Susan has just been appointed as the project manager for this software project and realizes that no WBS has been created and the project is entering the construction phase. What should she do?



A. She should report this to senior management and start work on the construction phase
B. She should get details from WBS dictionary to create the WBS
C. The WBS should be created first and then construction work started
D. She should refuse to manage the project without a WBS

This question is part of

Stockton PMP Mock Exam
Asked by Mia, Last updated: Mar 29, 2020

+ Answer
Request

1 Answer

John Smith

John Smith

Answered Sep 12, 2016

The wbs should be created first and then construction work started-planning - scope managementthe problem here is that the wbs had not been prepared. the correct choice c states that she should first create a wbs and then start the contruction phase. choice a talks about reporting the matter to senior management but that does not solve the problem. choice b talks about finding information from the wbs dictionary, but the wbs dictionary is dependent on the wbs. choice d is also wrong as it talks about refusing to manage the project, which does not solve the problem. moreover, the role of project manager is one of a proactive problem solver.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.