it is crucial to focus only on the predecessors that are essential for determining the sequence of activities.

    Rate this question:

  • 4. 

    Mark the wrong statement.

    • A.

      The head event of activity also represents the tail event of its predecessor activity.

    • B.

      Nodes should be numbered in such a way that, for every activity, the initial node bears a lower number while the final node bears a higher number.

    • C.

      The event marking the start of an activity is called head event, and the event marking the end is termed a tail-event.

    • D.

      In drawing a network, it may happen that A precedes B, B precedes C, and C precedes A.

    Correct Answer
    D. In drawing a network, it may happen that A precedes B, B precedes C, and C precedes A.
    Explanation
    This statement is incorrect because it states that A precedes B, B precedes C, and C precedes A. This is not possible in a network diagram as it creates a loop, which is not allowed in project management. In a network diagram, activities should have a clear sequence and should not have circular dependencies.

    Rate this question:

  • 5. 

    It is known that in a project, activity 4-6 has a duration of six days and a total float of three days. The E and L times at node 4 are 8 and 11, respectively, while, at node 6, both are equal to 17. Which of the following is not a true statement about 4-6?

    • A.

      Its free float is three days.

    • B.

      Its independent float is 0.

    • C.

      It is a critical activity.

    • D.

      The ES of this activity is 8.

    Correct Answer
    C. It is a critical activity.
    Explanation
    The given information states that the E and L times at node 4 are 8 and 11, respectively, while at node 6, both are equal to 17. This means that the earliest start time (ES) of activity 4-6 is 8. Since the ES of the activity is provided, it implies that it is not a critical activity. Critical activities are those with zero float, meaning any delay in their completion will directly impact the project's overall duration. Therefore, the statement "It is a critical activity" is not true based on the given information.

    Rate this question:

  • 6. 

    Mark the wrong statement.

    • A.

      All activities on a critical path are critical activities.

    • B.

      A project network may have none, one, or more critical paths.

    • C.

      A delay in critical activity surely delays the completion of project.

    • D.

      Each critical activity has identical earliest and the latest start times.

    Correct Answer
    B. A project network may have none, one, or more critical paths.
    Explanation
    This statement is incorrect because a project network can only have one critical path. The critical path is the longest path in the network and determines the minimum time required to complete the project. Any delay in activities on the critical path will directly impact the project's completion time.

    Rate this question:

  • 7. 

    Pick the wrong relationship:

    • A.

      Interfering float = Total float – Free float

    • B.

      Total float =Free float + Independent float

    • C.

      Total float ≥ Free float ≥ Independent float

    • D.

      Free float = Total float – Head event slack

    Correct Answer
    A. Interfering float = Total float – Free float
    Explanation
    The given relationship "Interfering float = Total float – Free float" is incorrect because interfering float is a separate concept and is not equal to the difference between total float and free float.

    Rate this question:

  • 8. 

    Given, expected duration of project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days? Z       :   0.33           1.0Area  :   0.1293       0.3413

    • A.

      0.6293

    • B.

      0.8413

    • C.

      0.1587

    • D.

      0.3707

    Correct Answer
    C. 0.1587
    Explanation
    The answer is 0.1587 because the question is asking for the probability of not completing the project in 50 days. To find this probability, we need to calculate the area under the standard normal distribution curve to the left of the Z-score corresponding to 50 days. The Z-score can be calculated by subtracting the expected duration from the given time and dividing it by the standard deviation. In this case, the Z-score is (50-47)/√9 = 1. Therefore, the area to the left of the Z-score of 1 is 0.1587. This represents the probability of not completing the project in 50 days.

    Rate this question:

  • 9. 

    Given, expected duration of project = 47 days, variance = 9 days. Expected Time for Project Completion: 50 days Z       :   0.33           1.0Area  :   0.1293       0.3413 What is the probability of completing the project within three days more or less than the expected time?  

    • A.

      0.5000

    • B.

      0.6826

    • C.

      0.2586

    • D.

      0.3174

    Correct Answer
    B. 0.6826
    Explanation
    The answer is 0.6826 because the given information includes the expected duration of the project and the variance. The expected time for project completion is 50 days, and the variance is 9 days. By using this information, we can calculate the standard deviation, which is the square root of the variance. In this case, the standard deviation is approximately 3 days. The probability of completing the project within three days more or less than the expected time is equivalent to the probability of completing the project within one standard deviation of the expected time. According to the empirical rule, this probability is approximately 68.26%. Therefore, the correct answer is 0.6826.

    Rate this question:

  • 10. 

    Which of the following is not true about crashing?

    • A.

      Always focus on critical path and choose between critical activities only.

    • B.

      Crashing cost per day = (Crash cost – Normal cost) / (Normal time – Crash time).

    • C.

      Of all activities of the project, choose the activity with the least crashing cost.

    • D.

      If there are multiple the critical paths, crash them all.

    Correct Answer
    C. Of all activities of the project, choose the activity with the least crashing cost.
    Explanation
    The statement "Of all activities of the project, choose the activity with the least crashing cost" is not true about crashing. When crashing a project, the activity with the least crashing cost may not necessarily be the best choice. Instead, the focus should be on the critical path and choosing between critical activities only. The critical path is the sequence of activities that determines the project's overall duration, so it is important to prioritize these activities for crashing in order to minimize the project's duration.

    Rate this question:

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jul 10, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 06, 2018
    Quiz Created by
    Juanahernande
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.