This quiz will cover all URE multiple choice questions from Vol. 2 of the A-Set of Pavements and Construction Equipment Operator 5-Level upgrade course. All questions are taken directly from the UREs and the multiple choice options are the same. Correct answers reflect the correct answers from the CDC themselves and not necessarily the correct See moreanswers from the CERTest
To lower the water table
To drain underground lakes
To intercept seepage or underground springs
All of the above
Rate this question:
Location
Distance to be covered
Amount of rainfall to be expected
Type of building equipment used
Rate this question:
Shaped to fit the pipe
Shaped the same as the sides
Filled with select filter material
Filled with a layer of impervious soil
Rate this question:
Prevent washouts
Retard the water flow
Prevent silt settlement
Allow for normal flow of water
Rate this question:
Use a spillway at the outlet
Use a sump at the inlet
Build a headwall
Flare the end walls
Rate this question:
Build a headwall
Install a drop inlet
Flare the endwalls
Build a spillway
Rate this question:
Space is limited
The water table is low
Groundwater is within 1 foot of the pavement
Groundwater is within 1 foot of the basecourse
Rate this question:
Storm drain
French drain
Vertical dry well
Intercepting drain
Rate this question:
Inadequate slop
A tendency to silt up
A tendemcy to overflow
The ability to carry only a low amount of water
Rate this question:
Raise the water table
Lower the water table
Assist in drainage
Prevent freezing
Rate this question:
The structure is to be placed along the side of pavement
The structure is to be placed under the pavement
Slope is not a factor
The grade is steep
Rate this question:
Shaped to fit the pipe
At the correct slope
In a V-shape
Rounded
Rate this question:
Riding
Walking
Operational
Maintenance
Rate this question:
Flushing with high-pressure water
Probing with cleaning rods
Using a plumber's snake
Digging up the line
Rate this question:
Heighten the dam
Build a spillway
Expand the sidewalls
Build additional dams
Rate this question:
Build a spillway with concrete
Flare the end walls
Install a plank headwall
Install a check dam
Rate this question:
Increase water flow
Prevent erosion
Control silting
Act as a funnel
Rate this question:
Hauling off debris
Flushing with detergents
Flushing with high-pressure water
Blowing it out with high-pressure air
Rate this question:
A
B
C
D
Rate this question:
Coarse-grained
Fine-grained
Organic
Plastic
Rate this question:
2
4
6
8
Rate this question:
Terrain
Weather conditions
Equipment available
Amount of work
Rate this question:
First curve
End of the curve
Beginning of the project
End of the project
Rate this question:
PC
PI
PT
C
Rate this question:
Front
Back
Top
Side
Rate this question:
Foundations
Boundaries
Utility lines
Soil characteristics
Rate this question:
Elevation
Dimension
Utility
Lines
Rate this question:
Center line
Object line
Section line
Detailed line
Rate this question:
It represents a center line
It represents a hidden line
It shows that everything inside the line is complete
It shows the kind of material that is to be used
Rate this question:
Lines
Letters
Symbols
Abbreviations
Rate this question:
Cost estimate
Required tools
Digging permit
Commander's approval
Rate this question:
Draw and label pertinent items
Draw and label proposed sidewalk
Physically check the construction site
Measure distances and place figures on sketch
Rate this question:
Your name
Cost estimate
Special instructions
Estimated time of completion
Rate this question:
By leveling the legs
By rotating the eyepiece
By turning the adjusting screw
By adjusting the azimuth clamp
Rate this question:
The compensator
The azimuth clamp
The tangent screw
The leveling screw
Rate this question:
Leave the instrument on the tripod
Dismantle the instrument from the tripod
Tighten the clamp screw to prevent movement
Loosen the clamp to let the instrument move in case it is hit
Rate this question:
To compensate for windy conditions
To keep all legs at a uniform angle
To find a more stable surface
To level the head slightly
Rate this question:
Uphill
Downhill
To the left
To the right
Rate this question:
Rodman
Levelman
Signalman
Engineer
Rate this question:
Backsight
Sidesight
Foresight
Mean Sea Level
Rate this question:
200 RPM
400 RPM
600 RPM
800 PM
Rate this question:
12
26
18
24
Rate this question:
Radio
Microwave
TV
Electric
Rate this question:
2 feet
3 feet
4 feet
6 feet
Rate this question:
Bench
Through
Sidehill
Combination
Dozer
Scraper
Backhoe
Clamshell
Rate this question:
Parent material
A horizon soil
B horizon soil
C horizon soil
Rate this question:
Increase the wheel loads
Decrease the wheel loads
Increase drainage
Decrease drainage
Rate this question:
Quiz Review Timeline (Updated): Mar 22, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.