As part of the CMMI Awareness Program we have organized a quiz related to the CMMI level 3 certification. All the information required to answer these questions are available in the CMMI Mails, Posters, Tit Bits and the CMMI Wiki. Watch out for these and answer the questions to Win Exciting prizes !!! So what are you waiting for? Put on your thinking caps and post your answers as soon as possible!!!

Questions and Answers
  • 1. 
    Which one of the following Process Area is not a requirement for CMMI Level 2?
    • A. 

      Project Monitoring and Control

    • B. 

      Project Planning

    • C. 

      Process and Product Quality Assurance

    • D. 

      Integrated Project Management

    • E. 

      None of the above

  • 2. 
    To satisfy a Process Area, we should satisfy its Specific Goals and _ Goals
    • A. 

      Inclusive

    • B. 

      Exclusive

    • C. 

      Generic

    • D. 

      Defined

    • E. 

      None of the above

  • 3. 
    CMMI can be implemented two ways : staged and
    • A. 

      Non-staged

    • B. 

      Contiguous

    • C. 

      Continuous

    • D. 

      Staggered

    • E. 

      None of the above

  • 4. 
    OPF stands for:
    • A. 

      Organizational Process Focus

    • B. 

      Original Process Focus

    • C. 

      Organizations’ Process Facilities

    • D. 

      On-site People Focus

    • E. 

      None of the above

  • 5. 
    Which among the Following is not a CMMI Level 3 Process Area?
    • A. 

      Product Integration

    • B. 

      Requirements Development

    • C. 

      Risk Management

    • D. 

      Quantitative Project Management

  • 6. 
    In simple terminology Level 3 is called as "Defined" , level 4 as "-" and level 5 as "-"
    • A. 

      Formal, Inclusive

    • B. 

      Formal, Quantitive

    • C. 

      Managed, Superlative

    • D. 

      Managed, Optimizing

  • 7. 
    CMMI as a model is defined and controlled by
    • A. 

      KPMG

    • B. 

      SEI

    • C. 

      ISO

    • D. 

      QAI

  • 8. 
    • A. 

      Three

    • B. 

      Five

    • C. 

      Twelve

    • D. 

      Twenty four

  • 9. 
    GSP CMMI software development life cycle has _ stages
    • A. 

      Seven

    • B. 

      Eight

    • C. 

      Nine

    • D. 

      Twelve

  • 10. 
    One of the following is not a required template to be completed as part of the "Initiate" stage
    • A. 

      Product requirements

    • B. 

      Estimation template

    • C. 

      Project schedule

    • D. 

      Communication plan