A company has a requirement to have labor certificates defined.
...
A maintenance planner is in the process of planning time sensitive...
A company has a requirement to share calendar, classification, job...
Which report option provides multiple access points for an end user to...
Which report option provides multiple access points for an end user to...
A company is training on the use of the material status fields on work...
A company has a requirement that certain GL Accounts expire.In which...
Maintenance is required on an asset at every 6,000 miles that uses job...
An administrator has a requirement to add a new meter to 100 existing...
A fixed-schedule PM needs to be set up.What other setting need to be...
The planner identified that the pump required four widgets as material...
A user has entered a material receipt in error and wishes to correct...
A company requires that laborers record the actual time they spent on...
What is the reason to specify asset relationships?
Which application must be used to create services that can be selected...
A company wishes to group its location records into a hierarchy to...
A company wishes to create a location that is used during the...
To minimize Start Center load times, end users can see detailed KPI...
What costing method should be used if the receipt cost of items that...
A company is creating an ad hoc report indicating the number of days...
A vendor requires a payment of 20% of the purchase price when the...
The business analyst for the purchasing department of a company is...
The maintenance supervisor is gathering data to use to build job...
Incorrect meter readings have been taken for gauge meters and...
An administrator needs to enable a prompt in the Organizations...
The organizational rules allow for labor hours entered by internal...
An Administrator needs to return a rotating asset to a vendor. When...
A company has a requirement to report on actual labor hours,...
A quantity of 5 is received on a PO Line which has a quantity of 10....
An administrator has a requirement to ensure that purchase...
A user has created a work order against asset ABC. A technician...
An administrator needs to report failures that are occuring on a...
A new revision of a workflow subprocess has been created for a...
A company wants to trigger a PM based on a characteristic type meter....
A company is using Process Flow Control and wants to change the...
An administrator has a requirement to update the address of all...
The user wants to have a new job plan reference an existing job plan...
A company would like to make full use of item assembly structures. To...
An approved work order has been assigned an incorrect job plan. How do...
The job plan coordinator needs to add new tasks to an existing job...
After creating and approving a non-contract related invoice for a...
A company has acquired a contract for an asset covering labor,...
A user tries to edit a meter in the Manage Meter Reading History...
A company has identified three tasks (10, 20 and 30) and these tasks...
A custom field has been added to the Work Order Tracking application...
A user gets an error when trying to move a rotating asset via the...
When a route is applied to a work order, which of the following is...
A supervisor is required to report actual work hours by work order...
A company needs to add the unit of measures for items, tool and...
What can be performed in the Assignments tab of Work Order Tracking?
A company orders and receives a case containing 36 light bulbs which...
A forecast has been made for a PM. The decision has been made to...
Cutover work from cooling to heating is performed on the air handling...
A company has multiple crews that work different days and hours. The...
A company has a work order with 50 separate tasks and 40 of the tasks...
A company wants to create a rotating (serialized) tool to issue to a...
A planner is creating a list of various types of records that will...
A company wishes to make a system the Primary System. Where can this...
A master PM can be used to do which of the following?
A company wants to ignore storeroom availability for work order status...
A storeroom clerk is processing items to be shipped to various...
Which delivered report option enables a user to dynamically interact...
A user is in the Inventory application and has enabled a record for...
Which statement is true about routes?
A buyer runs a BIRT report which details Supplier Compliance. The...
An item has been flagged as rotating by mistake. The rotating checkbox...
A company wishes to track items previously used for maintenance work...
A company has users which perform a variety of roles from Planning,...
A company has a requirement to have items in the storerooms to be...
A company is using Process Flow Control to ensure the tasks are done...
A forecast for a monthly PM has been generated for 6 minutes. A new...
A planner needs to combine a number of items to be used regularly that...
An administrator want to create a time based escalation point to...
A workflow process has been revised and the new revision made...
A supervisor has a requirement to group labor transactions by work...
A company wants non-rotating items that are issued to assets to...
An administrator is setting up inventory items in storerooms and the...
A company has a requirement to temporarily give a user the privilege...
An engineer schedules a very complex asset report developed in BIRT....
A user wants to create an ad hoc report with details of a set of...
A company recently had to do a massive overhaul of a pump asset. The...
A user is searching for a classification to add to a record in Work...
A company has a requirement to present an informational dialog box to...
A supervisor has a requirement in Labor Reporting to report labor...
Which of the following describes the work list section in the...
Which configuration could be used by a company with two organizations...
A company has critical and time sensitive processes and tasks foe...
A company wishes to configure Maximo so that meter readings...
An administrator wishes to create company records without first...
A company wishes to apply an item assembly structure to a location....
A company wants to receive rotating items that require inspection....
A company purchased many non-rotating as well as rotating assets and...
New centrifugal pumps have been acquired. These new assets need to be...
A company wants to refuse receipt on 2 of 7 items from a single PO...
A user has created a request for quotation and sent it to vendors....
A company has business units that each have different GL account...
A store manager needs to make changes to an asset via the Move/Modify...
A company purchasing agent would like to have the company purchase...
A rotating asset has been inspected and approved. The asset is then...
A company has a requirement to identify and characterize similar...