Evaluate the status of the project against the defined exit criteria. Which of the following optionsshows the correct status? 2 credits



A. Criteria A = OK, criteria B = OK, criteria C = OK
B. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK
C. Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK
D. Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

This question is part of ISTQB Exam
Asked by Raquell.japhta, Last updated: Apr 17, 2020

+ Answer
Request

1 Answer

John Smith

John Smith

Answered May 09, 2017

Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK

####
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.