The Ultimate Questions On Project Management! Test - Quiz

Welcome to the ultimate questions on project management! It is made up of some of the hardest questions that you will come across in this study that only the smartest can be able to answer. Think you belong to this class of geniuses? How about you tackle the quiz and see how high you get to score. All the best!


Questions and Answers
  • 1. 

    An element of work normally found on the WBS that has an expected duration, a cost, and resource requirements

    • A. 

      Activity

    • B. 

      Project Time Management

    • C. 

      Project Schedules

    • D. 

      Project Charter

    Correct Answer
    A. Activity
    Explanation
    An activity is an element of work that is typically found on the Work Breakdown Structure (WBS) and has an expected duration, a cost, and resource requirements. It represents a specific task or set of tasks that need to be completed in order to achieve the project objectives. Activities are essential for creating project schedules and managing project time effectively. They help in identifying the sequence of tasks, allocating resources, estimating costs, and tracking progress. Therefore, the correct answer is Activity.

    Rate this question:

  • 2. 

    A tabulation of activities to be included on a project schedule

    • A. 

      Project Schedules

    • B. 

      Project Charter

    • C. 

      Activity List

    • D. 

      Activity Attributes

    Correct Answer
    C. Activity List
    Explanation
    The given correct answer is "Activity List". In project management, an activity list is a tabulation of all the activities that need to be included in a project schedule. It provides a comprehensive breakdown of the tasks or actions that need to be performed in order to complete the project successfully. The activity list serves as a reference for project managers and team members to understand the scope of work and plan accordingly. It is an essential component of project planning and helps in organizing and sequencing the project activities effectively.

    Rate this question:

  • 3. 

    A significant event that normally has no duration.

    • A. 

      Critical Path

    • B. 

      Milestone

    • C. 

      Effort

    • D. 

      Schedule

    Correct Answer
    B. Milestone
    Explanation
    A milestone is a significant event that marks a major achievement or progress towards a goal. Unlike other options like Critical Path, Effort, or Schedule, a milestone does not have a specific duration associated with it. It represents a point in time or a specific accomplishment rather than a period of time. Therefore, a milestone is the correct answer for this question.

    Rate this question:

  • 4. 

    It often takes several activities and a lot of work to complete a milestone.

    • A. 

      True

    • B. 

      False

    Correct Answer
    A. True
    Explanation
    The statement suggests that completing a milestone typically requires multiple activities and a significant amount of effort. This implies that milestones are not easily achieved and often involve a series of tasks or steps. Therefore, the correct answer is true.

    Rate this question:

  • 5. 

    Involves reviewing activities and determining dependencies.

    • A. 

      Activity Sequencing

    • B. 

      Activity Definition

    • C. 

      Activity Duration Sequencing

    • D. 

      Schedule development

    Correct Answer
    A. Activity Sequencing
    Explanation
    Activity sequencing involves reviewing activities and determining dependencies. This process helps in determining the order in which activities should be performed to ensure a smooth flow of work. By reviewing activities and their dependencies, project managers can identify any activities that need to be completed before others can start. This helps in creating a logical sequence of activities and ensures that the project progresses efficiently. Activity sequencing is an important step in project planning and scheduling as it helps in identifying the critical path and determining the project timeline.

    Rate this question:

  • 6. 

    A schematic display of the logical relationships among, or sequencing of, project activities.

    • A. 

      Project Charter

    • B. 

      Network Sequencing

    • C. 

      Network Diagram

    Correct Answer
    C. Network Diagram
    Explanation
    A network diagram is a visual representation that shows the logical relationships and sequencing of project activities. It helps to illustrate the flow and dependencies of tasks, allowing project managers to understand the critical path and identify potential bottlenecks or delays. This diagram is an essential tool for planning and managing projects effectively, as it provides a clear overview of the project's timeline and helps in coordinating activities and resources.

    Rate this question:

  • 7. 

    Includes the actual amount of time worked on an activity plus the elapsed time

    • A. 

      Activity

    • B. 

      Effort

    • C. 

      Duration

    • D. 

      Slack

    Correct Answer
    C. Duration
    Explanation
    Duration refers to the actual amount of time worked on an activity, including both the time spent actively working on the task and any time that has passed since the activity started. It represents the total time taken to complete the activity, regardless of any breaks or interruptions that may have occurred. Duration is an important factor in project management as it helps in estimating the overall timeline and scheduling of activities.

    Rate this question:

  • 8. 

    Which of the following is NOT a SMART Criteria

    • A. 

      Specific

    • B. 

      Meaningful

    • C. 

      Realistic

    Correct Answer
    B. Meaningful
    Explanation
    The SMART criteria is a framework used to set goals that are Specific, Measurable, Achievable, Relevant, and Time-bound. "Meaningful" is not one of the criteria in the SMART framework. The other options, Specific, Realistic, and Time-bound, are all part of the SMART criteria.

    Rate this question:

  • 9. 

    The amount of time an activity can be delayed without delaying the early start of any immediately following activities.

    • A. 

      Free Slack

    • B. 

      Total Slack

    • C. 

      Duration

    Correct Answer
    A. Free Slack
    Explanation
    Free slack refers to the amount of time that an activity can be delayed without causing any delay to the early start of the activities that follow it. In other words, it is the amount of time that an activity can be delayed without affecting the project's overall schedule. Free slack is calculated by subtracting the duration of the activity from the total slack available. It helps project managers in identifying activities that have flexibility in their schedules and allows them to prioritize tasks accordingly.

    Rate this question:

  • 10. 

    Activities by obtaining the greatest amount of schedule compression for the least incremental cost.

    • A. 

      Shortening

    • B. 

      Crashing

    • C. 

      Fast Tracking

    Correct Answer
    B. Crashing
    Explanation
    Crashing is the correct answer because it refers to a technique used in project management to shorten the project schedule by adding additional resources or increasing the intensity of work. This allows the project to be completed in a shorter amount of time, but it also comes with additional costs. Crashing is chosen when there is a need to complete the project as quickly as possible, and the benefits of the time saved outweigh the extra expenses incurred.

    Rate this question: