Select the best answer for each question. You will have unlimited tries! This quiz is NOT graded. . . For practice only!
An expansion of the WBS
An expansion of the Gantt chart
A sequential mapping of the project work
A topology of a project phase
Rate this question:
FS
SS
FF
SF
Rate this question:
Activity list
Project network diagram
Risk management plan
Schedule management plan
Rate this question:
Project management plan
Quality management plan
Team leadership plan
Project human resource plan
Rate this question:
It is all the work, and only the required work, to meet the project objectives.
It is the combination of the project scope statement, the WBS, and the WBS dictionary.
It is the combination of the project requirements, the project scope, and the WBS.
It the consideration of the project requirements, assumptions, and constraints that affect the project planning
Rate this question:
Lag times allow the team to take a break.
Lag times reflect instances when task overruns are anticipated.
Lag time reflect weekends and holidays.
Lag times allow the events to be completed before successor tasks can begin.
Rate this question:
The network of all the tasks within the project
The assignment of resources
The budget for the project
The reflection of the WBS
Rate this question:
Process improvement plan
Scope management plan
Risk management plan
Quality management plan
Rate this question:
Every project will have float.
Only complex project will have float.
Float is the amount of time an activity can be delayed without increasing the project costs
Float is the amount of time an activity can be delayed without causing the project to be late
Rate this question:
Law of Diminishing Returns
Moore's Law
Parkinson's Law
Murphy's Law
Rate this question:
Dates cannot change; tasks can.
Dates require the activity to happen at a specific time.
Tasks assigned to dates do not consider successor tasks
Tasks assigned to dates do not consider both successor and predecessor tasks
Rate this question:
Quality management plan
Scope management plan
Change control plan
Risk management plan
Rate this question:
Sharing
Mitigation
Avoidance
Transference
Rate this question:
RFP
RFI
IFB
PO
Rate this question:
Quiz Review Timeline (Updated): Mar 21, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.