Project Management Questions and Answers (Q&A)

John Smith
Answered: Aug 15, 2020
Establishing a cost baseline for tracking project performance-the cost control process does not involve establishing a cost baseline for tracking project performance. this is part of the cost...Read More

1 Answer

336 views
Krystle
Answered: Aug 15, 2020
Quality is the process of completing the scope to meet stated or implied needs.

1 Answer

333 views
Wyatt Williams
Answered: Aug 15, 2020
Project Scope Statement

1 Answer

328 views
John Smith
Answered: Aug 15, 2020
Corrective actions-corrective actions are not an input used in scope verification. corrective actions are steps taken to bring future performance in line with the project plan. scope verification...Read More

2 Answers

327 views
John Smith
Answered: Aug 15, 2020
Project records-project records consist of all documentation and correspondence relating to the project including internal notes and memos. this is an output of the information distribution process....Read More

1 Answer

325 views
John Smith
Answered: Aug 15, 2020
Define scope, define activities, plan quality

The correct order is scope definition, activity definition, and then plan quality.

1 Answer

325 views
John Smith
Answered: Aug 15, 2020
Cost baseline-cost baseline is not an output of the cost control process. cost baseline is anoutput of the cost budgeting process and an input to the cost control process.outputs of cost control...Read More

1 Answer

320 views
Matz Lewis Clark, College student
Answered: Mar 28, 2019
The correct answer to this question is B, include project plan updates. Integrated change control is the process of reviewing all change requests, approving changes, and changes to the...Read More

3 Answers

319 views
John Smith
Answered: Aug 15, 2020
$26,000

$26,000 is the variance. This is calculated by subtracting the actual costs of $65,000 from the earned value of $39,000. EV is calculated by taking the 30 percent completion of...Read More

1 Answer

315 views
Krystle
Answered: Aug 15, 2020
Not all processes and procedures in the PMBOK Guide are actually required on all projects.

A. Not all information in the PMBOK Guide should be applied uniformly to all projects. It is the...Read More

1 Answer

313 views
L. Sevigny, Doctor
Answered: Feb 11, 2019
Often times, project managers are hired in order to make sure that the production process is being run smoothly. This is to make sure that the employees in all aspects of the production in their...Read More

2 Answers

303 views
Sihemsmida
Answered: Aug 15, 2020
Forward pass calculations yield the earliest and the latest start and finish times of various activities.

1 Answer

299 views
Wyatt Williams
Answered: Aug 15, 2020
Prevention costs – appraisal costs – failure costs

1 Answer

297 views