We have sent an email with your new password.

Close this window

Ch 6 Pared Down

33 Questions  I  By Quizcreationhelp
Ch 6 pared down

  
Changes are done, please start the quiz.


Question Excerpt

Removing question excerpt is a premium feature

Upgrade and get a lot more done!
1.  Network diagrams are the preferred technique for showing activity discretionary dependencies.
A.
B.
2.  The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project.
A.
B.
C.
D.
3.  The activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets all include information that affect ____.
A.
B.
C.
D.
4.  A work package represents the level of work that the project manager monitors and controls.
A.
B.
5.  Every item on the WBS needs to be on the network diagram.
A.
B.
6.  Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of many projects.
A.
B.
C.
D.
7.  The main outputs of estimating activity resources include the activity list and attributes, project scope statement, milestone list, and organizational process assets.
A.
B.
8.  ____ is a network diagramming technique used to predict total project duration.
A.
B.
C.
D.
9.  The main outputs of the ____ process are an activity list, activity attributes, and milestone list.
A.
B.
C.
D.
10.  Project managers often illustrate progress with a ____ showing key deliverables and activities.
A.
B.
C.
D.
11.  Activity information is not a required input to the other time management processes.
A.
B.
12.  Critical chain scheduling protects tasks on the critical chain from being delayed by using ____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
A.
B.
C.
D.
13.  ____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.
A.
B.
C.
D.
14.  By using the PERT weighted average for each activity duration estimate, the total project duration estimate does not account for the risk or uncertainty in the individual activity estimates.
A.
B.
15.  ____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
A.
B.
C.
D.
16.  ______ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables.
A.
B.
C.
D.
17.  The ____ approach is best suited to project managers who have vast technical insight and a big-picture perspective.
A.
B.
C.
D.
18.  In a Gantt chart created in Microsoft Project, a black diamond symbol represents a milestone.
A.
B.
19.  ____ occur when two or more activities follow a single node.
A.
B.
C.
D.
20.  The main outputs of ____ are accepted deliverables and change requests.
A.
B.
C.
D.
21.  The ____ should list and describe all of the deliverables required for the project.
A.
B.
C.
D.
22.  ____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities.
A.
B.
C.
D.
23.  ____ involves controlling and managing changes to the project schedule.
A.
B.
C.
D.
24.  The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
A.
B.
C.
D.
25.  The ____ is a network diagramming technique in which boxes represent activities.
A.
B.
C.
D.
26.  A project team always organizes the WBS around project products.
A.
B.
27.  An up-to-date ____ is an important document for developing and confirming a common understanding of the project scope.
A.
B.
C.
D.
28.  Start-to-finish relationships are the most common type of relationships.
A.
B.
29.  ____ states that work expands to fill the time allowed.
A.
B.
C.
D.
30.  ____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
A.
B.
C.
D.
31.  ____ involves analyzing activity sequences, activity resource estimates, and activity duration.
A.
B.
C.
D.
32.  The project scope statement provides the basis for planning and managing project schedules, costs, resources, and changes.
A.
B.
33.  ____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date.
A.
B.
C.
D.
Back to top

Removing ad is a premium feature

Upgrade and get a lot more done!
Take Another Quiz