  • 1. 
    A wbs numbering system allows project staff to :
    • A. 

      Systematically estimate costs of wbs elements

    • B. 

      Provide project justification

    • C. 

      Identify the level at which individual items are found

    • D. 

      Use it in project management software

  • 2. 
    The WBS can BEST be thought of as an effective aid for -------------------- communications
    • A. 

      Team

    • B. 

      Project manager

    • C. 

      Customer

    • D. 

      Stakeholder

  • 3. 
    To manage a project effectively, work should be broken down to small pieces. Which of the following does NOT describe how far to to decompose the work?
    • A. 

      Until it has a meaningful conclusion

    • B. 

      Until it cannot be logically subdivided further

    • C. 

      Until it can be done by one person

    • D. 

      Until it can be realistically estimated

  • 4. 
    The most valuable outcome / result of creating a wbs is:
    • A. 

      A bar chart

    • B. 

      Team buy in

    • C. 

      Activities

    • D. 

      List of Risks