Which of the following is a situation in which you would expect an iterative quality risk analysis to result in the largest number of new or changed risk items and risk levels?



A. You perform a risk analysis on the final requirements specification and subsequently receive a draft design specification.
B. A tester leaves after test design is complete, and you hire a new tester to replace her.
C. The development manager hires two additional programmers after the quality risk analysis is complete.
D. You perform a risk analysis on the final requirements specification and then that document is placed under formal configuration management.

This question is part of ISTQB Advanced Test Manager Mock Chapter 3 Exam

+ AnswerRequest Answer
...

1 Answer

mandujaz

Mandujaz

Answered on Oct 06, 2017

You perform a risk analysis on the final requirements specification and subsequently receive a draft design specification.

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.