Pipe Laying, Trenching, Miscellaneous

Reviewed by Editorial Team
The ProProfs editorial team is comprised of experienced subject matter experts. They've collectively created over 10,000 quizzes and lessons, serving over 100 million users. Our team includes in-house content moderators and subject matter experts, as well as a global network of rigorously trained contributors. All adhere to our comprehensive editorial guidelines, ensuring the delivery of high-quality content.
Learn about Our Editorial Process
| By 23kfgn98
2
23kfgn98
Community Contributor
Quizzes Created: 1 | Total Attempts: 488
| Attempts: 488
SettingsSettings
Please wait...
  • 1/100 Questions

    What is on the opposite end of the bell of a pipe? 

    • Flat end
    • Mouth
    • Spigot
    • Lead
Please wait...
Pipe Laying, Trenching, Miscellaneous - Quiz
About This Quiz

This quiz focuses on Pipe Laying and Trenching, assessing knowledge in water pipe installation, trenching techniques, and safety measures. It evaluates understanding of equipment usage, regulatory compliance, and environmental considerations in civil engineering projects.


Quiz Preview

  • 2. 

    Which pipe can no longer be used in laying water pipe? 

    • PVC

    • Ductile iron

    • Asbestos cement

    • Cast iron

    Correct Answer
    A. Asbestos cement
    Explanation
    Asbestos cement pipes can no longer be used in laying water pipes due to health and safety concerns. Asbestos is a hazardous material that has been linked to serious health issues, including lung cancer and mesothelioma. In many countries, the use of asbestos has been banned or heavily restricted. Therefore, it is no longer considered a safe or suitable material for water pipe infrastructure.

    Rate this question:

  • 3. 

    What is color code for electric? 

    • Red

    • Blue

    • Yellow

    • Green

    Correct Answer
    A. Red
    Explanation
    Electricity is commonly associated with the color red, especially in electrical wiring and circuits. Red is often used to indicate live or active electrical components, while other colors such as blue, yellow, and green are typically used for different purposes, such as neutral wires, grounding, or signaling. Therefore, the color code for electric is red.

    Rate this question:

  • 4. 

    What is a purple pipe used for?

    • Potable water

    • Reclaimed water

    • Gas

    • Sewer

    Correct Answer
    A. Reclaimed water
    Explanation
    A purple pipe is used for reclaimed water. Reclaimed water refers to treated wastewater that is reused for non-potable purposes such as irrigation, industrial processes, or toilet flushing. Purple pipes are used to distinguish reclaimed water from other types of water sources and to prevent accidental cross-connections with potable water systems. This helps ensure that reclaimed water is used safely and appropriately for its intended purposes, conserving freshwater resources and reducing the strain on traditional water supplies.

    Rate this question:

  • 5. 

    What type of tablet is needed to kill bacteria when pipe is filled with water?

    • Florine

    • Chlorine

    • Bleach

    • Ammonia

    Correct Answer
    A. Chlorine
    Explanation
    Chlorine is the correct answer because it is a chemical compound that is commonly used as a disinfectant to kill bacteria and other microorganisms in water. When added to water, chlorine reacts with the bacteria and viruses, disrupting their cellular structure and rendering them unable to reproduce or cause harm. This makes chlorine an effective agent for treating water in pipes and other water systems to ensure that it is safe for consumption and use.

    Rate this question:

  • 6. 

    What is color code for potable water? 

    • Green

    • White

    • Yellow

    • Blue

    Correct Answer
    A. Blue
    Explanation
    Blue is the color code for potable water. This color is widely recognized as the standard for indicating that water is safe for drinking. It is used in various contexts such as water pipes, plumbing fixtures, and water storage containers to differentiate potable water from other types of water. The use of blue as the color code for potable water helps to ensure that people can easily identify and access safe drinking water sources.

    Rate this question:

  • 7. 

    What does yellow represent? 

    • Sewer

    • Gas

    • Communication

    • Storm Drain

    Correct Answer
    A. Gas
    Explanation
    Yellow represents gas. This is because in many countries, yellow is the standardized color for gas pipes and fittings. This helps to easily identify and differentiate gas lines from other utilities like water or electricity. The use of yellow for gas is a safety measure to prevent accidents and ensure that gas-related equipment and infrastructure are easily recognizable.

    Rate this question:

  • 8. 

    When shall initial backfill of pipe take place? 

    • Within 24 hours after laying pipe

    • By the next shift

    • Immediately after laying pipe

    • Within 4 hours after laying pipe

    Correct Answer
    A. Immediately after laying pipe
    Explanation
    The correct answer is "Immediately after laying pipe". This is because the initial backfill of the pipe should be done as soon as possible after the pipe is laid to prevent any damage or movement of the pipe. By backfilling immediately, the soil around the pipe is compacted and stabilized, providing support and preventing any potential issues such as settling or shifting of the pipe. This ensures the integrity and stability of the pipe system.

    Rate this question:

  • 9. 

    Efficient planning for pipe laying includes:

    • Resources available for planned footage per day

    • Shoring crew must stay ahead of grading operation

    • Pipe stacked close to trench for easy accessibility

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    Efficient planning for pipe laying includes considering the resources available for planned footage per day, ensuring that the shoring crew stays ahead of the grading operation, and stacking the pipe close to the trench for easy accessibility. All of these factors contribute to a smooth and efficient pipe laying process.

    Rate this question:

  • 10. 

    In general, why is no shoring required for water trenches?

    • They are planned for stable ground.

    • They are usually less than 5 ft deep.

    • Sloping is required instead of shoring.

    • Shielding is required instead of shoring.

    Correct Answer
    A. They are usually less than 5 ft deep.
    Explanation
    Water trenches are usually less than 5 ft deep, which is why no shoring is required. Shoring is typically needed for trenches that are deeper than 5 ft to prevent the sides from collapsing and to ensure the safety of workers. However, since water trenches are shallower, the soil is more stable and less likely to cave in, eliminating the need for shoring.

    Rate this question:

  • 11. 

    What is installed on the main line to connect to the service line?

    • Waddle strap

    • Strap saddle

    • Main strap connection

    • Cradle gurney

    Correct Answer
    A. Strap saddle
    Explanation
    A strap saddle is installed on the main line to connect to the service line. This device acts as a connector between the main line and the service line, ensuring a secure and stable connection. It is commonly used in plumbing or utility installations to join pipes or lines together. The strap saddle is designed to provide support and prevent any potential leaks or disruptions in the flow of the service line.

    Rate this question:

  • 12. 

    Where is the service line most likely to have leaks?

    • At connection with main line.

    • At connection with property line (meter).

    • At connection with main line and at connection with property line (meter).

    • In the middle of service line.

    Correct Answer
    A. At connection with main line and at connection with property line (meter).
    Explanation
    The service line is most likely to have leaks at the connection with the main line and at the connection with the property line (meter). These are the two points where the service line is connected to other pipes, making them potential weak points where leaks can occur. Leaks at these connections can result from improper installation, corrosion, or damage to the pipes. Regular inspection and maintenance of these connections are important to identify and repair any leaks promptly.

    Rate this question:

  • 13. 

    What is the purpose of running insulated wire along the service line? 

    • To connect electrical utility connection.

    • It is not required to run wire along service line.

    • It is necessary to feed electrical water valve along service line.

    • Line can later be detected by metal detector.

    Correct Answer
    A. Line can later be detected by metal detector.
    Explanation
    The purpose of running insulated wire along the service line is to make it possible to detect the line later using a metal detector. This is important for various reasons, such as locating the line for maintenance or repair purposes, or to prevent accidental damage to the line during construction or excavation work. The insulation on the wire helps to protect it from damage and ensures that it can be easily detected using a metal detector.

    Rate this question:

  • 14. 

    How is the gap between the end of the pipe and the inner wall of the precast manhole sealed?

    • Tar

    • Epoxy

    • Emulsion

    • Mortar

    Correct Answer
    A. Mortar
    Explanation
    The gap between the end of the pipe and the inner wall of the precast manhole is sealed using mortar. Mortar is a mixture of cement, sand, and water that is used to bind building materials such as bricks or stones together. In this case, it is used to fill and seal the gap, ensuring that there are no leaks or openings between the pipe and the manhole wall. Mortar is a durable and long-lasting material that provides a strong seal, making it an ideal choice for this application.

    Rate this question:

  • 15. 

    Why is the slotted bucket attachment used on the hoe when backfilling the first 3 feet of trench?

    • The teeth are needed to rip the confined area.

    • To capture the large rocks to set aside and keep out of initial backfill around pipe.

    • To capture the smaller rocks for use on initial backfill.

    • It digs efficiently in the confined area.

    Correct Answer
    A. To capture the large rocks to set aside and keep out of initial backfill around pipe.
    Explanation
    The slotted bucket attachment is used on the hoe when backfilling the first 3 feet of the trench in order to capture the large rocks and set them aside. This is important to keep these rocks out of the initial backfill around the pipe, as they could potentially cause damage or blockage. By capturing and setting aside the large rocks, the backfill can be done more effectively and without any obstruction.

    Rate this question:

  • 16. 

    Why is a waterproofing membrane needed on the exterior of a basement foundation wall?

    • Concrete itself without additives is not waterproof.

    • To insulate against water seepage into interior

    • Protect foundation's durability from potential distress caused by water

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    A waterproofing membrane is needed on the exterior of a basement foundation wall for several reasons. Firstly, concrete itself is not waterproof, so the membrane serves as an additional layer of protection against water seepage. Secondly, it helps to insulate against water seepage into the interior of the basement, preventing any potential damage or flooding. Lastly, the membrane protects the foundation's durability by preventing any distress that could be caused by water, such as cracks or deterioration. Therefore, all of the above reasons justify the need for a waterproofing membrane on the exterior of a basement foundation wall.

    Rate this question:

  • 17. 

    Why is a coupling necessary when repairing a straight section of sewer pipe? 

    • Couplings are necessary on all pipe connections.

    • Because it is a repair and not a new installation.

    • Couplings are necessary on all pipe repairs.

    • Because there is no spigot and bell to connect.

    Correct Answer
    A. Because there is no spigot and bell to connect.
    Explanation
    When repairing a straight section of sewer pipe, a coupling is necessary because there is no spigot and bell to connect. A spigot and bell is a type of joint used to connect pipes, but in this case, since it is a repair and not a new installation, the original spigot and bell may not be present. Therefore, a coupling is needed to join the two ends of the pipe together securely.

    Rate this question:

  • 18. 

    What does orange represent? 

    • Gas

    • Electric

    • Communication

    • Potable water

    Correct Answer
    A. Communication
    Explanation
    Orange is commonly associated with communication because it is often used to represent warning signs or alerts. In many countries, orange is used for traffic cones, construction signs, and other indications of caution or potential danger. This color choice is intended to grab attention and convey important information quickly. Therefore, the correct answer for this question is communication.

    Rate this question:

  • 19. 

    What does green represent? 

    • Sewer

    • Water

    • Storm Drain

    • Communication

    Correct Answer
    A. Sewer
    Explanation
    Green typically represents the sewer system. This is because sewer pipes are often colored green to distinguish them from other utility pipes. The color coding helps to prevent accidental damage or confusion during construction or maintenance work. Additionally, green is commonly associated with nature and the environment, which aligns with the purpose of the sewer system in managing and treating wastewater to protect the environment.

    Rate this question:

  • 20. 

    How many pounds per square inch (PSI) is required for testing water line? 

    • 100 psi

    • 120 psi

    • 140 psi

    • 150 psi

    Correct Answer
    A. 150 psi
    Explanation
    The correct answer is 150 psi. This is the amount of pressure in pounds per square inch that is required for testing a water line. This level of pressure is necessary to ensure that the water line is able to withstand the normal operating conditions and any potential fluctuations in pressure. It is important to test the water line at this high pressure to identify any leaks or weaknesses in the system before it is put into use.

    Rate this question:

  • 21. 

    What is the advantage of PVC sewer pipe over cast iron when installing? 

    • Because they come in longer spans, there is less total connections to make.

    • It requires smaller machines.

    • It requires smaller crew.

    • PVC comes in smaller spans allowing easier handling by crewmen.

    Correct Answer
    A. Because they come in longer spans, there is less total connections to make.
    Explanation
    The advantage of PVC sewer pipe over cast iron when installing is that PVC pipes come in longer spans, which means there are fewer total connections to make. This reduces the time and effort required for installation and decreases the chances of leaks or other issues at connection points. Additionally, fewer connections also mean fewer potential weak points in the sewer system, enhancing its overall durability and reliability.

    Rate this question:

  • 22. 

    What can happen if the bell and spigot get dirty before connecting? 

    • Cause leak

    • Contamination

    • Replacement at a later date if not detected during testing

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    If the bell and spigot get dirty before connecting, several things can happen. Firstly, it can cause leaks in the connection, as dirt and debris can prevent a tight seal from forming. Secondly, there is a risk of contamination, as the dirt can introduce harmful substances into the connection. Lastly, if the dirt is not detected during testing, it may require replacement at a later date, as the connection may not function properly. Therefore, all of the above consequences can occur if the bell and spigot get dirty before connecting.

    Rate this question:

  • 23. 

    What is normal compaction % for subgrade under street? 

    • 80%

    • 85%

    • 90%

    • 95%

    Correct Answer
    A. 95%
    Explanation
    The correct answer is 95%. Compaction is a process that involves applying pressure to soil in order to reduce its volume and increase its density. In the case of subgrade under a street, it is important to achieve a high level of compaction to ensure stability and prevent settlement. A compaction percentage of 95% indicates that the soil has been compacted to a high degree, resulting in a dense and stable subgrade.

    Rate this question:

  • 24. 

    What are commonly the three crews needed to lay pipe?

    • (1) Shoring, sloping, or shielding; (2) grading; (3) pipe laying

    • (1) Grading; (2) trenching; (3) pipe laying

    • (1) Trenching; (2) pipe laying; (3) joint filler

    • (1) Excavation; (2) trenching; (3) pipe laying

    Correct Answer
    A. (1) Shoring, sloping, or shielding; (2) grading; (3) pipe laying
    Explanation
    The correct answer is (1) Shoring, sloping, or shielding; (2) grading; (3) pipe laying. These are the three crews commonly needed to lay pipe. Shoring, sloping, or shielding is necessary to ensure the safety and stability of the excavation site. Grading is required to prepare the ground for pipe installation, ensuring proper alignment and elevation. Finally, the crew responsible for pipe laying will actually install the pipes according to the required specifications.

    Rate this question:

  • 25. 

    What equipment is used to trench rock and hardpan? 

    • Excavator with carbide tipped breaker

    • Dozer

    • Dragline

    • Vermeer trencher with carbide tipped teeth

    Correct Answer
    A. Vermeer trencher with carbide tipped teeth
    Explanation
    The Vermeer trencher with carbide tipped teeth is the correct answer because it is specifically designed to trench rock and hardpan. The carbide tipped teeth on the trencher are able to penetrate and break through tough surfaces effectively. The other options, such as the excavator with carbide tipped breaker, dozer, and dragline, may be used for other excavation purposes but may not be as suitable for trenching rock and hardpan.

    Rate this question:

  • 26. 

    Using shields for protection of workers in trenches instead of other protection methods _________ productivity.

    • Decreases

    • Increases

    • Does not affect and maintains the same

    • None of the above

    Correct Answer
    A. Decreases
    Explanation
    Using shields for protection of workers in trenches instead of other protection methods decreases productivity. This is because using shields requires additional time and effort to set up and maneuver, which can slow down the work process. Additionally, shields may obstruct the workers' movements and limit their ability to perform tasks efficiently. Therefore, opting for other protection methods that are less intrusive and time-consuming would be more conducive to maintaining productivity levels.

    Rate this question:

  • 27. 

    Pipes over ___” generally require mechanical fittings (flange, gasket, bolts

    • 6"

    • 8"

    • 10"

    • 12"

    Correct Answer
    A. 6"
    Explanation
    Pipes over 6" generally require mechanical fittings such as flange, gasket, and bolts. This means that for pipes with a diameter larger than 6 inches, it is necessary to use these fittings to ensure a secure and tight connection. This is because larger pipes have a higher flow rate and pressure, requiring stronger and more reliable fittings to prevent leaks and maintain the integrity of the pipeline system.

    Rate this question:

  • 28. 

    Where are plugs located relative to upstream and downstream manholes for AIR test of sewer system?

    • One plug is located downstream from upstream manhole; other plug is located downstream from downstream manhole

    • One plug is located upstream from upstream manhole; other plug is located upstream from downstream manhole

    • One plug is located downstream from upstream manhole; other plug is located upstream from downstream manhole

    • None of the above

    Correct Answer
    A. One plug is located downstream from upstream manhole; other plug is located upstream from downstream manhole
    Explanation
    In an AIR test of a sewer system, plugs are used to block off sections of the sewer line. The purpose of the test is to check for leaks or defects in the system. The correct answer states that one plug is located downstream from the upstream manhole, and the other plug is located upstream from the downstream manhole. This configuration allows for the section of the sewer line between the two plugs to be isolated and tested for leaks. Placing one plug downstream from the upstream manhole ensures that the test can be conducted in the correct direction of flow. Placing the other plug upstream from the downstream manhole allows for the section to be completely sealed off.

    Rate this question:

  • 29. 

    If a leak is found during water testing of sewer pipe, what needs to be checked for leaking? 

    • Manhole and its joints

    • Pipe and its joints

    • Plugs

    • A and B only

    • All

    Correct Answer
    A. All
    Explanation
    All of the options need to be checked for leaking. If a leak is found during water testing of a sewer pipe, it is important to inspect all possible areas where the leak could be occurring. This includes checking the manhole and its joints, as well as the pipe and its joints. Additionally, plugs should also be examined to ensure they are not causing any leaks. By inspecting all of these components, any potential leaks can be identified and addressed promptly.

    Rate this question:

  • 30. 

    Which test of sewer pipe is considered faster, cleaner and less expensive?

    • Pressure testing

    • Air testing

    • Water testing

    • Sewer testing

    Correct Answer
    A. Air testing
    Explanation
    Air testing is considered faster, cleaner, and less expensive compared to other tests for sewer pipes. This is because air testing involves pressurizing the pipe with air and checking for any leaks or pressure drops. It does not require filling the pipe with water or using any other substances, making it a cleaner method. Additionally, air testing is usually quicker to perform and does not require as much equipment or resources, resulting in lower costs.

    Rate this question:

  • 31. 

    When using a no-joint cast-in-place concrete pipe machine, why is it so important that soil conditions are good?

    • You don’t grade the trench.

    • You don’t place bedding material.

    • Trench is cut the exact size of outside diameter of pipe.

    • All of the above

    Correct Answer
    A. All of the above
    Explanation
    In order to use a no-joint cast-in-place concrete pipe machine effectively, it is crucial that the soil conditions are good. This is because if the soil conditions are not favorable, it can lead to various issues. If the trench is not properly graded, it can result in uneven support for the pipe, leading to potential damage or instability. Similarly, if bedding material is not placed, it can cause inadequate support and increase the risk of pipe failure. Lastly, cutting the trench to the exact size of the pipe's outside diameter ensures proper fit and alignment, preventing any potential issues during installation. Therefore, all of the mentioned factors are important for ensuring the successful use of the machine.

    Rate this question:

  • 32. 

    What component goes in between main line and property water meter? 

    • Component stop

    • Stop plug

    • Stop connection

    • Corporation stop

    Correct Answer
    A. Corporation stop
    Explanation
    A corporation stop is a component that is placed between the main water line and the property water meter. It is used to control the flow of water to the property and allows for easy maintenance and repairs. The other options mentioned, such as component stop, stop plug, and stop connection, do not accurately describe the specific component that is typically used in this location.

    Rate this question:

  • 33. 

    What is used to join new water line with old for testing before new can be approved for use? 

    • Nothing. New cannot be connected to old until approved independently.

    • Connected by pipe with a blowoff on old side and a blowoff on new side

    • Connected by a strap saddle.

    • Connected by a temporary pressure release valve.

    Correct Answer
    A. Connected by pipe with a blowoff on old side and a blowoff on new side
    Explanation
    In order to test the new water line before it can be approved for use, it needs to be connected to the old line using a pipe. This pipe should have a blowoff on both the old side and the new side. The blowoff valves allow for the release of any excess pressure or water during the testing process. This method ensures that the new water line can be independently tested and approved before being connected to the old line.

    Rate this question:

  • 34. 

    What is the normal drop of sewer service lines?

    • 1/2" per foot

    • 1/4" per foot

    • 0.1" per foot

    • 0.01" per foot

    Correct Answer
    A. 1/4" per foot
    Explanation
    The normal drop of sewer service lines is 1/4" per foot. This means that for every one foot of horizontal distance, the sewer service line should have a vertical drop of 1/4 inch. This drop is necessary to ensure proper flow and prevent any blockages or backups in the sewer system.

    Rate this question:

  • 35. 

    What is important to a contractor when selecting the bucket size used for the bottom of a sloped trench?

    • The bottom of trench around pipe must not be less than 6 inches or more than 1 foot wider than the pipe on each side.

    • The bottom of trench around pipe must not be less than 3 inches or more than 2 foot wider than the pipe on each side.

    • Trench at the bottom must no be greater than 2 ft wide on each side of pipe.

    • Trench at the bottom must be cut exactly to size of width of pipe and its diameter.

    Correct Answer
    A. The bottom of trench around pipe must not be less than 6 inches or more than 1 foot wider than the pipe on each side.
    Explanation
    The correct answer states that the bottom of the trench around the pipe should be between 6 inches and 1 foot wider than the pipe on each side. This is important for the contractor because it ensures that there is enough space for the pipe to be properly installed and allows for proper compaction of the soil around the pipe. If the trench is too narrow, it may be difficult to properly install the pipe or compact the soil, leading to potential issues with the pipe's stability and functionality. On the other hand, if the trench is too wide, it may result in unnecessary excavation and increased material costs. Therefore, selecting the correct bucket size is crucial for maintaining the appropriate width of the trench around the pipe.

    Rate this question:

  • 36. 

    Every shoring section has at least ___ pump cylinders.

    • 1

    • 2

    • 4

    • 6

    Correct Answer
    A. 2
    Explanation
    Every shoring section has at least two pump cylinders. This means that in order to provide adequate support and stability, a minimum of two pump cylinders are required for each shoring section. These pump cylinders are essential for adjusting and maintaining the desired height and pressure of the shoring system, ensuring its effectiveness in supporting the structure.

    Rate this question:

  • 37. 

    The valve at the highest point in a water system is the ___________________.

    • Blowoff valve

    • Air release and vacuum relief valve

    • Backflow valve

    • Service valve

    • None of the above

    Correct Answer
    A. Air release and vacuum relief valve
    Explanation
    The valve at the highest point in a water system is the air release and vacuum relief valve. This valve is designed to automatically release air from the system, preventing air pockets from forming and causing water flow issues. It also helps to relieve any vacuum pressure that may build up in the system, preventing damage to pipes and other components. The blowoff valve is typically used to release excess pressure, the backflow valve is used to prevent the reverse flow of water, and the service valve is a general term for valves used to control water flow.

    Rate this question:

  • 38. 

    Which of the following areas of road section would NOT likely require additional undercut to subgrade?

    • Road

    • Curb & gutter

    • Ditch

    • Sidewalk

    Correct Answer
    A. Ditch
    Explanation
    The ditch is a depression or channel alongside the road that is designed to collect and drain water. It is typically excavated to a specific depth and does not require additional undercutting to the subgrade because its purpose is to facilitate water drainage rather than provide a stable foundation for the road. Therefore, the ditch would not likely require additional undercutting to the subgrade.

    Rate this question:

  • 39. 

    What must the grade setter do to prepare for cut when reviewing surveyor’s stakes? 

    • Consult engineer or inspector to review before cutting

    • Calculate the flow line from the surveyor's off-set

    • Cut exactly where surveyor has indicated on his stakes

    • Add the thickness of pipe and bedding material to cut

    Correct Answer
    A. Add the thickness of pipe and bedding material to cut
    Explanation
    The grade setter must add the thickness of the pipe and bedding material to the cut when reviewing the surveyor's stakes. This is necessary to ensure that the cut is made at the correct depth, taking into account the additional layers that will be added later. By adding the thickness of the pipe and bedding material, the grade setter can accurately determine the depth at which the cut should be made.

    Rate this question:

  • 40. 

    When are watertight plugs placed onto ends of pipe to protect from debris and animals? 

    • When not in use

    • End of week

    • End of shift

    • None of the above

    Correct Answer
    A. End of shift
    Explanation
    Watertight plugs are placed onto ends of pipes at the end of a shift to protect them from debris and animals. This is done to ensure that the pipes remain clean and free from any potential damage or blockage. Placing the plugs at the end of the shift allows for immediate protection and prevents any unwanted materials or creatures from entering the pipes during periods of inactivity.

    Rate this question:

  • 41. 

    Why do job specifications usually call for the last 2 feet of digging to be vertical and no more than 1’ wider than sewer pipe to be laid?

    • To ensure that trench bottom will be compacted.

    • To avoid excess and unnecessary excavation.

    • To keep the pipe from being damaged by the full bearing weight of the width of the trench

    • None of the above

    Correct Answer
    A. To keep the pipe from being damaged by the full bearing weight of the width of the trench
    Explanation
    The last 2 feet of digging being vertical and no more than 1' wider than the sewer pipe helps to keep the pipe from being damaged by the full bearing weight of the width of the trench. This means that the weight of the soil and any other materials above the pipe will be evenly distributed and not concentrated on the sides of the pipe. This reduces the risk of the pipe being crushed or damaged, ensuring its integrity and longevity.

    Rate this question:

  • 42. 

    The spigot of the pipe should face? 

    • Upstream

    • North

    • May be upstream or downstream

    • Downstream

    Correct Answer
    A. Downstream
    Explanation
    The spigot of the pipe should face downstream because it allows for a smoother flow of water. When the spigot is facing downstream, the water can flow freely without any obstructions or resistance. This ensures that the water can easily move through the pipe without causing any damage or blockages. Additionally, facing the spigot downstream helps to prevent any backflow or pressure buildup in the pipe, which can lead to leaks or bursts.

    Rate this question:

  • 43. 

    How long does 1st fill of water test take for new sewer pipe that goes up to 5 ft in upstream manhole?

    • 4 hours

    • 6 hours

    • 12 hours

    • 24 hours

    Correct Answer
    A. 4 hours
    Explanation
    The first fill of water test for a new sewer pipe that goes up to 5 ft in an upstream manhole takes 4 hours. This test is conducted to check for any leaks or defects in the sewer pipe. By filling the pipe with water and observing if there is any loss of water or increase in water level, any issues can be identified. The 4-hour duration allows enough time for any potential leaks or defects to become apparent.

    Rate this question:

  • 44. 

    If specifications require you to backfill before testing, you should:

    • Backfill completely and then test for leakage.

    • Backfill partially and then test for leakage

    • Conduct your own test before backfilling to identify leakage and then test again after backfilling.

    • None of the above.

    Correct Answer
    A. Conduct your own test before backfilling to identify leakage and then test again after backfilling.
    Explanation
    When specifications require backfilling before testing, it is important to conduct a test before backfilling to identify any potential leakage. This initial test allows for the detection and resolution of any leakage issues before proceeding with the backfilling process. After the backfilling is complete, another test should be conducted to ensure that the backfilled area is free from any leakage. This approach ensures that any leakage is identified and addressed both before and after the backfilling, ensuring the integrity of the project.

    Rate this question:

  • 45. 

    What is one advantage of air testing over water testing of sewer pipe? 

    • Can be done before manholes are built.

    • Can be done without engineer approval.

    • Can be done before pipes are laid.

    • Can be done with partial backfill only.

    Correct Answer
    A. Can be done before manholes are built.
    Explanation
    Air testing of sewer pipes can be done before manholes are built because it does not require access to the manholes. This means that the testing can be conducted earlier in the construction process, allowing for any necessary repairs or adjustments to be made before the manholes are built. This can help to prevent any potential issues or delays that may arise from testing after the manholes are in place.

    Rate this question:

  • 46. 

    When are precast rings used to connect pipe to manholes?

    • For large pipes with precast manholes

    • For all pipes with precast manholes

    • For large pipes with cast-in-place manholes

    • For all pipes with cast-in-place manholes

    Correct Answer
    A. For large pipes with precast manholes
    Explanation
    Precast rings are used to connect pipe to manholes for large pipes with precast manholes because precast manholes are already manufactured and ready to be installed. These precast manholes are designed to accommodate larger pipes, and the precast rings provide a secure and efficient connection between the pipe and the manhole. For smaller pipes or cast-in-place manholes, different methods or materials may be used for the connection.

    Rate this question:

  • 47. 

    After pouring cast-in-place pipes with no-joint machine, what is used to avoiding drying too fast and cracking?

    • Drying agent in concrete mix

    • Cover trench to keep in humidity

    • Curing compound spray, polyethylene film

    • None of the above

    Correct Answer
    A. Curing compound spray, polyethylene film
    Explanation
    After pouring cast-in-place pipes with no-joint machine, curing compound spray and polyethylene film are used to avoid drying too fast and cracking. Curing compound spray helps in retaining moisture in the concrete, preventing it from drying too quickly. Polyethylene film acts as a barrier, keeping the moisture trapped and allowing for a slow and controlled curing process. Both these methods ensure that the concrete dries evenly and reduces the risk of cracking.

    Rate this question:

  • 48. 

    What is NOT used to prevent erosion?

    • Hydroseeding

    • Fiber rolls

    • Sand or gravel bags

    • Pumping

    Correct Answer
    A. Pumping
    Explanation
    Pumping is not used to prevent erosion. Pumping refers to the process of moving water from one location to another, typically for irrigation or drainage purposes. It does not directly address erosion control measures such as hydroseeding, which involves spraying a mixture of seed, mulch, and fertilizer onto the soil surface to promote vegetation growth, fiber rolls that act as barriers to slow down water flow and trap sediment, or sand or gravel bags that are used to create barriers and stabilize slopes.

    Rate this question:

  • 49. 

    What does the surveyor stakes represent? 

    • Flow line only

    • The undercut for bedding material

    • Off-set of flow line

    • Cut and fill

    Correct Answer
    A. Flow line only
    Explanation
    The surveyor stakes represent the flow line only. Flow line refers to the elevation or level at which water would flow if it were present. The surveyor stakes are used to mark this specific level, allowing for accurate measurements and calculations in construction or engineering projects that involve water drainage or management. The stakes do not represent the undercut for bedding material, the off-set of flow line, or the cut and fill aspects of the project.

    Rate this question:

Quiz Review Timeline (Updated): Mar 21, 2023 +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 21, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Feb 15, 2013
    Quiz Created by
    23kfgn98
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.