The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Thames
T
Thames
Community Contributor
Quizzes Created: 8865 | Total Attempts: 106,055
| Questions: 20 | Updated: Aug 14, 2026
Please wait...
Question 1 / 21
🏆 Rank #--
0 %
0/100
Score 0/100

1. Which of the following activities can typically have slack without affecting project completion?

Submit
Please wait...
About This Quiz
Project+ Critical Path Method Calculation Quiz - Quiz

This quiz assesses your understanding of the Critical Path Method (CPM), a core project management technique covered in CompTIA Project+ V5. You'll evaluate activity sequences, calculate early and late start\/finish times, identify slack or float, and determine project duration. Mastering CPM helps you optimize schedules, manage dependencies, and control project... see moretimelines effectively. see less

2.

What first name or nickname would you like us to use?

You may optionally provide this to label your report, leaderboard, or certificate.

2. Total slack (or total float) is calculated as ______ minus Early Finish.

Submit

3. Which statement about the critical path is true?

Submit

4. Activity J has a duration of 7 days, ES = 3, and EF = 10. Is this activity scheduled correctly?

Submit

5. Free float represents the amount of time an activity can be delayed without affecting which activity?

Submit

6. If the project has a critical path of 45 days and Activity I has a total slack of 8 days, can Activity I be delayed by 10 days without affecting the project deadline?

Submit

7. Activity H depends on both Activity F and Activity G finishing. What type of dependency is this?

Submit

8. The backward pass in CPM calculations determines all ______ values.

Submit

9. The forward pass in CPM calculations determines all ______ values.

Submit

10. If Activity G has ES = 6, duration = 8, and LS = 9, what is the total slack?

Submit

11. In a network diagram, Activity A takes 5 days, Activity B takes 8 days and depends on A, and Activity C takes 3 days and depends on A. What is the critical path duration?

Submit

12. Activity F has LS = 12 and duration = 5. Calculate its LF.

Submit

13. In backward pass calculations, Late Finish of a predecessor activity equals the ______ of its successor.

Submit

14. In forward pass calculations, Early Start of a successor activity equals the ______ of its predecessor.

Submit

15. Activity E has a duration of 4 days and free float of 2 days. What is its total float if the project slack is 5 days?

Submit

16. An activity on the critical path has zero slack. Why is this significant?

Submit

17. The critical path is the longest path through the network diagram. What does this mean for project duration?

Submit

18. An activity has ES = 5, EF = 12, LS = 8, LF = 15. What is the total slack?

Submit

19. Which formula correctly calculates Late Finish (LF) from Late Start (LS) and duration?

Submit

20. Activity D has an Early Start (ES) of 10 days and a duration of 6 days. What is its Early Finish (EF)?

Submit
×
Saved
Thank you for your feedback!
View My Results
Cancel
  • All
    All (20)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
Which of the following activities can typically have slack without...
Total slack (or total float) is calculated as ______ minus Early...
Which statement about the critical path is true?
Activity J has a duration of 7 days, ES = 3, and EF = 10. Is this...
Free float represents the amount of time an activity can be delayed...
If the project has a critical path of 45 days and Activity I has a...
Activity H depends on both Activity F and Activity G finishing. What...
The backward pass in CPM calculations determines all ______ values.
The forward pass in CPM calculations determines all ______ values.
If Activity G has ES = 6, duration = 8, and LS = 9, what is the total...
In a network diagram, Activity A takes 5 days, Activity B takes 8 days...
Activity F has LS = 12 and duration = 5. Calculate its LF.
In backward pass calculations, Late Finish of a predecessor activity...
In forward pass calculations, Early Start of a successor activity...
Activity E has a duration of 4 days and free float of 2 days. What is...
An activity on the critical path has zero slack. Why is this...
The critical path is the longest path through the network diagram....
An activity has ES = 5, EF = 12, LS = 8, LF = 15. What is the total...
Which formula correctly calculates Late Finish (LF) from Late Start...
Activity D has an Early Start (ES) of 10 days and a duration of 6...
play-Mute sad happy unanswered_answer up-hover down-hover success oval cancel Check box square blue
Alert!