Wyatt Williams
Answered: Apr 19, 2024
A Statement of work that has been formally agreed upon by both parties and is therefore part of a Contract.

1 Answer

1895 views
Wyatt Williams
Answered: Apr 19, 2024
Once project deliverables have been identified, their description should not be changed any more.

1 Answer

1312 views
C. Lopez, Chauffer
Answered: Feb 26, 2019
The correct answer to this question is C. The hardest part of a project manager's job is managing the constraints. There are six contraints of a project that influence each other: scope, quality,...Read More

3 Answers

1227 views
Wyatt Williams
Answered: Apr 19, 2024
Integration of the archive with business software

1 Answer

1169 views
L. Sevigny, Doctor
Answered: Sep 27, 2018
The project management plan should begin with a summary showing the aims and expected benefits, plus the possible constraints. The schedule is important, then the processes to be used for...Read More

2 Answers

940 views
Agilep
Answered: Apr 19, 2024
C. Hierarchical-type charts

C - Hierarchical-type organization chart can clearly show roles and reporting relationships within a team. [PMBPK 220] [Project Human Management]

1 Answer

765 views
M. Parker, Internet Researcher
Answered: Sep 20, 2018
Customer satisfaction depends upon a project, product or service meeting their expectations. This will fail if the technical aspects are inadequate, that is, the product or service did not...Read More

3 Answers

755 views
H. Jones, Web Content Writer
Answered: Jul 16, 2018
Project Charter allows for the project manager to be able to work on the project. These types of programs are something that are becoming more and more of the norm these days especially with ever...Read More

2 Answers

680 views
Agilep
Answered: Apr 19, 2024
C. Overstating the cost estimate

C- Contingency funds are used to handle cost uncertainty due to unknown purchases that may be needed during a project. These funds are generally used for...Read More

1 Answer

674 views
B. Wright, Analyst
Answered: May 17, 2019
The correct answer to this question is A, $45,600. This answer corresponds with the amount labeled ETC in the question. Related to project management, ETC stands for an estimate to complete. It...Read More

2 Answers

663 views
F. Ray, Student
Answered: Sep 14, 2018
The Project Management Institute provides certification via an examination to become a Project Manager Professional. This is a highly regarded international qualification. A project manager has...Read More

2 Answers

649 views
L. Sevigny, Doctor
Answered: Sep 14, 2018
In an internal project, the profit or potential profit must take into account any expenses incurred or possible detrimental factors. If you purchase equipment, its cost will detract from the...Read More

2 Answers

640 views
L. Sevigny, Doctor
Answered: Oct 11, 2018
A project manager is a worker who is responsible for making sure that all aspects of a project are distributed to the best workers and that they are completed so that the project is completely in...Read More

2 Answers

622 views
F. Ray, Student
Answered: Aug 29, 2018
Control threshold is often described as the limit of the project. For example, there might be a threshold in the finances that will be used for a certain project. This means that it can only...Read More

4 Answers

595 views
H. Jones, Web Content Writer
Answered: Oct 24, 2018
Letter D is the answer. Project scope is a planning activity where all of the needed work of the project is discussed. This means from specific goals, tasks, deadlines, and costs are being...Read More

3 Answers

575 views