The Ultimate Questions On Project Management! Test

Welcome to the ultimate questions on project management! It is made up of some of the hardest questions that you will come across in this study that only the smartest can be able to answer. Think you belong to this class of geniuses? How about you tackle the quiz and see how high you get to score. All the best!


Questions and Answers
  • 1. 
    An element of work normally found on the WBS that has an expected duration, a cost, and resource requirements
    • A. 

      Activity

    • B. 

      Project Time Management

    • C. 

      Project Schedules

    • D. 

      Project Charter

  • 2. 
    A tabulation of activities to be included on a project schedule
    • A. 

      Project Schedules

    • B. 

      Project Charter

    • C. 

      Activity List

    • D. 

      Activity Attributes

  • 3. 
    A significant event that normally has no duration.
    • A. 

      Critical Path

    • B. 

      Milestone

    • C. 

      Effort

    • D. 

      Schedule

  • 4. 
    It often takes several activities and a lot of work to complete a milestone.
    • A. 

      True

    • B. 

      False

  • 5. 
    Involves reviewing activities and determining dependencies.
    • A. 

      Activity Sequencing

    • B. 

      Activity Definition

    • C. 

      Activity Duration Sequencing

    • D. 

      Schedule development

  • 6. 
    A schematic display of the logical relationships among, or sequencing of, project activities.
    • A. 

      Project Charter

    • B. 

      Network Sequencing

    • C. 

      Network Diagram

  • 7. 
    Includes the actual amount of time worked on an activity plus the elapsed time
    • A. 

      Activity

    • B. 

      Effort

    • C. 

      Duration

    • D. 

      Slack

  • 8. 
    Which of the following is NOT a SMART Criteria
    • A. 

      Specific

    • B. 

      Meaningful

    • C. 

      Realistic

  • 9. 
    The amount of time an activity can be delayed without delaying the early start of any immediately following activities.
    • A. 

      Free Slack

    • B. 

      Total Slack

    • C. 

      Duration

  • 10. 
    Activities by obtaining the greatest amount of schedule compression for the least incremental cost.
    • A. 

      Shortening

    • B. 

      Crashing

    • C. 

      Fast Tracking