What is the recommended course of action for the processes and procedures in the PMBOK Guide? You are a project manager for Johnson Keyboards, Inc. Your organization has adapted the PMBOK Guide as a standard tool for how projects should operate, and you are involved in shaping the standardization for all future projects.



A. Not all processes and procedures in the PMBOK Guide are actually required on all projects.
B. All processes and procedures are to be followed as defined in the PMBOK Guide.
C. Not all processes and procedures are needed, unless the PMBOK Guide states the process or procedure is a requirement for the project type.
D. All processes and procedures are to be followed as identified in the PMBOK Guide; otherwise, the PMP is in violation of the PMP Code of Ethics and Professional Conduct.

This question is part of Framework of Project Management
Asked by Krystle, Last updated: Aug 15, 2020

+ Answer
Request

1 Answer

Krystle

Krystle

Answered Feb 09, 2018

Not all processes and procedures in the PMBOK Guide are actually required on all projects.

A. Not all information in the PMBOK Guide should be applied uniformly to all projects. It is the responsibility of the project management team to determine what practices are appropriate for each project.
 

Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer
Search for Google images
Select a recommended image
Upload from your computer

Email Sent
We have sent an email to your address "" with instructions to reset your password.