Which one of the following estimation approaches is appropriate at this stage of the project?



A. Create an estimate based on the function point analysis technique and test point analysis
B. Create an estimate based on the complexity of the code
C. Create an estimate based on the credentials of the successful bidder
D. Create an estimate based on a percentage of the development effort

This question is part of ISTQB Exam
Asked by Raquell.japhta on Sep 28, 2016

+ AnswerRequest Answer
...

1 Answer

John Smith

John Smith

Answered on Sep 28, 2016

Create an estimate based on the function point analysis technique and test point analysis

####
 Reply

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.