Quiz Chapters 1-9

46 Questions  I  By Smith457

  
Changes are done, please start the quiz.


Question Excerpt

Removing question excerpt is a premium feature

Upgrade and get a lot more done!
1.  __________predict future project status and progress based on past information and trends.
A.
B.
C.
2.  A_______is another name for a project close-out meeting.
A.
B.
C.
3.  The___________ should include requirements for formal acceptance and closure of contracts.
A.
B.
C.
4.  Contract close involves completion and settlement of contracts and resolution of __________.
A.
B.
C.
5.  ______change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.
A.
B.
C.
6.  When a process is out of control, variations in the results of the process are caused by _____events.
A.
B.
C.
7.  Given the earned value and _, you can see how well the project team is meeting schedule goals and forecast when the project will be completed based on past schedule performance.
A.
B.
C.
8.  Pareto analysis is sometimes referred to as the _____rule, meaning that 80 percent of problems are often due to 20 percent of the causes.
A.
B.
C.
9.  How do you determine the duration of the Critical Path? It is the longest path.
10.  If a project is running behind schedule and over budget, where will the estimate at completion point be on the earned value chart relative to the budget at completion point?
A.
B.
C.
11.  In earned value management, a baseline includes __________(WBS tasks), time (start and finish estimates for each task), and cost information (cost estimates for each task).
A.
B.
C.
12.  As part of project closing it is important to plan for and execute a smooth__________of the project into normal operations of the company.
A.
B.
C.
13.  The approved time estimate for a project can be divided by the______performance index to calculate when the project will be completed.
A.
B.
C.
14.  _________issues cause the most conflict over the life of projects.
A.
B.
C.
15.  Project___are usually most interested in making sure that final products, services, or results are delivered and transitioned to the appropriate part of the organization.
A.
B.
C.
16.  ______involves formal acceptance of the completed project scope by the stakeholders.
A.
B.
C.
17.  A__________are reviews often performed during contract closure to identify lessons learned in the entire procurement process.
A.
B.
C.
18.  Answering questions like "Reflect on whether or not you met the project success criteria" and "Describe one example of what went wrong on this project" are found in a __________report.
A.
B.
C.
19.  Risk reassessment, risk audits, variance and trend analysus, technical performance measurements, reserve analysis, and status meetings or periodic risk reviews are all tools and techniques for performing _______monitoring and control.
A.
B.
C.
20.  According to Andy Crowe's research, the best project managers send________emails per day and spend______time in meetings than typical project managers.
A.
B.
C.
21.  The main monitoring and controlling task performed as part of project cost management is controlling ________.
A.
B.
C.
22.  What pre-initiating task can be done to justify investing in a project?
A.
B.
C.
23.  __________is an estimate of the value of the physical work actually completed.
A.
B.
C.
24.  Answering questions such as, "What will you do differently on the next project based on your experience working on this project?" is part of a _____.
A.
B.
C.
25.  Which of the following statements is false?
A.
B.
C.
26.  What is the Pert formula?
27.  You want to see if there is a relationship between two variables, like time of day and worker productivity. What type of quality control tool could you use to visualize this information?
A.
B.
C.
28.  ___________change orders are oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.
A.
B.
C.
29.  If seven data points in a row are all below the mean, above the mean, increasing or decreasing, it is a vioation of _______.
A.
B.
C.
30.  A_____chart compares planned and actual project schedule information.
A.
B.
C.
31.  When developing a transition plan, the project, the project team should exclude managers in affected operating departments.
A.
B.
32.  In the context of earned value management, the _____cost is the total direct and indirect costs incurred in accomplishing work on an activity during a given period.
A.
B.
C.
33.  Many organizations are working hard to improve the ____process since human capital is one of their key assets.
A.
B.
C.
34.  Two tools to assist in contract closure are ______audits and a records management system.
A.
B.
C.
35.  When developing a ____plan, the project team should work with managers in affected operating departments, and the contents of the plan should be tailored to fit the support needs of the project.
A.
B.
C.
36.  Which of the following is a category under portfolio best practices?
A.
B.
C.
37.  _______reports describe where the project stands at a specific point in time.
A.
B.
C.
38.  Changes related to procurred items should be__________.
A.
B.
C.
39.  What is the Communication Channel formula?  
40.  _________is a project performance measurement technique that integrates scope, time and cost data.
A.
B.
C.
41.  What is the Pert formula  Optimistic time + 4*(times) most likely time + pessimistic time / (divided) by 6
42.  Assigning a project manager from operations to lead projects that affect operations is considered a best practice.
A.
B.
43.  Which of the following is not advice for closing projects or phases?
A.
B.
C.
44.  ______are unplanned responses to risk events.
A.
B.
C.
45.  A___________chart is a histogram that can help you identify and prioritize problem areas.
A.
B.
C.
46.  Which of the following is not a tool or technique for managing project teams?
A.
B.
C.
Back to top


to post comments.

Removing ad is a premium feature

Upgrade and get a lot more done!
Take Another Quiz