Contractors'/Consultants' Materials Engineer - Test #1

Approved & Edited by ProProfs Editorial Team
The editorial team at ProProfs Quizzes consists of a select group of subject experts, trivia writers, and quiz masters who have authored over 10,000 quizzes taken by more than 100 million users. This team includes our in-house seasoned quiz moderators and subject matter experts. Our editorial experts, spread across the world, are rigorously trained using our comprehensive guidelines to ensure that you receive the highest quality quizzes.
Learn about Our Editorial Process
| By Sidneyvillaflor
S
Sidneyvillaflor
Community Contributor
Quizzes Created: 2 | Total Attempts: 2,113
Questions: 25 | Attempts: 1,273

SettingsSettingsSettings
Contractors/Consultants Materials Engineer - Test #1 - Quiz

Test # 1 - April 5, 2020 (Sunday)


Questions and Answers
  • 1. 

    A one-lane road, with a pavement width of 3.5 meters and shoulder width of 0.5 meter on each side of the pavement, was designed to have sub base and base courses with a combined thickness of 300mm. If the thickness of the sub base is a 125mm, the spreading and compaction of the subbase and base courses shall be carried out in:

    • A.

      2 layers over the full width of 3.5 m

    • B.

      2 layers over the full width of 4.5 m

    • C.

      3 layers over the full width of 3.5 m

    • D.

      3 layers over the full width of 4.5 m

    Correct Answer
    D. 3 layers over the full width of 4.5 m
    Explanation
    The correct answer is 3 layers over the full width of 4.5 m. This is because the pavement width is 3.5 m and there is a shoulder width of 0.5 m on each side. Therefore, the total width of the road including the pavement and shoulders is 4.5 m. The combined thickness of the sub base and base courses is 300 mm, and since the thickness of the sub base is 125 mm, the remaining thickness for the base course is 175 mm. To achieve this thickness, it is necessary to carry out the spreading and compaction in 3 layers over the full width of 4.5 m.

    Rate this question:

  • 2. 

    Sampling of the freshly mixed concrete should be taken on the ______ batch discharge of the transit mixer?

    • A.

      Middle

    • B.

      First

    • C.

      Last

    • D.

      Second

    • E.

      Third

    Correct Answer
    A. Middle
    Explanation
    The sampling of the freshly mixed concrete should be taken on the middle batch discharge of the transit mixer. This is because the middle batch represents a more representative sample of the overall concrete mixture. The first batch may not be fully mixed, while the last batch may have settled or segregated during transportation. Taking the sample from the middle batch ensures that it is a fair representation of the entire mixture.

    Rate this question:

  • 3. 

    How many times per layer should a concrete specimen molded in a 6” x 6” x 21” beam mold be rodded?

    • A.

      63 times

    • B.

      25 times

    • C.

      50 times

    • D.

      75 times

    Correct Answer
    A. 63 times
    Explanation
    A concrete specimen molded in a beam mold should be rodded multiple times per layer to ensure proper compaction and removal of air voids. The correct answer of 63 times suggests that the concrete should be rodded 63 times in each layer of the mold to achieve the desired density and strength. This ensures that the concrete is evenly distributed and free of any potential weak spots caused by inadequate compaction.

    Rate this question:

  • 4. 

    The submission of any type of samples in the laboratory, what should you accomplished and to be submitted together with the samples?

    • A.

      Sample card

    • B.

      Materials logbook

    • C.

      Letter

    • D.

      Form

    Correct Answer
    A. Sample card
    Explanation
    When submitting any type of samples in the laboratory, it is important to include a sample card along with the samples. A sample card provides important information about the samples such as the type of sample, its origin, and any specific instructions or requirements for testing. This helps the laboratory staff to properly handle and analyze the samples. Including a sample card ensures that the samples are accurately identified and processed, leading to reliable and accurate test results.

    Rate this question:

  • 5. 

    What is the minimum average strength requirement for non load bearing concrete hollow blocks?

    • A.

      600 psi

    • B.

      500 psi

    • C.

      1000 psi

    • D.

      550 psi

    Correct Answer
    A. 600 psi
    Explanation
    The minimum average strength requirement for non load-bearing concrete hollow blocks is 600 psi. This means that the blocks should have a compressive strength of at least 600 pounds per square inch to ensure their durability and ability to withstand non-load-bearing applications. A higher psi value indicates a stronger block that can withstand more pressure and is less likely to crack or break under normal use.

    Rate this question:

  • 6. 

    Concrete in the area represented by the cores will be consider adequate if the average strength of the cores is equal to at least ________ of the specified strength, f’c and no single core is less than 75% of f’c.

    • A.

      85%

    • B.

      75%

    • C.

      80%

    • D.

      70%

    Correct Answer
    A. 85%
    Explanation
    The concrete in the area represented by the cores will be considered adequate if the average strength of the cores is equal to at least 85% of the specified strength, f'c, and no single core is less than 75% of f'c. This means that the cores should have a minimum average strength of 85% of the specified strength and no individual core should have a strength less than 75% of the specified strength.

    Rate this question:

  • 7. 

    A department Order series of 1997 give supplement guidelines on the conduct of Project assessment by the Quality assurance units Regional Office (QAU-RO).

    • A.

       D.O. # 52

    • B.

       D.O. # 42

    • C.

       D.O. # 25

    • D.

       D.O. # 24

    Correct Answer
    A.  D.O. # 52
  • 8. 

    Using the standard Proctor test or AASHTO T-99 or moisture density relation test, what is the recommended no. of blows per layer?

    • A.

      25 blows

    • B.

      15 blows

    • C.

      63 blows

    • D.

      75 blows

    Correct Answer
    A. 25 blows
    Explanation
    The recommended number of blows per layer for the standard Proctor test or AASHTO T-99 or moisture density relation test is 25 blows.

    Rate this question:

  • 9. 

    If you are to use AASHTO T-99 method (standard proctor test) in compaction test, what is the weight of rammer to be used?

    • A.

      5.5 lb

    • B.

      4.5 lb

    • C.

      5.0 lb

    • D.

      4.0 lb

    Correct Answer
    A. 5.5 lb
    Explanation
    The weight of the rammer to be used in the compaction test using the AASHTO T-99 method (standard proctor test) is 5.5 lb.

    Rate this question:

  • 10. 

    Concrete not in place within ________ from the time the ingredients where charged into the mixing drum or that has developed initial set shall not be used.

    • A.

      90 minutes

    • B.

      45 minutes

    • C.

      30 minutes

    • D.

      60 minutes

    Correct Answer
    A. 90 minutes
    Explanation
    Concrete that has not been placed within 90 minutes from the time the ingredients were charged into the mixing drum or that has developed initial set should not be used. This is because concrete undergoes a chemical reaction called hydration, where the water and cement in the mixture react to form a solid mass. The initial set refers to the point at which the concrete starts to harden and lose its workability. After 90 minutes, the concrete may have already started to set and harden, making it unsuitable for use in construction.

    Rate this question:

  • 11. 

    Required slump for PCCP,  if vibrated.

    • A.

      10 to 40 mm

    • B.

      40 to 50 mm

    • C.

      40 to 75 mm

    • D.

      10 to 75 mm

    Correct Answer
    A. 10 to 40 mm
    Explanation
    The required slump for PCCP (Plain Cement Concrete Pavement) if vibrated is 10 to 40 mm. Slump refers to the consistency or workability of the concrete mix. A slump of 10 to 40 mm indicates that the concrete should have a medium to stiff consistency, which is suitable for vibrating and compacting the concrete during construction. This range of slump ensures that the concrete is easy to handle and place, while also providing enough stiffness to resist segregation and maintain its shape.

    Rate this question:

  • 12. 

    Flexural strength of PCCP when tested at third point.

    • A.

      550 psi

    • B.

      650 psi

    • C.

      3000 psi

    • D.

      3500 psi

    Correct Answer
    A. 550 psi
    Explanation
    The flexural strength of PCCP (prestressed concrete cylinder pipe) refers to its ability to withstand bending or flexing without breaking. When tested at the third point, the flexural strength of PCCP is found to be 550 psi. This means that the PCCP can withstand a bending force of up to 550 pounds per square inch before breaking.

    Rate this question:

  • 13. 

    Slump for a workable PCCP, if not vibrated

    • A.

      40 to 75 mm

    • B.

      10 to 40 mm

    • C.

      10 to 75 mm

    • D.

      50 to 100 mm

    Correct Answer
    A. 40 to 75 mm
    Explanation
    The correct answer is 40 to 75 mm. This range indicates the slump, or the measure of the consistency, of a workable PCCP (Portland Cement Concrete Pavement). A slump of 40 to 75 mm means that the concrete has a medium to high workability, allowing it to be easily placed and compacted without excessive segregation or bleeding. This range is commonly used for PCCP construction as it ensures that the concrete is both manageable and durable.

    Rate this question:

  • 14. 

    Bars placed perpendicular to the longitudinal joint of PCCP.

    • A.

      Tie bars

    • B.

      Dowel bars

    • C.

      Plain bars

    • D.

      Angle bars

    Correct Answer
    A. Tie bars
    Explanation
    Tie bars are used to connect and reinforce the longitudinal joint of precast concrete pavement (PCCP). These bars are placed perpendicular to the joint and help to prevent the slippage and separation of the two adjacent sections of pavement. By providing additional strength and stability, tie bars enhance the overall durability and performance of the pavement.

    Rate this question:

  • 15. 

    Vibrator shall not be operated longer than ________ in any one location. (PCCP)

    • A.

      15 seconds

    • B.

      10 seconds

    • C.

      20 seconds

    • D.

      25 seconds

    Correct Answer
    A. 15 seconds
    Explanation
    The correct answer is 15 seconds. This time limit is specified to prevent excessive vibration in a single location. Prolonged operation of a vibrator in one location can cause damage to the surrounding structures or the vibrator itself. Therefore, it is important to adhere to this time limit to ensure the safety and integrity of the construction site.

    Rate this question:

  • 16. 

    Flexural strength of PCCP when tested at mid-point.

    • A.

      4.50 Mpa

    • B.

      3.80 Mpa

    • C.

      24.1 Mpa

    • D.

      20.67 Mpa

    Correct Answer
    A. 4.50 Mpa
    Explanation
    The flexural strength of PCCP (prestressed concrete cylinder pipe) refers to its ability to withstand bending or flexing without breaking. When tested at the mid-point, the flexural strength of PCCP is measured to be 4.50 Mpa. This means that the PCCP can withstand a certain amount of bending force before it reaches its breaking point.

    Rate this question:

  • 17. 

    Class of concrete that is deposited in water.

    • A.

      Seal

    • B.

      W

    • C.

      B

    • D.

      C

    Correct Answer
    A. Seal
    Explanation
    The correct answer is "Seal." In the context of the question, the term "seal" refers to a class of concrete that is specifically designed to be deposited in water. This type of concrete is often used in underwater construction projects, such as building foundations or structures in marine environments. It is formulated to have high durability and resistance to water penetration, ensuring that it remains intact and functional even when submerged.

    Rate this question:

  • 18. 

    Sampling of Portland cement should be done in accordance with AASHTO  _________ .

    • A.

      T-127

    • B.

      T-217

    • C.

      T-172

    • D.

      T-721

    Correct Answer
    A. T-127
    Explanation
    Sampling of Portland cement should be done in accordance with AASHTO T-127. This standard provides guidelines for obtaining representative samples of Portland cement for testing purposes. It specifies the procedures for collecting samples from bulk shipments and bags, as well as the equipment and techniques to be used. Following the guidelines in AASHTO T-127 ensures that the samples obtained are representative of the cement being tested, which is crucial for accurate and reliable test results.

    Rate this question:

  • 19. 

    The depth of the weakened plane joint should at all times not be less than ___ mm,  while the width should not be more than ___  mm. (PCCP)

    • A.

      50  ,  6

    • B.

      60  ,  5

    • C.

      6    ,  50

    • D.

      5    ,  60

    Correct Answer
    A. 50  ,  6
    Explanation
    The depth of the weakened plane joint should not be less than 50 mm, while the width should not be more than 6 mm. This ensures that the weakened plane joint is of sufficient depth to allow for controlled cracking and movement, while also ensuring that it is not too wide to compromise the structural integrity of the joint.

    Rate this question:

  • 20. 

    What item number is Structure Excavation :

    • A.

      Item 103

    • B.

      Item 311

    • C.

      Item 104

    • D.

      Item 102

    Correct Answer
    A. Item 103
    Explanation
    The correct answer is item 103.

    Rate this question:

  • 21. 

    What item number is AGGREGATE SURFACE COURSE :

    • A.

      Item 300

    • B.

      Item 311

    • C.

      Item 301

    • D.

      Item 201

    Correct Answer
    A. Item 300
    Explanation
    AGGREGATE SURFACE COURSE is represented by Item 300.

    Rate this question:

  • 22. 

    If the required thickness for subbase or base is 150 mm or less, this maybe spread and compacted in.

    • A.

      1 layer

    • B.

      2 layers

    • C.

      3 layers

    • D.

      4 layers

    Correct Answer
    A. 1 layer
    Explanation
    If the required thickness for the subbase or base is 150 mm or less, it can be spread and compacted in just one layer. This means that the material can be evenly distributed and compressed effectively in a single application. Using multiple layers in this case would not be necessary or efficient.

    Rate this question:

  • 23. 

    The bituminous prime coat materials should be applied by a pressure distributor at specified temperature and at an application rate ranging from:

    • A.

      1 to 2 liters / sq.m.

    • B.

      2 to 3 liters / sq.m.

    • C.

      3 to 4 liters / sq.m.

    • D.

      Less than 1 liter / sq.m.

    Correct Answer
    A. 1 to 2 liters / sq.m.
    Explanation
    Bituminous prime coat materials are used to prepare the surface of a road before the application of an asphalt layer. The prime coat helps to bond the existing pavement surface with the new asphalt layer. It is important to apply the prime coat at the correct temperature and application rate to ensure proper bonding and effectiveness. The specified temperature and application rate for bituminous prime coat materials range from 1 to 2 liters per square meter. This range allows for sufficient coverage and penetration of the prime coat material without excessive wastage or insufficient application.

    Rate this question:

  • 24. 

    Unsuitable materials are soils with liquid limit exceeding ____ and/or plasticity index exceeding ____ .

    • A.

      80  ,  55

    • B.

      55  ,  80

    • C.

      80  ,  80

    • D.

      60  ,  15

    Correct Answer
    A. 80  ,  55
  • 25. 

    Determine the asphalt content, Given: Weight of original sample = 1140 g  ,      Weight after Extraction  = 980 g   ,      Original Weight of filler ring =  30 g  ,      Increase of Weight in filler ring =  30 g   

    • A.

      5.55

    • B.

      3.33

    • C.

      4.45

    • D.

      6.55

    Correct Answer
    A. 5.55

Quiz Review Timeline +

Our quizzes are rigorously reviewed, monitored and continuously updated by our expert board to maintain accuracy, relevance, and timeliness.

  • Current Version
  • Mar 20, 2023
    Quiz Edited by
    ProProfs Editorial Team
  • Apr 04, 2020
    Quiz Created by
    Sidneyvillaflor
Back to Top Back to top
Advertisement
×

Wait!
Here's an interesting quiz for you.

We have other quizzes matching your interest.