Operations Research MCQ Quiz!

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Juanahernande
J
Juanahernande
Community Contributor
Quizzes Created: 1 | Total Attempts: 2,158
| Attempts: 2,158 | Questions: 10
Please wait...
Question 1 / 10
0 %
0/100
Score 0/100
1. CPM is:

Explanation

The correct answer is Critical Path Method. CPM is a project management technique that helps in identifying the most critical tasks and determining the shortest possible duration to complete a project. It involves identifying the critical path, which is the longest sequence of dependent tasks that determines the project's overall duration. By focusing on the critical path, project managers can prioritize resources and activities to ensure timely completion of the project.

Submit
Please wait...
About This Quiz
Operations Research MCQ Quiz! - Quiz

Can you crack down all the questions of this "Operations Research MCQ Quiz!?" Try your luck, buddy! Operations research (OR) is meant by an analytical method that is... see moreused for problem-solving and decision-making that is also useful in the management of organizations. In operations research, problems have to be broken down into basic components, and then these problems are solved in defined steps by mathematical analysis. So, should we proceed with the quiz as you have understood the basics? Let's go! see less

2. Given, expected duration of project = 47 days, variance = 9 days.
Expected Time for Project Completion: 50 days

Z       :   0.33           1.0
Area  :   0.1293       0.3413

What is the probability of completing the project within three days more or less than the expected time?    

Explanation

The answer is 0.6826 because the given information includes the expected duration of the project and the variance. The expected time for project completion is 50 days, and the variance is 9 days. By using this information, we can calculate the standard deviation, which is the square root of the variance. In this case, the standard deviation is approximately 3 days. The probability of completing the project within three days more or less than the expected time is equivalent to the probability of completing the project within one standard deviation of the expected time. According to the empirical rule, this probability is approximately 68.26%. Therefore, the correct answer is 0.6826.

Submit
3. Pick the wrong relationship:

Explanation

The given relationship "Interfering float = Total float – Free float" is incorrect because interfering float is a separate concept and is not equal to the difference between total float and free float.

Submit
4. Which of the following is not true about crashing?

Explanation

The statement "Of all activities of the project, choose the activity with the least crashing cost" is not true about crashing. When crashing a project, the activity with the least crashing cost may not necessarily be the best choice. Instead, the focus should be on the critical path and choosing between critical activities only. The critical path is the sequence of activities that determines the project's overall duration, so it is important to prioritize these activities for crashing in order to minimize the project's duration.

Submit
5. Point out what is not required While considering precedence relationships.

Explanation

The correct answer is "redundant predecessors should be dropped." This means that while considering precedence relationships, it is important to eliminate any unnecessary or redundant predecessors. This is because including redundant predecessors can lead to confusion and potential logical faults, such as the formation of a loop in the project schedule. Therefore, it is crucial to focus only on the predecessors that are essential for determining the sequence of activities.

Submit
6. It is known that in a project, activity 4-6 has a duration of six days and a total float of three days. The E and L times at node 4 are 8 and 11, respectively, while, at node 6, both are equal to 17.
Which of the following is not a true statement about 4-6?

Explanation

The given information states that the E and L times at node 4 are 8 and 11, respectively, while at node 6, both are equal to 17. This means that the earliest start time (ES) of activity 4-6 is 8. Since the ES of the activity is provided, it implies that it is not a critical activity. Critical activities are those with zero float, meaning any delay in their completion will directly impact the project's overall duration. Therefore, the statement "It is a critical activity" is not true based on the given information.

Submit
7. Given, expected duration of project = 47 days, variance = 9 days.
What is the
probability of not completing the project in 50 days?

Z       :   0.33           1.0
Area  :   0.1293       0.3413

Explanation

The answer is 0.1587 because the question is asking for the probability of not completing the project in 50 days. To find this probability, we need to calculate the area under the standard normal distribution curve to the left of the Z-score corresponding to 50 days. The Z-score can be calculated by subtracting the expected duration from the given time and dividing it by the standard deviation. In this case, the Z-score is (50-47)/√9 = 1. Therefore, the area to the left of the Z-score of 1 is 0.1587. This represents the probability of not completing the project in 50 days.

Submit
8. Mark the wrong statement.

Explanation

This statement is incorrect because it states that A precedes B, B precedes C, and C precedes A. This is not possible in a network diagram as it creates a loop, which is not allowed in project management. In a network diagram, activities should have a clear sequence and should not have circular dependencies.

Submit
9. Which of these is not correct?

Explanation

The given statement is true as CPM (Critical Path Method) is not event-oriented. CPM is a project management technique that focuses on determining the critical path, which is the longest sequence of activities that determines the project's duration. It does not explicitly consider events or milestones in its methodology. On the other hand, PERT (Program Evaluation and Review Technique) is event-oriented as it emphasizes the identification and sequencing of events or milestones in a project. Both CPM and PERT are project management techniques but differ in their approach and focus.

Submit
10. Mark the wrong statement.

Explanation

This statement is incorrect because a project network can only have one critical path. The critical path is the longest path in the network and determines the minimum time required to complete the project. Any delay in activities on the critical path will directly impact the project's completion time.

Submit
View My Results

Quiz Review Timeline (Updated): Jul 10, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jul 10, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Nov 06, 2018
    Quiz Created by
    Juanahernande
Cancel
  • All
    All (10)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
CPM is:
Given, expected duration of project = 47 days, variance = 9 days....
Pick the wrong relationship:
Which of the following is not true about crashing?
Point out what is not required...
It is known that in a project, activity 4-6 has a duration of six days...
Given, expected duration of project = 47 days, variance = 9 days. What...
Mark the wrong statement.
Which of these is not correct?
Mark the wrong statement.
Alert!

Advertisement