Which of the following is not true about the WBS?



A. The project team must be involved in developing the WBS
B. As a rule of thumb, each activity of WBS should take less than 80 hours
C. WBS should focus on activities rather than deliverables
D. WBS is usually represented in a hierarchical fashion

This question is part of Full Length PMP Simulation Test 2
Asked by Agilep, Last updated: Mar 26, 2020

+ Answer
Request

1 Answer

agilep

Agilep

Answered Mar 18, 2018

WBS should focus on activities rather than deliverables

C - The WBS puts a greater focus on the deliverables than on actual activities.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.