Project+ Earned Value CPI and SPI Metrics Quiz

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By Thames
T
Thames
Community Contributor
Quizzes Created: 12024 | Total Attempts: 174,522
| Questions: 20 | Updated: Aug 11, 2026
Please wait...
Question 1 / 21
🏆 Rank #-- ▾
0 %
0/100
Score 0/100

1. When CPI = 1.0, the project is ____.

Submit
Please wait...
About This Quiz
Project+ Earned Value Cpi and SPI Metrics Quiz - Quiz

This quiz evaluates your understanding of earned value management (EVM) metrics, specifically Cost Performance Index (CPI) and Schedule Performance Index (SPI). These critical indicators help project managers assess project health, cost efficiency, and schedule adherence in real-time. Master CPI and SPI calculations and interpretations to effectively monitor and control project... see moreperformance. see less

2.

What first name or nickname would you like us to use?

You may optionally provide this to label your report, leaderboard, or certificate.

2. What is the primary purpose of monitoring CPI and SPI throughout a project?

Submit

3. Which scenario represents the best project performance?

Submit

4. A project with CPI = 0.80 and SPI = 0.90 is ____.

Submit

5. True or False: CPI and SPI are independent metrics that cannot be analyzed together.

Submit

6. Which metric is used to forecast final project cost?

Submit

7. An SPI of 0.75 means the project has completed ____ of the planned work.

Submit

8. Calculate CPI for a project: EV = $75,000, AC = $70,000.

Submit

9. What does a CPI of 1.25 suggest about project performance?

Submit

10. True or False: SPI measures cost efficiency while CPI measures schedule efficiency.

Submit

11. What does CPI (Cost Performance Index) measure in earned value management?

Submit

12. A project has PV = $100,000, EV = $85,000, and AC = $90,000. Calculate the SPI.

Submit

13. What is the relationship between CPI and project cost overruns?

Submit

14. True or False: An SPI greater than 1.0 indicates the project is behind schedule.

Submit

15. Which formula correctly calculates CPI?

Submit

16. An SPI of 1.15 means the project is ____.

Submit

17. If EV is $40,000 and PV is $50,000, what is the SPI?

Submit

18. What does SPI (Schedule Performance Index) measure?

Submit

19. A CPI of 0.85 indicates the project is ____.

Submit

20. If a project has an EV of $50,000 and an AC of $55,000, what is the CPI?

Submit
×
Saved
Thank you for your feedback!
View My Results
Cancel
  • All
    All (20)
  • Unanswered
    Unanswered ()
  • Answered
    Answered ()
When CPI = 1.0, the project is ____.
What is the primary purpose of monitoring CPI and SPI throughout a...
Which scenario represents the best project performance?
A project with CPI = 0.80 and SPI = 0.90 is ____.
True or False: CPI and SPI are independent metrics that cannot be...
Which metric is used to forecast final project cost?
An SPI of 0.75 means the project has completed ____ of the planned...
Calculate CPI for a project: EV = $75,000, AC = $70,000.
What does a CPI of 1.25 suggest about project performance?
True or False: SPI measures cost efficiency while CPI measures...
What does CPI (Cost Performance Index) measure in earned value...
A project has PV = $100,000, EV = $85,000, and AC = $90,000. Calculate...
What is the relationship between CPI and project cost overruns?
True or False: An SPI greater than 1.0 indicates the project is behind...
Which formula correctly calculates CPI?
An SPI of 1.15 means the project is ____.
If EV is $40,000 and PV is $50,000, what is the SPI?
What does SPI (Schedule Performance Index) measure?
A CPI of 0.85 indicates the project is ____.
If a project has an EV of $50,000 and an AC of $55,000, what is the...
play-Mute sad happy unanswered_answer up-hover down-hover success oval cancel Check box square blue
Alert!