An important part of performing stakeholder analysis is documenting quantifiable expectations. Which of the following expectations is quantifiable?
A. The project Must improve customer satisfaction
B. The project should be higher quality
C. The project Must yield a 15% reduction in part cost
D. All stakeholders’ needs Must be satisfied

Asked by Jake, Last updated: Jan 13, 2020

This question is part of

PMP Framework

+ Answer
Request

3 Answers

mansour.alqubaty

Mansour.alqubaty

Answered Aug 01, 2017

C. The project must yield a 15% reduction in part cost

is the correct answer

 

John Adney

Shouldn't the answer be C? Because we are talking quantifiable (numbers). If not why?
 

John Smith

John Smith

Answered Sep 09, 2016

The project must improve customer satisfaction
A- Customer satisfaction is an important part of modern quality management.
 1

John Adney

Shouldn't the answer be C? Because we are talking quantifiable (numbers). If not why?

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.