John Smith
Answered: Jul 03, 2020
Cleaning the office building every day.

D. Cleaning the building is a repetitive task that is done everyday. Hence it is not an example of a project.

4 Answers

1112 views
R. Barnes, Analyst
Answered: Apr 19, 2019
The answer to this is B. The only thing that is not true about Project Charter is that it is used only to award a contract or the phase of a project. If you are not too familiar with what Project...Read More

4 Answers

534 views
The correct answer is A. The traditional project life has 5 phases which are: project initiation, planning, execution, monitoring and controlling, and closure. In the project initiation phase,...Read More

2 Answers

484 views
Jufelm.rafols
Answered: Nov 07, 2017

D. Where large or complex projects may be separated into phases or sub-projects, all of the Process Group processes would normally be repeated

2 Answers

483 views
John Adney
Answered: Nov 24, 2017

It is used primarily to award contract of a project or its phase.

2 Answers

459 views
John Smith
Answered: Jul 03, 2020
Elements can be used to update fields in the database
Only one version of a flow can be activated at a time
Apex code must be used to pass data to legacy systems

1 Answer

422 views
John Smith
Answered: Jul 03, 2020
Identical initial and final nodes can identify two activities.

1 Answer

400 views
Daina
Answered: Jul 03, 2020
It is important for leadership to promote quality.

Week 10 powerpoint slide 12-13.

1 Answer

383 views
J. Shatner, Content writer
Answered: Jan 09, 2019
Project charter is a common term heard in the project management system. It is simply the goals, outline and people who are in the project. The roles and the responsibilities that should occur in...Read More

3 Answers

382 views
Wyatt Williams
Answered: Jul 03, 2020
A specific sequence of work, described in terms of Soft logic.

1 Answer

368 views
L. Hawkes, Teacher
Answered: Nov 05, 2018
When you begin to make new products, there are certain tasks that must be done first. They must do technical, financial, and marketing tasks. Project management practices must be done in order...Read More

2 Answers

355 views
John Smith
Answered: Jul 03, 2020
Scatter diagram-a scatter diagram is used for trend analysis. this diagram plots data on an x/y axis to identify the correlation between the parameters plotted on these axes. it helps in forecasting...Read More

1 Answer

343 views
R.o.harris
Answered: Jul 03, 2020
Individuals participating must know each other for Delphi technique to be successful.

. A. Experts participating in the Delphi technique are anonymous.

1 Answer

336 views
John Smith
Answered: Jul 03, 2020
$79,000

The present value of $100,000 four years from now can be calculated by using this formula: present value = FV / (1 + i)n. FV is the future value, i is the interest rate, and n is...Read More

1 Answer

320 views
John Smith
Answered: Jul 03, 2020
Establishing a cost baseline for tracking project performance-the cost control process does not involve establishing a cost baseline for tracking project performance. this is part of the cost...Read More