Which of these precedence relationship is least commonly used in precedence Diagramming Method?



A. A. Start to Start
B. B. Finish to Finish
C. C. Finish to Start
D. D. Start to Finish

This question is part of PMP Lite Mock Exam 1
Asked by Agilep, Last updated: May 26, 2020

+ Answer
Request

1 Answer

agilep

Agilep

Answered Mar 08, 2018

D. Start to Finish

D - Start to Finish relationships indicate that the next task is not able to be completed until the one preceding it has started. This is not commonly used. [PMBOK Page 138] [Project Time Management]
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.