Pert Cpm- Operations Research 1

15 Questions  I  By Dmmarathe
this test is on the topic pert cpm, subject operations research.IT is a multiple- choice test. questions: 15 questions marks: 15time: 20 mins remember: you need to click on submIT answer after selecting an option for each question.click on start quiz to begin

  
Changes are done, please start the quiz.


Question Excerpt

Removing question excerpt is a premium feature

Upgrade and get a lot more done!
1.  It is known that in a project, an activity 4-6 has duration of six days and total float of three days. The E and L times at node 4 and 8 and 11 respectively while, at node 6, both are equal to 17. Which of the following is not a true statement about 4-6?
A.
B.
C.
D.
2.  Mark the wrong statement.
A.
B.
C.
D.
3.  CPM is:
A.
B.
C.
D.
4.  Which of the following is not a rule of network construction?
A.
B.
C.
D.
5.  Mark the wrong statement.
A.
B.
C.
D.
6.  Mark the wrong statement:
A.
B.
C.
D.
7.  Which of the following is not correct in respect of PERT calculations?
A.
B.
C.
D.
8.  Which of the following is not true about crashing?
A.
B.
C.
D.
9.  Given, expected duration of project = 47 days, variance = 9 days. What is the probability of not completing the project in 50 days?      Z      :   0.33           1.00     Area :   0.1293       0.3413
A.
B.
C.
D.
10.  Point out what is not required, While considering precedence relationships
A.
B.
C.
D.
11.  Given, expected duration of project = 47 days, variance = 9 days. What is the probability of completing the project within three days more or less than the expected time?      Z      :   0.33           1.00     Area :   0.1293       0.3413
A.
B.
C.
D.
12.  Mark the wrong statement.
A.
B.
C.
D.
13.  Which of these is not correct
A.
B.
C.
D.
14.  Mark the wrong statement.
A.
B.
C.
D.
15.  Pick the wrong relationship:
A.
B.
C.
D.
Back to top


to post comments.

Removing ad is a premium feature

Upgrade and get a lot more done!
Take Another Quiz