Your change control board (CCB) has just approved a change request.

Asked by Atkins, Last updated: Apr 15, 2024

+ Answer
Request
Question menu
Vote up 1 Vote down

1 Answer

John Smith

John Smith

John Smith
John Smith

Answered Sep 12, 2016

Update the project plan to reflect the change-monitoring & controlling. Integration management. The first thing you should do after a change request is approved is to update the project documents. Once the documents are updated, then you can inform the stakeholders. After that you can go back to work and manage the project based on the approved change. Choice a is clearly wrong, because you always analyze the impact of a change prior to submitting a change request (that is likely the first question you will be asked by the CCB - what's the impact to your project?).

upvote downvote
Reply 

Advertisement
Advertisement
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader
Image Preview
Search for Google images Google Image Icon
Select a recommended image
Upload from your computer Loader

Email Sent
We have sent an email to your address "" with instructions to reset your password.