ProProfs Quiz Maker

Ch 6 pared down

33 Questions  I  37 Attempts  I  Created By quizcreationhelp 446 days ago
Name

  


Question Excerpt From Ch 6 pared down
Q.1) 
The main outputs of estimating activity resources include the activity list and attributes, project scope
statement, milestone list, and organizational process assets.
A.
B.
Q.2)  Activity information is not a required input to the other time management processes.
A.
B.
Q.3)  Network diagrams are the preferred technique for showing activity discretionary dependencies.
A.
B.
Q.4)  Every item on the WBS needs to be on the network diagram.
A.
B.
Q.5)  Start-to-finish relationships are the most common type of relationships.
A.
B.
Q.6)  In a Gantt chart created in Microsoft Project, a black diamond symbol represents a milestone.
A.
B.
Q.7) 
By using the PERT weighted average for each activity duration estimate, the total project duration
estimate does not account for the risk or uncertainty in the individual activity estimates.
A.
B.
Q.8) 
______ involves identifying the specific activities that the project team members and stakeholders must
perform to produce the project deliverables.
A.
B.
C.
D.
Q.9) 
The main outputs of the ____ process are an activity list, activity attributes, and milestone list.
A.
B.
C.
D.
Q.10)  ____ involves analyzing activity sequences, activity resource estimates, and activity duration.
A.
B.
C.
D.
Q.11)  ____ involves controlling and managing changes to the project schedule.
A.
B.
C.
D.
Q.12) 
The ____ provide(s) schedule-related information about each activity, such as predecessors,
successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates,
and assumptions related to the activity.
A.
B.
C.
D.
Q.13)  ____ occur when two or more activities follow a single node.
A.
B.
C.
D.
Q.14)  The ____ is a network diagramming technique in which boxes represent activities.
A.
B.
C.
D.
Q.15) 
The activity list, activity attributes, activity resource requirements, resource calendars, project scope
statement, enterprise environmental factors, and organizational process assets all include information
that affect ____.
A.
B.
C.
D.
Q.16)  ____ is a network diagramming technique used to predict total project duration.
A.
B.
C.
D.
Q.17) 
The critical path is the ____ path through a network diagram, and it represents the ____ time it takes
to complete a project.
A.
B.
C.
D.
Q.18) 
____ is the amount of time an activity can be delayed without delaying the early start date of any
immediately following activities.
A.
B.
C.
D.
Q.19) 
____ is the amount of time an activity can be delayed from its early start without delaying the planned
project finish date.
A.
B.
C.
D.
Q.20) 
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule
compression for the least incremental cost.
A.
B.
C.
D.
Q.21) 
____ is a method of scheduling that considers limited resources when creating a project schedule and
includes buffers to protect the project completion date.
A.
B.
C.
D.
Q.22) 
Critical chain scheduling protects tasks on the critical chain from being delayed by using ____, which
consist of additional time added before tasks on the critical chain that are preceded by
non-critical-path tasks.
A.
B.
C.
D.
Q.23)  ____ states that work expands to fill the time allowed.
A.
B.
C.
D.
Q.24)  Project managers often illustrate progress with a ____ showing key deliverables and activities.
A.
B.
C.
D.
Q.25) 
The project scope statement provides the basis for planning and managing project schedules, costs,
resources, and changes.
A.
B.
Q.26)  A project team always organizes the WBS around project products.
A.
B.
Q.27)  A work package represents the level of work that the project manager monitors and controls.
A.
B.
Q.28) 
____ involves reviewing the project charter, requirements documents, and organizational process
assets to create a scope statement, adding more information as requirements are developed and change
requests are approved.
A.
B.
C.
D.
Q.29)  The main outputs of ____ are accepted deliverables and change requests.
A.
B.
C.
D.
Q.30) 
An up-to-date ____ is an important document for developing and confirming a common understanding
of the project scope.
A.
B.
C.
D.
Q.31) 
Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of
many projects.
A.
B.
C.
D.
Q.32)  The ____ should list and describe all of the deliverables required for the project.
A.
B.
C.
D.
Q.33) 
The ____ approach is best suited to project managers who have vast technical insight and a
big-picture perspective.
A.
B.
C.
D.

Take this quiz by clicking Start button on top.



Please login to post comments.
After login, we will forward you back to this quiz.

Upgrade and get a lot more done!
Upgrade

 Adding Media is not included in your current plan

Upgrade and get a lot more:
  • Upload documents


  • Upload Videos


  • Upload Powerpoints


  • Add training/teaching material



Upgrade