Which of the following would generally NOT be taken into account when setting up the work breakdown structure (WBS) for a project?



A. The relative simplicity or complexity of the WBS
B. That the WBS relates to the contractual requirements specific to the project in question
C. That the WBS can accurately track project financials
D. That the WBS allows access to only the project manager

This question is part of LAREprep Section 1 - Exam A
Asked by LAREprep, Last updated: Dec 18, 2019

+ Answer
Request

1 Answer

LAREprep

LAREprep

Answered Jul 31, 2019

That the WBS allows access to only the project manager

When setting up the work breakdown structure (WBS) for a project, the WBS should be made as simple and straightforward as possible to manage the project in question. Likewise, the WBS should relate to the contractual requirements specific to the project in question and be able to accurately track project financials. The WBS should NOT allow access to only the project manager, as various support staff may need to access the document for a variety of reasons, including tracking project budgets and billing.####
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.