Select the best answer for each question. You will have unlimited tries! This quiz is NOT graded. . . For practice only!
How long a phase should last
A heuristic that says a project should last more than 8 months or less than 80 days
A heuristic that says a task should not last more than 80 hours or less than 8 hours
A description of a collection of tasks within one phase
Rate this question:
To ensure maximum billable hours
To ensure the project is complete and whole at finish
To ensure Todd performs all of his responsibilities
To work toward a definite deliverable
Rate this question:
Milestones
Project management life cycle
Deliverables
Project funding
Rate this question:
Project charter
Project scope statement
Project WBS
WBS dictionary
Rate this question:
A predefined schedule
A predefined budget
Interoperability of the software and existing hardware
A requirement to include scalability in the hardware you add to operations
Rate this question:
Project team members
A preferred sequence of project activities
A project scope
Identified project deliverables
Rate this question:
Create a sample WBS and give it the project team to complete.
Work with the project team to create a sample WBS and give it to management.
Work with the project team and the key stakeholders to create the WBS.
A project of this size does not need a WBS.
Rate this question:
It adds additional team members to the project.
It distracts the team members from the project.
Additions, even simple ones, can greatly impact the success of a project.
Additions, even simple ones, must be approved through the project sponsor.
Rate this question:
A milestone that has been reached
A party for project team
A date that has been established within the WBS
A definite deliverable result
Rate this question:
A unit of work that must be completed before the next unit begin
The smallest unit of work that can be performed by the team as a whole
The smallest decomposed object in the WBS
One of the three parts of any project; the introduction, the implementation, and the project wrap-up
Rate this question:
RACI chart
Roles and responsibility chart
Requirement traceability matrix
WBS dictionary
Rate this question:
Code of accounts
Chart of accounts
WBS dictionary index
Project glossary
Rate this question:
The WBS allows the project manager to work backward from the targeted date to assign.
The WBS allows the project manager to assign resources to tasks.
The creation of the WBS ensures that all of the project deliverables are fully identified and decomposed so that the necessary resources may be obtained and assigned to the work.
The WBS allows the project manager to assign multiple team meembers to multiples tasks to speed up the implementation
Rate this question:
Including stakeholders ensures that all of the requirements are identified and captured.
Including stakeholders ensures that the stakeholders know who the project manager is and who the project team members are.
Including stakeholders ensures that the stakeholders see that all of the requirements have been identified and are accounted for in the project.
Including stakeholders helps to promote shared ownership of the project.
Rate this question:
Quiz Review Timeline (Updated): Mar 15, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.