Which of the following would be helpful in determining the total duration of your project?



A. Schedule management plan
B. WBS
C. Network diagram
D. Scope statement

This question is part of

Stockton PMP Mock Exam
Asked by Brayden, Last updated: Feb 27, 2020

+ Answer
Request

1 Answer

John Smith

John Smith

Answered Sep 12, 2016

Network diagram-monitoring & controlling - time managementthe project schedule network diagram displays the relationships among activities (dependencies), thus it would be the most helpful in determining the total duration of the project. the schedule management plan would tell you how to go about doing the schedule planning, it would not contain information about project duration though. the wbs and scope statement would contain information about project scope, but not sufficient detail about individual activities to determine the project duration.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.