CONTRACT DOCUMENTS
Stop work if the contractor’s performance in not satisfactory or in variance with the contract documents.
Carry on the work and deduct costs normally due to the contractor for these corrections.
Stop the work if the Architect reports safety problems on the site.
Refuse, with good cause, to give the contactor proof the owner can meet the financial obligations of the project.
CONTRACT SUM
CONTIGENT ADDITIONAL SERVICES
PROJECT REPRESENTATION BEYOND BASIC SERVICES
OPTIONAL ADDITIONAL CHARGES
DUTIES TO THE CONTRACTOR
PRIVITY
ARCHITECT’S SERVICES
THIRD PARTY RELATIONSHIP
RETAINAGE
FIXED LIMIT
SURETY BOND
LIQUIDATED DAMAGES
FIXED SUM
MULTIPLE OF DIRECT PERSONNEL EXPENSE
PERCENTAGE PF CONSTRUCTION COST
UNIT COST BASED ON SQUARE METER
After receiving the Architect’s field reports, the owner should stop the work and arrange for a meeting between the owner, the owner, Architect and the contractor to determine the cause of the problems and what the contractor intends to do. If the contractor does not correct the work, the owner should carry out the work with other contractors and deduct the cost by change order from the original contractor’s construction cost.
The Architect should recommend that the owner give the contractor written notice of non-conformance with the contract documents and if, after seven days the contractor has not begun corrective measures, terminate the contract.
The Architect and owner should discuss the problem to see if the owner would be willing to accept it in exchange for the reduction in the contract sum. If not, the owner should give seven days written notice to terminate the contract and find another contractor to finish the job.
The Architect should, with the owner’s knowledge, reject non-conforming work and notify the contractor that it must be corrected promptly. The Architect should remind the owner that the owner can have the work corrected after giving the contractor two (2) seven day written notices to correct the work.
The Architect acts on behalf of the owner, making decisions and expediting the work and taking responsibilities the owner would normally have.
The Architect mediates between the owner and the contractor and vendors for the benefit of the owner.
The Architect is the principal of the relationship who balances the needs of the contractor and the owner.
The Architect works fir the owner in certain designated area with the authority to act on the owner’s behalf.
DESIGN-BUILD
FAST-TRACK
MULTIPLE PRIME CONTRACT
DESIGN-AWARD-BUILD
I, III, and V
I, II, III, and V
II, III, IV, and V
. all of the above
The Architect is responsible for the defect in the work if he or she sees it but fails to report it to the contractor.
The owner has the sole right to make changes in the work but must do it through the Architect.
The Architect does not have to verify and test reports given by the owner.
By the time construction documents are almost completed, the architect still does not have to give a reasonably accurate construction price.
CHANGE ORDER
ADDENDUM
ALTERNATE LISTING
CONSTRUCTION CHANGE DIRECTIVE
I,II, IV, and V
II, III, and IV
II, III, IV, and V
All of the above
Quiz Review Timeline +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.