Project+ Risk Response Avoid Mitigate Transfer Accept Quiz

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Thames
T
Thames
Community Contributor
Quizzes Created: 8865 | Total Attempts: 106,055
| Questions: 20 | Updated: Aug 14, 2026
Please wait...
Question 1 / 21
🏆 Rank #--
0 %
0/100
Score 0/100

1. A contractor purchases a performance bond to protect against vendor failure. This demonstrates:

Submit
Please wait...
About This Quiz
Project+ Risk Response Avoid Mitigate Transfer Accept Quiz - Quiz

This quiz evaluates your understanding of risk response strategies in project management. You'll assess scenarios involving risk avoidance, mitigation, transfer, and acceptance\u2014core techniques from the CompTIA Project+ V5 framework. Master these strategies to make informed decisions that protect project objectives and stakeholder interests.

2.

What first name or nickname would you like us to use?

You may optionally provide this to label your report, leaderboard, or certificate.

2. Which response strategy is most cost-effective for low-probability, high-impact risks?

Submit

3. A vendor fails to deliver on time. If the project manager had accepted this risk, what tool should have been in place?

Submit

4. When a risk response strategy is implemented, the project manager should:

Submit

5. A project team identifies a potential schedule delay. They add buffer time to the project timeline. This is:

Submit

6. Which of the following best describes the difference between mitigation and acceptance?

Submit

7. Eliminating a high-risk activity by redesigning the project workflow is an example of:

Submit

8. In risk response planning, what is a 'contingency reserve'?

Submit

9. A project manager decides to implement redundant systems to prevent single points of failure. This is an example of:

Submit

10. Which response strategy is best suited for high-impact, high-probability risks?

Submit

11. Which risk response strategy involves eliminating the risk by changing project scope or objectives?

Submit

12. When should risk acceptance be chosen as a response strategy?

Submit

13. A project faces potential budget overrun. The team creates a detailed cost control process to minimize spending variance. This is:

Submit

14. Which response strategy reduces the probability or impact of a risk without eliminating it?

Submit

15. Outsourcing a critical function to reduce internal risk is an example of which strategy?

Submit

16. A development team identifies the risk of losing a key technical expert. To avoid this risk, what action should they take?

Submit

17. Which response strategy is most appropriate when a risk has low probability and low impact?

Submit

18. When a project manager accepts a risk, what must they establish?

Submit

19. Risk transfer typically involves shifting responsibility to a third party. Which tool best supports this?

Submit

20. A project manager identifies that a supplier delay could impact the schedule. She develops a backup supplier relationship. What strategy is this?

Submit
×
Saved
Thank you for your feedback!
View My Results
Cancel
  • All
    All (20)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
A contractor purchases a performance bond to protect against vendor...
Which response strategy is most cost-effective for low-probability,...
A vendor fails to deliver on time. If the project manager had accepted...
When a risk response strategy is implemented, the project manager...
A project team identifies a potential schedule delay. They add buffer...
Which of the following best describes the difference between...
Eliminating a high-risk activity by redesigning the project workflow...
In risk response planning, what is a 'contingency reserve'?
A project manager decides to implement redundant systems to prevent...
Which response strategy is best suited for high-impact,...
Which risk response strategy involves eliminating the risk by changing...
When should risk acceptance be chosen as a response strategy?
A project faces potential budget overrun. The team creates a detailed...
Which response strategy reduces the probability or impact of a risk...
Outsourcing a critical function to reduce internal risk is an example...
A development team identifies the risk of losing a key technical...
Which response strategy is most appropriate when a risk has low...
When a project manager accepts a risk, what must they establish?
Risk transfer typically involves shifting responsibility to a third...
A project manager identifies that a supplier delay could impact the...