How will this affect your ability to calculate float for the finished - ProProfs
     

How will this affect your ability to calculate float for the finished activity?
As a project manager, you are tracking the project work using a network logic diagram. You would like to enter an actual finish date in order to calculate float for a finished activity.



A. Finished activities will prevent float from being calcuated correctly unless the actual finish date is equal to the scheduled finish date.
B. Calculating free float and total float is typically not done for finished activities.
C. Once the activity is finished, the amount of total float will be converted to free float.
D. Once the activity is finished, the amount of total float will be converted to slack.

This question is part of PMP Exam Prep - (Focus on Quality Management)

+ AnswerRequest Answer
...

2 Answers

Pete

Pete

Answered on Jul 18, 2019

Not done for finished activities

PMPprepper

PMPprepper

Answered on Jun 18, 2018

Calculating free float and total float is typically not done for finished activities.

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.