A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package.
B. You should use Rolling Wave Planning to determine the correct sequencing for long-term items.
C. You should use Rolling Wave Planning to help you organize team member s activities within a large project group.
D. You should use Rolling Wave Planning to help you determine which activities are more important and should be done first.

This question is part of PMP Lite Mock Exam 1
Asked by Agilep, Last updated: May 30, 2020

+ Answer
Request

1 Answer

agilep

Agilep

Answered Jul 28, 2018

A. You should use Rolling Wave Planning to help you achieve the appropriate level of detail in each work package.

A - Rolling Wave Planning is a technique used to create a more detailed work plan while keeping the right level of detail for each activity-activities happening sooner have more detail than those further in future. [PMBOK Page 135] [Project Time Management]
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.