1.
An element of work normally found on the WBS that has an expected duration, a cost, and resource requirements
Correct Answer
A. Activity
Explanation
An activity is an element of work that is typically found on the Work Breakdown Structure (WBS) and has an expected duration, a cost, and resource requirements. It represents a specific task or set of tasks that need to be completed in order to achieve the project objectives. Activities are essential for creating project schedules and managing project time effectively. They help in identifying the sequence of tasks, allocating resources, estimating costs, and tracking progress. Therefore, the correct answer is Activity.
2.
A tabulation of activities to be included on a project schedule
Correct Answer
C. Activity List
Explanation
The given correct answer is "Activity List". In project management, an activity list is a tabulation of all the activities that need to be included in a project schedule. It provides a comprehensive breakdown of the tasks or actions that need to be performed in order to complete the project successfully. The activity list serves as a reference for project managers and team members to understand the scope of work and plan accordingly. It is an essential component of project planning and helps in organizing and sequencing the project activities effectively.
3.
A significant event that normally has no duration.
Correct Answer
B. Milestone
Explanation
A milestone is a significant event that marks a major achievement or progress towards a goal. Unlike other options like Critical Path, Effort, or Schedule, a milestone does not have a specific duration associated with it. It represents a point in time or a specific accomplishment rather than a period of time. Therefore, a milestone is the correct answer for this question.
4.
It often takes several activities and a lot of work to complete a milestone.
Correct Answer
A. True
Explanation
The statement suggests that completing a milestone typically requires multiple activities and a significant amount of effort. This implies that milestones are not easily achieved and often involve a series of tasks or steps. Therefore, the correct answer is true.
5.
Involves reviewing activities and determining dependencies.
Correct Answer
A. Activity Sequencing
Explanation
Activity sequencing involves reviewing activities and determining dependencies. This process helps in determining the order in which activities should be performed to ensure a smooth flow of work. By reviewing activities and their dependencies, project managers can identify any activities that need to be completed before others can start. This helps in creating a logical sequence of activities and ensures that the project progresses efficiently. Activity sequencing is an important step in project planning and scheduling as it helps in identifying the critical path and determining the project timeline.
6.
A schematic display of the logical relationships among, or sequencing of, project activities.
Correct Answer
C. Network Diagram
Explanation
A network diagram is a visual representation that shows the logical relationships and sequencing of project activities. It helps to illustrate the flow and dependencies of tasks, allowing project managers to understand the critical path and identify potential bottlenecks or delays. This diagram is an essential tool for planning and managing projects effectively, as it provides a clear overview of the project's timeline and helps in coordinating activities and resources.
7.
Includes the actual amount of time worked on an activity plus the elapsed time
Correct Answer
C. Duration
Explanation
Duration refers to the actual amount of time worked on an activity, including both the time spent actively working on the task and any time that has passed since the activity started. It represents the total time taken to complete the activity, regardless of any breaks or interruptions that may have occurred. Duration is an important factor in project management as it helps in estimating the overall timeline and scheduling of activities.
8.
Which of the following is NOT a SMART Criteria
Correct Answer
B. Meaningful
Explanation
The SMART criteria is a framework used to set goals that are Specific, Measurable, Achievable, Relevant, and Time-bound. "Meaningful" is not one of the criteria in the SMART framework. The other options, Specific, Realistic, and Time-bound, are all part of the SMART criteria.
9.
The amount of time an activity can be delayed without delaying the early start of any immediately following activities.
Correct Answer
A. Free Slack
Explanation
Free slack refers to the amount of time that an activity can be delayed without causing any delay to the early start of the activities that follow it. In other words, it is the amount of time that an activity can be delayed without affecting the project's overall schedule. Free slack is calculated by subtracting the duration of the activity from the total slack available. It helps project managers in identifying activities that have flexibility in their schedules and allows them to prioritize tasks accordingly.
10.
Activities by obtaining the greatest amount of schedule compression for the least incremental cost.
Correct Answer
B. Crashing
Explanation
Crashing is the correct answer because it refers to a technique used in project management to shorten the project schedule by adding additional resources or increasing the intensity of work. This allows the project to be completed in a shorter amount of time, but it also comes with additional costs. Crashing is chosen when there is a need to complete the project as quickly as possible, and the benefits of the time saved outweigh the extra expenses incurred.