Quiz Chapters 1-9

46 Questions | Attempts: 212
Share

SettingsSettingsSettings
Quiz Chapters 1-9 - Quiz

Questions and Answers
  • 1. 

    What pre-initiating task can be done to justify investing in a project?

    • A.

      Project charter

    • B.

      Business case

    • C.

      Business plan

    Correct Answer
    B. Business case
  • 2. 

    In earned value management, a baseline includes __________(WBS tasks), time (start and finish estimates for each task), and cost information (cost estimates for each task).

    • A.

      Range

    • B.

      Scope

    • C.

      Schedule

    Correct Answer
    B. Scope
  • 3. 

    In the context of earned value management, the _____cost is the total direct and indirect costs incurred in accomplishing work on an activity during a given period.

    • A.

      Real

    • B.

      Estimated

    • C.

      Actual

    Correct Answer
    C. Actual
  • 4. 

    The approved time estimate for a project can be divided by the______performance index to calculate when the project will be completed.

    • A.

      Cost

    • B.

      Schedule

    • C.

      Price

    Correct Answer
    A. Cost
  • 5. 

    Given the earned value and _, you can see how well the project team is meeting schedule goals and forecast when the project will be completed based on past schedule performance.

    • A.

      Actual cost

    • B.

      Cost variance

    • C.

      Planned value

    Correct Answer
    C. Planned value
  • 6. 

    The main monitoring and controlling task performed as part of project cost management is controlling ________.

    • A.

      Time

    • B.

      Scope

    • C.

      Cost

    Correct Answer
    C. Cost
  • 7. 

    Pareto analysis is sometimes referred to as the _____rule, meaning that 80 percent of problems are often due to 20 percent of the causes.

    • A.

      80/20

    • B.

      20/20

    • C.

      20/80

    Correct Answer
    A. 80/20
  • 8. 

    _______reports describe where the project stands at a specific point in time.

    • A.

      Ad hoc

    • B.

      Status

    • C.

      Critical

    Correct Answer
    B. Status
  • 9. 

    Risk reassessment, risk audits, variance and trend analysus, technical performance measurements, reserve analysis, and status meetings or periodic risk reviews are all tools and techniques for performing _______monitoring and control.

    • A.

      Scope

    • B.

      Risk

    • C.

      Cost

    Correct Answer
    B. Risk
  • 10. 

    ___________change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.

    • A.

      Virtual

    • B.

      Apparent

    • C.

      Constructive

    Correct Answer
    C. Constructive
  • 11. 

    _________is a project performance measurement technique that integrates scope, time and cost data.

    • A.

      Integrated change control

    • B.

      Flowcharting

    • C.

      Earned Value Management

    Correct Answer
    C. Earned Value Management
  • 12. 

    ______involves formal acceptance of the completed project scope by the stakeholders.

    • A.

      Scope verification

    • B.

      Deliverable acceptance

    • C.

      Customer signoff

    Correct Answer
    C. Customer signoff
  • 13. 

    _________issues cause the most conflict over the life of projects.

    • A.

      Change control

    • B.

      Cost

    • C.

      Schedule

    Correct Answer
    C. Schedule
  • 14. 

    A___________chart is a histogram that can help you identify and prioritize problem areas.

    • A.

      Pareto

    • B.

      Control

    • C.

      Scatter

    Correct Answer
    A. Pareto
  • 15. 

    When a process is out of control, variations in the results of the process are caused by _____events.

    • A.

      Randam

    • B.

      Nonrandom

    • C.

      Planned

    Correct Answer
    B. Nonrandom
  • 16. 

    Which of the following is not a tool or technique for managing project teams?

    • A.

      Observation and conversation

    • B.

      Performance appraisals

    • C.

      Control charts

    Correct Answer
    C. Control charts
  • 17. 

    __________predict future project status and progress based on past information and trends.

    • A.

      Forecasts

    • B.

      Status reports

    • C.

      Histograms

    Correct Answer
    A. Forecasts
  • 18. 

    ______are unplanned responses to risk events.

    • A.

      Contingencies

    • B.

      Reserves

    • C.

      Workarounds

    Correct Answer
    C. Workarounds
  • 19. 

    ______change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.

    • A.

      Constructive

    • B.

      Contract

    • C.

      Procurement

    Correct Answer
    A. Constructive
  • 20. 

    __________is an estimate of the value of the physical work actually completed.

    • A.

      Planned value

    • B.

      Actual cost

    • C.

      Earned value

    Correct Answer
    C. Earned value
  • 21. 

    If a project is running behind schedule and over budget, where will the estimate at completion point be on the earned value chart relative to the budget at completion point?

    • A.

      Above and to the right

    • B.

      Above and to the left

    • C.

      Below and to the right

    Correct Answer
    A. Above and to the right
  • 22. 

    A_____chart compares planned and actual project schedule information.

    • A.

      Gantt

    • B.

      Tracking Gantt

    • C.

      Comparison Gantt

    Correct Answer
    B. Tracking Gantt
  • 23. 

    You want to see if there is a relationship between two variables, like time of day and worker productivity. What type of quality control tool could you use to visualize this information?

    • A.

      Control chart

    • B.

      Run chart

    • C.

      Scatter diagram

    Correct Answer
    C. Scatter diagram
  • 24. 

    If seven data points in a row are all below the mean, above the mean, increasing or decreasing, it is a vioation of _______.

    • A.

      The seven run rule

    • B.

      The points rule

    • C.

      A normal distribution

    Correct Answer
    A. The seven run rule
  • 25. 

    Changes related to procurred items should be__________.

    • A.

      Approved in the same way that the original part of the plan was approved

    • B.

      Evaluated using an impact analysis

    • C.

      All of the above

    Correct Answer
    C. All of the above
  • 26. 

    Project___are usually most interested in making sure that final products, services, or results are delivered and transitioned to the appropriate part of the organization.

    • A.

      Managers

    • B.

      Auditors

    • C.

      Sponsors

    Correct Answer
    C. Sponsors
  • 27. 

    When developing a transition plan, the project, the project team should exclude managers in affected operating departments.

    • A.

      True

    • B.

      False

    Correct Answer
    B. False
  • 28. 

    When developing a ____plan, the project team should work with managers in affected operating departments, and the contents of the plan should be tailored to fit the support needs of the project.

    • A.

      Training

    • B.

      Transition

    • C.

      Performance

    Correct Answer
    B. Transition
  • 29. 

    Two tools to assist in contract closure are ______audits and a records management system.

    • A.

      Dispatch

    • B.

      Supply

    • C.

      Procurement

    Correct Answer
    C. Procurement
  • 30. 

    Which of the following statements is false?

    • A.

      Even though many projects are canceled before completion, it is still important to formally close any project

    • B.

      Closing often includes a final presentation and report

    • C.

      Closing does not include developing a transition plan

    Correct Answer
    C. Closing does not include developing a transition plan
  • 31. 

    Answering questions such as, "What will you do differently on the next project based on your experience working on this project?" is part of a _____.

    • A.

      Lessons-learned report

    • B.

      Customer acceptance/project completion form

    • C.

      Written notice of contract closure

    Correct Answer
    A. Lessons-learned report
  • 32. 

    Contract close involves completion and settlement of contracts and resolution of __________.

    • A.

      Payments

    • B.

      Any open items

    • C.

      Performance issues

    Correct Answer
    B. Any open items
  • 33. 

    The___________ should include requirements for formal acceptance and closure of contracts.

    • A.

      Project management plan

    • B.

      Procurement management plan

    • C.

      Contract itself

    Correct Answer
    C. Contract itself
  • 34. 

    A__________are reviews often performed during contract closure to identify lessons learned in the entire procurement process.

    • A.

      Procurement audits

    • B.

      Post mortems

    • C.

      Lessons learned

    Correct Answer
    A. Procurement audits
  • 35. 

    Which of the following is not advice for closing projects or phases?

    • A.

      You don't need to celebrate completing a project, especially if it did not go well.

    • B.

      You should capture lessons learned as soon as possible, not just at the end of a project.

    • C.

      You should include tasks in the WBS.

    Correct Answer
    A. You don't need to celebrate completing a project, especially if it did not go well.
  • 36. 

    As part of project closing it is important to plan for and execute a smooth__________of the project into normal operations of the company.

    • A.

      Takeover

    • B.

      Transition

    • C.

      Turnover

    Correct Answer
    B. Transition
  • 37. 

    Answering questions like "Reflect on whether or not you met the project success criteria" and "Describe one example of what went wrong on this project" are found in a __________report.

    • A.

      Final project

    • B.

      Transition

    • C.

      Lessons learned

    Correct Answer
    C. Lessons learned
  • 38. 

    Many organizations are working hard to improve the ____process since human capital is one of their key assets.

    • A.

      Transition

    • B.

      Project closing

    • C.

      Knowledge transfer

    Correct Answer
    C. Knowledge transfer
  • 39. 

    Which of the following is a category under portfolio best practices?

    • A.

      Program initiation process standardization

    • B.

      Project plan development process measurement

    • C.

      Portfolio risk management planning process improvement

    Correct Answer
    C. Portfolio risk management planning process improvement
  • 40. 

    Assigning a project manager from operations to lead projects that affect operations is considered a best practice.

    • A.

      True

    • B.

      False

    Correct Answer
    A. True
  • 41. 

    According to Andy Crowe's research, the best project managers send________emails per day and spend______time in meetings than typical project managers.

    • A.

      More, more

    • B.

      Fewer, more

    • C.

      Fewer, less

    Correct Answer
    C. Fewer, less
  • 42. 

    A_______is another name for a project close-out meeting.

    • A.

      Celebration

    • B.

      Post project

    • C.

      Post mortem

    Correct Answer
    C. Post mortem
  • 43. 

    How do you determine the duration of the Critical Path? It is the longest path.

  • 44. 

    What is the Pert formula  Optimistic time + 4*(times) most likely time + pessimistic time / (divided) by 6

  • 45. 

    What is the Communication Channel formula?  

    Correct Answer
    N(N-1)/2
  • 46. 

    What is the Pert formula?

    Correct Answer
    optimistic+4*most likely+pessimistic/6

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Jan 28, 2013
    Quiz Edited by
    ProProfs Editorial Team
  • Jun 14, 2011
    Quiz Created by
    Smith457
Back to Top Back to top
Advertisement