UAP Doc 301 - General Condition

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Mozadelacruz
M
Mozadelacruz
Community Contributor
Quizzes Created: 1 | Total Attempts: 1,529
| Attempts: 1,529 | Questions: 60
Please wait...
Question 1 / 60
0 %
0/100
Score 0/100
1. The person or firm whose proposal has been accepted and to whom the Contract was awarded.

Explanation

The correct answer is Contractor. The contractor is the person or firm whose proposal has been accepted and who has been awarded the contract. They are responsible for executing the project and ensuring that all the terms and conditions of the contract are met. The contractor may hire sub-contractors to assist in completing the project, but ultimately they are the ones in charge of overseeing the work and delivering the final product to the owner. The owner, architect, and sub-contractor are all involved in the project, but the contractor is the one with the primary responsibility for its execution.

Submit
Please wait...
About This Quiz
UAP Doc 301 - General Condition - Quiz

Kindly comment if there are some corrections. Thank you!-Tinkerbell

2. Shall mean to build in, mount positions, connect or apply any object specified ready for the intended use.

Explanation

The word "install" is the correct answer because it accurately reflects the meaning of the given sentence. The sentence states that "shall mean" refers to the action of building in, mounting positions, connecting, or applying any object specified ready for the intended use. "Install" is the most appropriate word that encompasses all of these actions, making it the correct choice.

Submit
3. Shop Drawings shall be dated and contains the following, EXCEPT:

Explanation

A bubble diagram is not a requirement for shop drawings. Shop drawings should be dated and include descriptive names of equipment, materials, and classified item numbers, as well as the location at which materials or equipment are to be installed and the name of the project. However, a bubble diagram, which is a schematic representation of spaces and their relationships, is not typically included in shop drawings.

Submit
4. Graphical representations of the work involved in the project.

Explanation

The correct answer is "Drawings" because graphical representations of the work involved in the project are commonly referred to as drawings. Drawings provide visual representations of the project plans and specifications, allowing stakeholders to better understand the scope and requirements of the project. They can include architectural, structural, electrical, or mechanical drawings, depending on the nature of the project. Drawings are essential for communication and coordination among project team members and serve as a reference throughout the construction process.

Submit
5. Guarantee Bond equivalent to _____% of the contract price covering a period of _____year of the final acceptance of the work.

Explanation

The correct answer is 30% ; 1 year. This means that a guarantee bond equivalent to 30% of the contract price will be provided for a period of 1 year from the final acceptance of the work.

Submit
6. For reimbursable expenses, how many kilometers from the architect's area of operation shall a work be located to allow reimbursable expenses.

Explanation

Reimbursable expenses are costs that are incurred by the architect while performing their work and can be claimed back from the client. In this case, the question is asking how far a work should be located from the architect's area of operation in order to be eligible for reimbursable expenses. The correct answer is 100km, meaning that any work that is located within a 100km radius from the architect's area of operation can qualify for reimbursable expenses.

Submit
7. This is submitted by the contractor in critical path method form or any other form acceptable to the architect indicating the approximate date, equipment, and number of men to be employed

Explanation

The Schedule of Construction work is the correct answer because it is the document submitted by the contractor in critical path method form or any other acceptable form to the architect. This document provides information about the approximate date, equipment, and number of men to be employed for the construction project. It helps in planning and organizing the construction activities, ensuring that the project is completed on time and within budget. The Schedule of Construction work is an essential tool for coordinating the various tasks and resources involved in the project.

Submit
8. In Sec.6 Art. 19 of UAP Doc. 301, the supervisor must be a licensed engineer or architect who will work personally and inspect the site at least__________.

Explanation

According to Section 6, Article 19 of UAP Doc. 301, the supervisor must be a licensed engineer or architect who will personally inspect the site at least once a week.

Submit
9. The person or firm or corporation who provides the guarantee for the contractor's bonds.

Explanation

The correct answer is "Surety." A surety is a person, firm, or corporation that provides a guarantee for the contractor's bonds. This means that they are responsible for ensuring that the contractor fulfills their obligations and completes the project as agreed upon. The surety acts as a financial backstop and provides assurance to the owner or local government that they will be compensated if the contractor fails to meet their obligations.

Submit
10. The contractors shall provide and maintain adequate weather tight temporary office. What is the area of the room to be provided for the Architect's use?

Explanation

The question asks for the area of the room to be provided for the Architect's use. The correct answer is 12 sq. m. This means that the contractors are required to provide a temporary office with an area of 12 sq. m. which is weather tight. This office will be used by the Architect during the project.

Submit
11. A contract provision setting forth the damages a party must pay in the event of his breach.

Explanation

Liquidated damages refer to a contract provision that specifies the amount of damages a party must pay in case of a breach. This provision helps to determine the damages in advance, making it easier to calculate and enforce them. It provides certainty and fairness to both parties involved in the contract. Unlike penalty costs, which are designed to punish the breaching party, liquidated damages are intended to compensate the non-breaching party for the actual loss suffered as a result of the breach. Extra cost and NOTA are not relevant in this context.

Submit
12. If the architect as project manager performs regular design services for the same project, the compensation is included in his fee as project manager. True or False?

Explanation

The compensation for regular design services performed by the architect as a project manager is not included in his fee as project manager. This means that the architect would receive separate compensation for the design services in addition to his fee as a project manager. Therefore, the statement is False.

Submit
13. List of work and corresponding value in materials & labor including profit and overhead allowance.

Explanation

The correct answer is "Breakdown of work and corresponding values". This refers to a list or breakdown of the different tasks or activities involved in a project or work, along with their corresponding values or costs in terms of materials, labor, profit, and overhead allowance. It provides a detailed and organized overview of the project, allowing for better planning, budgeting, and monitoring of the work progress and costs.

Submit
14. Refers to acquisition of goods, consulting services, and the contracting for infrastructure projects by the procuring entity.

Explanation

Procurement refers to the process of acquiring goods, consulting services, and contracting for infrastructure projects. It involves the selection, purchase, and management of these resources by the procuring entity. The procurement office is responsible for overseeing and executing the procurement process. Consulting services are specialized professional services that are sought by the procuring entity to provide expert advice or assistance in a particular area. Therefore, the correct answer for this question is "Procurement."

Submit
15. Shall be understood to mean "Purchase and/or fabricate and deliver to the jobsite or other location when so designated.

Explanation

The phrase "Shall be understood to mean" indicates that the following statement is a definition or interpretation of a specific term. In this case, the term being defined is "Purchase and/or fabricate and deliver to the jobsite or other location when so designated." The term is being defined as "Furnish." Therefore, the correct answer is "Furnish."

Submit
16. A bond furnished by the contractor and his surety as a guarantee to execute the work in accordance with the terms of the contract

Explanation

A performance bond is a type of bond provided by the contractor and their surety to ensure that the work will be completed as per the terms of the contract. It serves as a guarantee that the contractor will fulfill their obligations and deliver the project as agreed upon. This bond provides financial protection to the project owner in case the contractor fails to perform or completes the work unsatisfactorily.

Submit
17. All costs for shipment, delivery, handling, and testing of samples are to be paid by the __________.

Explanation

The correct answer is Contractor because in a typical construction project, the contractor is responsible for managing all aspects of the project, including the shipment, delivery, handling, and testing of samples. This includes coordinating with suppliers, arranging for transportation, and ensuring that all necessary tests are conducted. Therefore, it is the contractor's responsibility to bear the costs associated with these activities.

Submit
18. A surety bond with the proposal submitted by the bidder to guarantee that the bidder will enter into the contract.

Explanation

A proposal bond is a type of surety bond that is submitted by a bidder as part of their proposal for a contract. This bond serves as a guarantee that the bidder will enter into the contract if they are awarded it. It provides assurance to the project owner that the bidder is serious and committed to fulfilling their obligations. If the bidder fails to enter into the contract, the bond can be used to compensate the project owner for any losses incurred. Therefore, a proposal bond is specifically designed to ensure the bidder's commitment to the contract.

Submit
19. After submission of the contract documents to the owner, a sum sufficient to increase the total payments to what percentage of the basic fee computed upon a reasonable estimated construction cost of the project is paid to architect.

Explanation

After the contract documents are submitted to the owner, the architect is paid a sum that is sufficient to increase the total payments to 90% of the basic fee. This means that the architect receives a significant portion of the fee based on the estimated construction cost of the project.

Submit
20. Refers to any branch, department, office, agency, or instrumentality of the government, including state universities and colleges, government owned and/or controlled corporations, government financial institutions, and local government units procuring goods, consulting services and infrastructure projects.

Explanation

The term "procuring entity" refers to any branch, department, office, agency, or instrumentality of the government, including state universities and colleges, government-owned and/or controlled corporations, government financial institutions, and local government units that are involved in the procurement process. This includes the procurement of goods, consulting services, and infrastructure projects. The procuring entity is responsible for acquiring the necessary resources and services needed by the government through a transparent and competitive procurement process.

Submit
21. A list of Instructions stipulating the manner on which bids are to be prepared

Explanation

The correct answer is "Instructions to bidder" because in the given list, it is the only item that specifically relates to the manner in which bids are to be prepared. The other items, such as "General Conditions," "Agreement," and "Bid bulletin," may be related to the bidding process in general, but they do not directly address the preparation of bids. Therefore, "Instructions to bidder" is the most appropriate choice as it provides the necessary guidance for bidders on how to prepare their bids.

Submit
22. Is the approved form of security furnished by the contractor and his surety as guarantee of good faith on the part of the Contractor to pay all obligations arising from the contract.

Explanation

A payment bond is a form of security provided by the contractor and their surety to guarantee that they will fulfill all financial obligations arising from the contract. It ensures that the contractor will make payment to subcontractors, suppliers, and laborers involved in the project. This bond protects these parties from non-payment and provides assurance that they will receive the compensation they are owed.

Submit
23. How many complete catalogue data for every item of equipment shall the contractor furnish?

Explanation

The contractor is required to furnish three complete catalogue data for every item of equipment. This means that for each equipment item, the contractor must provide detailed information and specifications from three different catalogues. This ensures that there is a variety of options and sources of information available for each equipment item, allowing for thorough evaluation and comparison.

Submit
24. A price given by a contractor, subcontractor, material supplier, or vendor to furnish materials, labor or both.

Explanation

A quotation is a price given by a contractor, subcontractor, material supplier, or vendor to furnish materials, labor, or both. It is a formal document that outlines the cost of a project or service. Quotations are typically provided to potential clients or customers as a proposal for the work to be done. They include detailed information on the materials required, the labor costs involved, and any additional expenses. Quotations are used to estimate the total cost of a project and help the client make an informed decision before proceeding with the work.

Submit
25. The person granting a possessory interest in buildings, property, etc. by lease.

Explanation

A lessor is the person who grants a possessory interest in buildings, property, etc. by lease. They are the landlord or property owner who allows another person or entity, known as the lessee, to use and occupy the property for a specified period of time in exchange for rent or other agreed-upon terms. The lessor retains ownership of the property but grants the lessee the right to possess and use it.

Submit
26. A statement from the architect confirming the amount of money due to the contractor for the works accomplished.

Explanation

The architect's confirmation of the amount of money due to the contractor for the completed works is known as a certificate of payment. This document serves as proof that the contractor has fulfilled their obligations and is entitled to receive payment for their services. It is typically issued after a thorough inspection and evaluation of the completed work, ensuring that it meets the required standards and specifications. The certificate of payment is an essential document in the payment process, providing transparency and accountability between the architect, contractor, and client.

Submit
27. The person receiving a possessory interest in buildings, property, etc. by lease.

Explanation

A lessee is the correct answer because they are the person who receives a possessory interest in buildings, property, etc. by lease. A lessee is someone who enters into a lease agreement with a lessor (the person who owns the property) and is granted the right to use and occupy the property for a specified period of time in exchange for rent payments.

Submit
28. Working drawings submitted by the contractor showing the system and actual locations of outlets, fixtures, services and equipment taht were installed.

Explanation

As built drawings refer to the working drawings that are submitted by the contractor after the completion of a project. These drawings show the actual locations of outlets, fixtures, services, and equipment that were installed. They serve as a record of the final construction and are used for reference and future maintenance purposes. Unlike construction drawings, which are created before the project begins, as built drawings provide an accurate representation of the finished project. Shop drawings, on the other hand, are detailed drawings created by subcontractors to show how specific components will be fabricated and installed. Specifications, on the other hand, outline the materials, methods, and quality standards for the project.

Submit
29. Is an outline specification enumerating the type or trade names of materials be used.

Explanation

The schedule of materials and finishes is a document that provides a detailed list of the type or trade names of materials to be used in a project. It outlines the specific materials and finishes that will be incorporated into the construction or design. This document helps ensure that the correct materials are selected and used, allowing for consistency and quality in the final product. It also serves as a reference for contractors and suppliers to procure the necessary materials.

Submit
30. Who shall verify and certify the lines and levels of any portion of work any time deemed necessary by the Architect?

Explanation

The surveyor is responsible for verifying and certifying the lines and levels of any portion of work as deemed necessary by the architect. This involves ensuring that the construction is aligned correctly and meets the required standards. The surveyor's expertise in measuring and mapping the land makes them the most suitable professional for this task. The contractor is responsible for executing the construction work, the architect designs the project, and the foreman supervises the workers on-site. However, none of these roles specifically involve verifying and certifying lines and levels.

Submit
31. What does PCAB stand for?

Explanation

The acronym PCAB stands for Philippine Contractors Accreditation Board. This board is responsible for accrediting and regulating contractors in the Philippines. They ensure that contractors meet certain standards and qualifications in order to protect the interests of both clients and contractors in the construction industry.

Submit
32. The owner has requested the Architect to instruct the Contractor for an extra work. What shall be the method of compensation for the Contractor?

Explanation

The correct answer is "Actual Direct Cost plus 15% for contractor's profit." This means that the contractor will be compensated based on the actual direct cost of the extra work, which includes the cost of labor, materials, and any other expenses directly related to the work. In addition, the contractor will receive a 15% profit on top of the direct cost. This method ensures that the contractor is fairly compensated for the additional work while also allowing for a reasonable profit margin.

Submit
33. If the project manager is hired by the owner, who shall have the responsibility of hiring the construction manager.

Explanation

If the project manager is hired by the owner, it is logical to assume that the responsibility of hiring the construction manager would also fall under the project manager's role. As the project manager is responsible for overseeing the entire project, including coordinating and managing various stakeholders, it makes sense that they would have the authority to hire the construction manager as well.

Submit
34. How many copies of keying schedule is submitted by the contractor before final payment is made?

Explanation

Before final payment is made, the contractor is required to submit three copies of the keying schedule. This is likely to ensure that there are sufficient copies for record-keeping purposes and to provide copies to relevant parties involved in the project. Having multiple copies can help prevent any potential loss or damage to the schedule and ensure that all parties have access to the necessary information.

Submit
35. No payments shall be made in excess of ____% of the contract price unless a notarized statement is submitted by the contractor to the effect taht all bills for labor, other tahn current wages, and bills for materials have been paid.

Explanation

No payments shall be made in excess of 65% of the contract price unless a notarized statement is submitted by the contractor to the effect that all bills for labor, other than current wages, and bills for materials have been paid. This means that the contractor must provide proof that they have paid all outstanding bills for labor (excluding current wages) and materials before receiving any payments exceeding 65% of the contract price. This ensures that the contractor is fulfilling their financial obligations and prevents any potential disputes or non-payment issues.

Submit
36. In case of transfer without previous consent, the owner may refuse to carry out the contract. The rights to breach the contract is reserved to whom?

Explanation

In the given scenario, if a transfer is made without the previous consent of the owner, the owner may refuse to carry out the contract. This means that both the owner and the contractor have the right to breach the contract. The owner can refuse to proceed with the contract because their consent was not obtained for the transfer, while the contractor can also choose to breach the contract due to the owner's refusal to carry it out.

Submit
37. Works covered by Copyright protection, EXCEPT:

Explanation

The correct answer is "Works of Government." This is because works created by the government are typically not eligible for copyright protection. This includes laws, court opinions, and government reports, among others.

Submit
38. Equipment such as temporary stairs, ladders, ramps, scaffolds, and all such other apparatus and construction shall meet all the requirements of what law.

Explanation

The Labor Law requires that equipment such as temporary stairs, ladders, ramps, scaffolds, and other construction apparatus meet all the necessary requirements. This law ensures the safety and well-being of workers by mandating that the equipment used in construction projects is up to standard and does not pose any risks or hazards. Compliance with the Labor Law helps to prevent accidents and injuries on construction sites, promoting a safe working environment.

Submit
39. The amount retained by the owner from the contractor shall be released __________the date of the final payment.

Explanation

The amount retained by the owner from the contractor shall be released 3 months after the date of the final payment. This means that the owner will hold onto a portion of the payment for a certain period of time before releasing it to the contractor. This allows the owner to ensure that all contractual obligations have been met and that there are no outstanding issues or disputes before releasing the retained amount.

Submit
40. Contract time shall commence how many days from receipt of the notice to proceed.

Explanation

The contract time will start 7 days after receiving the notice to proceed. This means that once the notice to proceed is received, there will be a 7-day period before the contract time officially begins. During this time, the necessary preparations and arrangements can be made before the contract work commences.

Submit
41. How many prints of progress photographs shall be delivered to the architect by the contractor?

Explanation

The contractor shall deliver 8 prints of progress photographs to the architect. This suggests that the architect requires multiple copies of the progress photographs for review and documentation purposes. Having multiple prints allows for distribution among different stakeholders and ensures that there are enough copies for future reference.

Submit
42. How many days must claim for adjustment involving questions of fact be asserted from the date the change is ordered?

Explanation

Claim for adjustment involving questions of fact must be asserted within 15 days from the date the change is ordered. This means that if there is a dispute or disagreement regarding the facts of the change, the claim must be made within 15 days. This time frame allows for a timely resolution of any issues related to the adjustment.

Submit
43. How much percent of the project construction cost is the architect's fee for design build services by administration aside from his fee for regular design services.

Explanation

The architect's fee for design build services by administration is 7% of the project construction cost. This means that out of the total cost of constructing the project, 7% is allocated for the architect's fee for design build services.

Submit
44. This type of method of procurement is also known as selective bidding, a method that involves direct invitation to bid by the procuring entity from a set of pre-selected suppliers or consultants with known experience and proven capability relative to the requirements of a particular contract.

Explanation

Limited source bidding is a method of procurement that involves direct invitation to bid by the procuring entity from a set of pre-selected suppliers or consultants with known experience and proven capability relative to the requirements of a particular contract. This method is also known as selective bidding because the procuring entity selects a limited number of suppliers or consultants to participate in the bidding process based on their qualifications and expertise. It is used when the procuring entity wants to ensure that only qualified and capable suppliers or consultants are invited to bid for a specific contract.

Submit
45. For claims for extra costs, the contractor shall give the architect written notice thereof within _____ days.

Explanation

The contractor is required to provide written notice to the architect within 15 days for any claims for extra costs. This allows the architect to be informed and take appropriate action in a timely manner. It also ensures that any additional expenses incurred by the contractor are properly documented and addressed.

Submit
46. How many days prior to bidding shall the contractor seek the architect's clarification as to the particular areas of work which the the competence of the sub-contractor shall be subjected to evaluation by the architect?

Explanation

Contractors should seek the architect's clarification regarding the areas of work that will be evaluated by the sub-contractor 15 days prior to bidding. This allows the contractor enough time to understand the specific requirements and evaluate the competence of potential sub-contractors in those areas. Seeking clarification earlier ensures that the bidding process proceeds smoothly and that the evaluation of sub-contractors is thorough and accurate.

Submit
47. A method of procurement that does not require elaborate bidding documents because the supplier is simple asked to submit a price quotation or a pro-forma invoice together with the conditions of sale, which offer may be accepted immediately or after some negotiations.

Explanation

Direct Contracting is a method of procurement that does not require elaborate bidding documents. Instead, the supplier is simply asked to submit a price quotation or a pro-forma invoice along with the conditions of sale. This offer may be accepted immediately or after some negotiations. This method allows for a more streamlined and efficient procurement process, as it eliminates the need for extensive bidding procedures.

Submit
48. The contractor shall execute at his won expense all work necessary for Making Good of Known Defects  within the period of _____days after issuance of certificate of completion.

Explanation

The correct answer is 60. This means that the contractor is responsible for fixing any known defects within 60 days after receiving the certificate of completion. This allows the contractor enough time to identify and address any issues or problems that may arise after the completion of the project. It ensures that the contractor is held accountable for the quality and durability of their work.

Submit
49. How many days upon written notice can a contractor terminate a contract with a valid reason?

Explanation

A contractor can terminate a contract with a valid reason upon giving a written notice of 15 days. This means that the contractor must provide written notice to the other party at least 15 days before terminating the contract. This allows both parties to have sufficient time to prepare for the termination and make any necessary arrangements or adjustments.

Submit
50. A cost reimbursement type construction management contract where the owner will pay the construction manager a fee which is adjusted by sharing formulas applied to the difference between the final allowable costs and the target costs.

Explanation

This type of contract is called a Cost Plus Incentive Fee contract. In this contract, the owner agrees to reimburse the construction manager for the actual costs incurred during the project, plus an additional fee that is adjusted based on sharing formulas. These sharing formulas are applied to the difference between the final allowable costs and the target costs. This contract provides an incentive for the construction manager to control costs and meet the target costs, as they can earn a higher fee if they are able to do so.

Submit
51. Effectivity of Intelletual Property Code of the Philippines.

Explanation

The correct answer is January 1, 1998. This is the most logical choice as it falls between the two given dates of June 1, 1997 and June 1, 1998. It is also the only date that is in the same year as the two given dates, making it the most likely effective date for the Intellectual Property Code of the Philippines.

Submit
52. Construction Industry Arbitration Law

Explanation

EO 1008 is the correct answer because it is the specific law related to the Construction Industry Arbitration. It is likely that the other options, EO 1005, RA 9184, and RA 8293, are unrelated to the construction industry or arbitration. Therefore, EO 1008 is the most relevant and appropriate choice in this context.

Submit
53. After submission of the design development to the owner, a sum sufficient to increase the total payments to what percentage of the basic fee computed upon a reasonable estimated construction cost of the project is paid to the architect. [2016SPP]

Explanation

After the design development is submitted to the owner, the architect is paid a sum that increases the total payments to 40% of the basic fee. This means that the architect receives 40% of the fee that was originally calculated based on a reasonable estimated construction cost of the project.

Submit
54. How many days shall the building official issue a certificate of occupancy after final inspection of the project?

Explanation

The building official is required to issue a certificate of occupancy within 30 days after the final inspection of the project. This allows for sufficient time to review all necessary documentation and ensure that the building meets all safety and code requirements before it can be occupied.

Submit
55. A type of construction management contract where the owner will pay the construction manager a fixed fee which is adjusted according to the difference between the final allowable cost and target costs.

Explanation

Fixed Price Incentive is a type of construction management contract where the owner agrees to pay the construction manager a fixed fee that can be adjusted based on the difference between the final allowable cost and the target costs. This means that if the actual costs are lower than the target costs, the construction manager will receive a higher fee as an incentive. Conversely, if the actual costs exceed the target costs, the fee will be reduced. This type of contract provides an incentive for the construction manager to control costs and complete the project within the agreed-upon budget.

Submit
56. The term of a Patent shall be _____ years from the filing date of the application.

Explanation

The term of a patent refers to the duration for which the patent holder has exclusive rights to their invention. In this case, the correct answer is 20 years from the filing date of the application. This means that for a period of 20 years, the patent holder has the sole right to make, use, and sell their invention, preventing others from doing so without their permission. After the 20-year term expires, the invention enters the public domain and can be freely used by anyone.

Submit
57. The contractor shall submit written notice to the architect at least _____ prior to beginning, suspending or resuming the work inspection without delaying the work.

Explanation

The contractor is required to provide written notice to the architect at least 10 days prior to beginning, suspending, or resuming the work inspection. This allows the architect to plan and schedule their inspections accordingly without causing any delays in the progress of the work. Providing sufficient notice ensures that the architect can allocate the necessary resources and personnel to conduct the inspection on the specified date.

Submit
58. Approval of the Intellectual Property Code of the Philippines?

Explanation

The correct answer is June 6, 1997. This date represents the approval of the Intellectual Property Code of the Philippines. This code is a legislation that provides legal protection for intellectual property rights in the country. It covers various forms of intellectual property, including patents, trademarks, copyrights, and trade secrets. By approving this code, the Philippines government recognized the importance of protecting intellectual property and ensuring that creators and inventors are granted exclusive rights to their work.

Submit
59. During the warranty period, repairs and corrective works shall be done without cost to the owner and at entire cost and expense of the contractor within _______ days upon written notice to the contractor by the owner.

Explanation

During the warranty period, the responsibility for repairs and corrective works lies with the contractor, who is obligated to cover all costs and expenses. The owner has the right to request these repairs by providing written notice to the contractor. According to the given information, the contractor must complete the repairs within 5 days of receiving the written notice from the owner.

Submit
60. How many days prior to cancelling an insurance be given to the owner stipulating the intention to cancel?

Explanation

In insurance policies, it is generally required to give a certain notice period before cancelling the policy. The correct answer is 10 days, which means that the owner must be informed at least 10 days prior to the cancellation of the insurance. This allows the owner to make necessary arrangements or find alternative coverage if needed.

Submit
View My Results

Quiz Review Timeline (Updated): Mar 22, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 22, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Mar 08, 2018
    Quiz Created by
    Mozadelacruz
Cancel
  • All
    All (60)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
The person or firm whose proposal has been accepted and to whom the...
Shall mean to build in, mount positions, connect or apply any object...
Shop Drawings shall be dated and contains the following, EXCEPT:
Graphical representations of the work involved in the project.
Guarantee Bond equivalent to _____% of the contract price covering a...
For reimbursable expenses, how many kilometers from the...
This is submitted by the contractor in critical path method form or...
In Sec.6 Art. 19 of UAP Doc. 301, the supervisor must be a licensed...
The person or firm or corporation who provides the guarantee for the...
The contractors shall provide and maintain adequate weather tight...
A contract provision setting forth the damages a party must pay in the...
If the architect as project manager performs regular design services...
List of work and corresponding value in materials & labor...
Refers to acquisition of goods, consulting services, and the...
Shall be understood to mean "Purchase and/or fabricate and...
A bond furnished by the contractor and his surety as a guarantee to...
All costs for shipment, delivery, handling, and testing of samples are...
A surety bond with the proposal submitted by the bidder to guarantee...
After submission of the contract documents to the owner, a sum...
Refers to any branch, department, office, agency, or instrumentality...
A list of Instructions stipulating the manner on which bids are to be...
Is the approved form of security furnished by the contractor and his...
How many complete catalogue data for every item of equipment shall the...
A price given by a contractor, subcontractor, material supplier, or...
The person granting a possessory interest in buildings, property, etc....
A statement from the architect confirming the amount of money due to...
The person receiving a possessory interest in buildings, property,...
Working drawings submitted by the contractor showing the system and...
Is an outline specification enumerating the type or trade names of...
Who shall verify and certify the lines and levels of any portion of...
What does PCAB stand for?
The owner has requested the Architect to instruct the Contractor for...
If the project manager is hired by the owner, who shall have the...
How many copies of keying schedule is submitted by the contractor...
No payments shall be made in excess of ____% of the contract price...
In case of transfer without previous consent, the owner may refuse to...
Works covered by Copyright protection, EXCEPT:
Equipment such as temporary stairs, ladders, ramps, scaffolds, and all...
The amount retained by the owner from the contractor shall be released...
Contract time shall commence how many days from receipt of the notice...
How many prints of progress photographs shall be delivered to the...
How many days must claim for adjustment involving questions of fact be...
How much percent of the project construction cost is the...
This type of method of procurement is also known as selective...
For claims for extra costs, the contractor shall give the architect...
How many days prior to bidding shall the contractor seek the...
A method of procurement that does not require elaborate bidding...
The contractor shall execute at his won expense all work necessary...
How many days upon written notice can a contractor terminate a...
A cost reimbursement type construction management contract where the...
Effectivity of Intelletual Property Code of the Philippines.
Construction Industry Arbitration Law
After submission of the design development to the owner, a sum...
How many days shall the building official issue a certificate of...
A type of construction management contract where the owner will pay...
The term of a Patent shall be _____ years from the filing date of the...
The contractor shall submit written notice to the architect at least...
Approval of the Intellectual Property Code of the Philippines?
During the warranty period, repairs and corrective works shall be done...
How many days prior to cancelling an insurance be given to the owner...
Alert!

Advertisement