1.
What pre-initiating task can be done to justify investing in a project?
Correct Answer
B. Business case
2.
In earned value management, a baseline includes __________(WBS tasks), time (start and finish estimates for each task), and cost information (cost estimates for each task).
Correct Answer
B. Scope
3.
In the context of earned value management, the _____cost is the total direct and indirect costs incurred in accomplishing work on an activity during a given period.
Correct Answer
C. Actual
4.
The approved time estimate for a project can be divided by the______performance index to calculate when the project will be completed.
Correct Answer
A. Cost
5.
Given the earned value and _, you can see how well the project team is meeting schedule goals and forecast when the project will be completed based on past schedule performance.
Correct Answer
C. Planned value
6.
The main monitoring and controlling task performed as part of project cost management is controlling ________.
Correct Answer
C. Cost
7.
Pareto analysis is sometimes referred to as the _____rule, meaning that 80 percent of problems are often due to 20 percent of the causes.
Correct Answer
A. 80/20
8.
_______reports describe where the project stands at a specific point in time.
Correct Answer
B. Status
9.
Risk reassessment, risk audits, variance and trend analysus, technical performance measurements, reserve analysis, and status meetings or periodic risk reviews are all tools and techniques for performing _______monitoring and control.
Correct Answer
B. Risk
10.
___________change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.
Correct Answer
C. Constructive
11.
_________is a project performance measurement technique that integrates scope, time and cost data.
Correct Answer
C. Earned Value Management
12.
______involves formal acceptance of the completed project scope by the stakeholders.
Correct Answer
C. Customer signoff
13.
_________issues cause the most conflict over the life of projects.
Correct Answer
C. Schedule
14.
A___________chart is a histogram that can help you identify and prioritize problem areas.
Correct Answer
A. Pareto
15.
When a process is out of control, variations in the results of the process are caused by _____events.
Correct Answer
B. Nonrandom
16.
Which of the following is not a tool or technique for managing project teams?
Correct Answer
C. Control charts
17.
__________predict future project status and progress based on past information and trends.
Correct Answer
A. Forecasts
18.
______are unplanned responses to risk events.
Correct Answer
C. Workarounds
19.
______change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.
Correct Answer
A. Constructive
20.
__________is an estimate of the value of the physical work actually completed.
Correct Answer
C. Earned value
21.
If a project is running behind schedule and over budget, where will the estimate at completion point be on the earned value chart relative to the budget at completion point?
Correct Answer
A. Above and to the right
22.
A_____chart compares planned and actual project schedule information.
Correct Answer
B. Tracking Gantt
23.
You want to see if there is a relationship between two variables, like time of day and worker productivity. What type of quality control tool could you use to visualize this information?
Correct Answer
C. Scatter diagram
24.
If seven data points in a row are all below the mean, above the mean, increasing or decreasing, it is a vioation of _______.
Correct Answer
A. The seven run rule
25.
Changes related to procurred items should be__________.
Correct Answer
C. All of the above
26.
Project___are usually most interested in making sure that final products, services, or results are delivered and transitioned to the appropriate part of the organization.
Correct Answer
C. Sponsors
27.
When developing a transition plan, the project, the project team should exclude managers in affected operating departments.
Correct Answer
B. False
28.
When developing a ____plan, the project team should work with managers in affected operating departments, and the contents of the plan should be tailored to fit the support needs of the project.
Correct Answer
B. Transition
29.
Two tools to assist in contract closure are ______audits and a records management system.
Correct Answer
C. Procurement
30.
Which of the following statements is false?
Correct Answer
C. Closing does not include developing a transition plan
31.
Answering questions such as, "What will you do differently on the next project based on your experience working on this project?" is part of a _____.
Correct Answer
A. Lessons-learned report
32.
Contract close involves completion and settlement of contracts and resolution of __________.
Correct Answer
B. Any open items
33.
The___________ should include requirements for formal acceptance and closure of contracts.
Correct Answer
C. Contract itself
34.
A__________are reviews often performed during contract closure to identify lessons learned in the entire procurement process.
Correct Answer
A. Procurement audits
35.
Which of the following is not advice for closing projects or phases?
Correct Answer
A. You don't need to celebrate completing a project, especially if it did not go well.
36.
As part of project closing it is important to plan for and execute a smooth__________of the project into normal operations of the company.
Correct Answer
B. Transition
37.
Answering questions like "Reflect on whether or not you met the project success criteria" and "Describe one example of what went wrong on this project" are found in a __________report.
Correct Answer
C. Lessons learned
38.
Many organizations are working hard to improve the ____process since human capital is one of their key assets.
Correct Answer
C. Knowledge transfer
39.
Which of the following is a category under portfolio best practices?
Correct Answer
C. Portfolio risk management planning process improvement
40.
Assigning a project manager from operations to lead projects that affect operations is considered a best practice.
Correct Answer
A. True
41.
According to Andy Crowe's research, the best project managers send________emails per day and spend______time in meetings than typical project managers.
Correct Answer
C. Fewer, less
42.
A_______is another name for a project close-out meeting.
Correct Answer
C. Post mortem
43.
How do you determine the duration of the Critical Path?
It is the longest path.
44.
What is the Pert formula
Optimistic time + 4*(times) most likely time + pessimistic time / (divided) by 6
45.
What is the Communication Channel formula?
Correct Answer
N(N-1)/2
46.
What is the Pert formula?
Correct Answer
optimistic+4*most likely+pessimistic/6