Which of the following is an output of Direct and Manage Project Execution?



A. Project management plan
B. Requested changes
C. Approved corrective actions
D. Validated defect repair

This question is part of

PSPKV 4
Asked by PRICE, Last updated: Jul 03, 2020

+ Answer
Request

1 Answer

John Smith

John Smith

Answered Sep 09, 2016

Requested changes-requested changes are an output of direct and manage project execution. the direct and manage project execution process involves activities necessary to complete project work. often during these activities, necessary changes in the project are identified. these requested changes often reflect an increase or decrease in project scope or modifications to the project schedule. the project management plan is an output of the develop project management plan process, which is a part of project integration management. project plans are one of the inputs to direct and manage project execution. approved corrective actions are one of the inputs to the direct and manage project execution process. these actions help ensure that the project performance is conforming to the plan. validated defect repair is one of the inputs to the direct and manage project execution process. defect repair is also known as rework. as project execution proceeds, defects are identified, defect repairs are recommended and approved, the defects are repaired, and the repairs are validated.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.