What is this an example of? A project team member has, on his own initiative, added extra vents to an attic to increase air circulation. The project plan did not call for these extra vents, but the team member decided they were needed based on the geographical location of the house. The project teams experts concur with this decision.

This question is part of Scope Management Quiz
Asked by Mat, Last updated: Jun 28, 2020

+ Answer
Request

1 Answer

mat

Mat

Answered Sep 03, 2018

Ineffective change control

Even though the change is agreed upon, this is an example of ineffective change control. The team member should follow the change control process as defined in the project scope management plan. Choices A, C, and D are incorrect choices.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.