Lesson 15 Quiz: Building The WBS

6 Questions | Total Attempts: 41

SettingsSettingsSettings
Please wait...
Lesson Quizzes & Trivia

With this quiz we develop a WBS for the case study provided in the charter case studyhttp://bootstrapproject. Blogspot. Com/2010/04/lesson-12-charter-case-stu dy. Html


Questions and Answers
  • 1. 
    What is the best combination of activities for the following sub deliverable"Assembly plant secured"
    • A. 

      Identify suitable site;sign rental contract; prepare assembly areas

    • B. 

      Dig trenches; lay foundation; sign off assembly area

    • C. 

      Functional specification completed;components delivered

    • D. 

      Assembly staff appointed; secure assembly area

  • 2. 
    What is the best combination of activities for the following sub deliverable"Workforce appointments completed"
    • A. 

      Identify skills needed;negotiate recruitment contract;conduct plant orientation;deploy staff

    • B. 

      Conduct selection tests;staff records inspected;appointment contracts completed

    • C. 

      Performance evaluations completed;Upskilling workshops competed

  • 3. 
    What is the best combination of activities for the following sub deliverable"Component delivery check-in completed"
    • A. 

      Negotiate transport service agreement;sign transport service agreement;negotiate delivery dates;receive and sign components in

    • B. 

      Functional specification completed;components delivered

    • C. 

      Components delivered; quality check completed; component stowed

  • 4. 
    What is the best combination of activities for the following sub deliverable"Sub-component assembly completed"
    • A. 

      Components delivered; assembly line inspection; painting completed

    • B. 

      Assemble fuselage;assemble wings;fit aviation equipment;Assemble landing gear;assemble engines

    • C. 

      Paint exterior;lift engines;assemble wings;assemble tail

  • 5. 
    What is the best combination of activities for the following sub deliverable"Interior fitted"
    • A. 

      Fit seats;install communication systems;install ventilation system;install catering features

    • B. 

      Paint exterior;lift engines;assemble wings;assemble tail

    • C. 

      Check wheel base; fit landing gear;fit seats

  • 6. 
    What is the best combination of activities for the following sub deliverable"Final assembly completed"
    • A. 

      Perform quality checks;final assembly completed

    • B. 

      Join wings to fuselage;fit motors;fit landing gear;perform function checks;perform quality checks

    • C. 

      Wings fitted; engine fitting completed