Kindly comment if there are some corrections. Thank you!-Tinkerbell
Cost Plus Incentive Fee
Fixed Price Incentive
Firm Fixed Price
Cost Plus Fixed Fee
Rate this question:
Bill of Materials
Project Cost
Quotation
Direct Cost
Rate this question:
Genderal Conditions
Instructions to bidder
Agreement
Bid bulletin
Rate this question:
Receipt
Breakdown of Work and Corresponding Value
Certificate of Payment
Payment Bond
Rate this question:
90%
80%
70%
60%
Rate this question:
50%
45%
40%
35%
Rate this question:
Owner
Architect
Contractor
Supplier
Rate this question:
30% ; 2 year
30% ; 4 year
30% ; 1 year
30% ; 3 year
Rate this question:
30
10
15
60
Rate this question:
98%
50%
65%
85%
Rate this question:
Contractor
Owner
Architect
Sub-contractor
Rate this question:
Specifications
Special Provisions
Bill of Materials
Schedule of Materials and Finishes
Rate this question:
Client
Architect
Project Manager
Architect and Project Manager
Rate this question:
10%
7%
15%
5%
Rate this question:
70km
80km
90km
100km
Rate this question:
True
False
Rate this question:
15 days
7 days
30 days
10 days
Rate this question:
15 days
10 days
7 days
30 days
Rate this question:
15 days
7 days
30 days
10 days
Rate this question:
2 copies
2 sets
3 copies
3 sets
Rate this question:
Plan
Document
Drawings
Contract
Rate this question:
30 days
15 days
7 days
10 days
Rate this question:
June 6, 1997
June 27, 1997
January 1, 1998
January 7, 1998
Rate this question:
June 1, 1997
June 1, 1998
January 1, 1998
January 1, 1997
Rate this question:
Portal
Goods
Procuring Entity
Consulting Services
Rate this question:
Procurement
Procuring Entity
Procurement Office
Consulting Services
Rate this question:
10
20
30
40
Rate this question:
6 sq. m.
10 sq. m.
12 sq. m.
15 sq. m.
Rate this question:
Everyday
3x a week
Twice a week
Once a week
Rate this question:
Lectures, sermon, addresses, dissertations prepared for oral delivery
Works of drawing, painting, architecture, sculpture, engraving, lithography or other work of art
Musical compositions, with or without words
Works of Government
Rate this question:
2
3
5
7
Rate this question:
Philippine Construction Association Board
Philippine Contractors Accreditation Board
Philippine Constructors Accreditation Board
Philippine Contractors Association Board
Rate this question:
Performance Bond
Guarantee Bond
Payment Bond
Proposal Bond
Rate this question:
Descriptive names of equipment, materials and classified item numbers
Location at which materials or equipment are to be installed
Name of Project
Bubble Diagram
Rate this question:
Surveyor
Contractor
Architect
Foreman
Rate this question:
Probable Construction Cost plus 15% for contractor's profit
Actual Direct Cost plus 15% for contractor's profit
Actual Direct Cost plus 30% for contractor's profit
Probable Construction Cost plus 30% for contractor's profit
Rate this question:
7 days
10 days
15 days
30 days
Rate this question:
3 months before
60 days before
3 months after
60 days after
Rate this question:
Owner only
Contractor only
Owner and contractor
NOTA
Rate this question:
Direct Contracting
Limited Source Bidding
Repeat Order
Shopping
Rate this question:
EO 1008
EO 1005
RA 9184
RA 8293
Rate this question:
Provide
Furnish
Install
Deliver
Rate this question:
Provide
Furnish
Install
Deliver
Rate this question:
Direct Contracting
Limited Source Bidding
Lease Contract
Negotiated Procurement
Rate this question:
Schedule of materials and finishes
Breakdown of work and corresponding values
Schedule of works
Quantities of works
Rate this question:
Performance bond
Payment bond
Proposal bond
Guarantee bond
Rate this question:
Construction drawings
Shop Drawings
As built drawings
Specifications
Rate this question:
Provisions
Contract Documents
Construction Drawing
Schedule of Construction work
Rate this question:
Quiz Review Timeline (Updated): Mar 22, 2023 +
Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.
Wait!
Here's an interesting quiz for you.