Which of the following would be considered a defect?



A. A work package that does not meet the requirements, but is later deemed acceptable by the customer
B. A mistake made by a team member
C. A system component that was designed to specifications, but the entire system does not work properly
D. Any change request

This question is part of

Stockton PMP Mock Exam
Asked by Mackenzie, Last updated: Mar 29, 2020

+ Answer
Request

1 Answer

John Smith

John Smith

Answered Sep 12, 2016

A work package that does not meet the requirements, but is later deemed acceptable by the customer-monitoring & controlling - quality managementremember a defect is any deliverable that does not meet the documented requirements. choice a clearly is the only choice that matches this description. just because a customer later decides that it is acceptable does not negate the fact that it did not meet the requirements and thus is a defect. in choice c, even if the deliverable doesnt work properly, if it meets the requirements then it is not defective. change requests are not necessarily derived from defects.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.