| Side A | Side B | ||
| 1 |
What is Time Management? How many processes does it contain. Also what part of the Project...
|
Time management deals with the duration and cost of project. It contains the 6 process groups...
|
|
| 2 |
Before we start the Time Management Process what must we wait for? What does this help...
|
We need to Scope Statement & Project Management Plan.This helps us with decisions of HOW...
|
|
| 3 |
What else do we need to wait for and why?
|
Need to wait for the WBS which is the skeleton to build our schedule upon. We are also going...
|
|
| 4 |
Is Time Management a Separate process from the project?
|
No! Time is part of the overall Project Management Plan!
|
|
| 5 |
Time Management will produce what?
|
Project Schedule, Schedule Baseline and Control Procedures to manage our schedule!
|
|
| 6 |
Define Acitivities is part of what process group?
|
This is part of the Planning Process Group.
|
|
| 7 |
By creating the WBS this is necessary for what?
|
Accurate estimating (cost) and duration of the project.
|
|
| 8 |
When do we stop our WBS?Is a work package considered to be a deliverable?
|
We stop it at the Work Package level. (The marker is 2-10 day duration of work packaqe to complete!)Yes,...
|
|
| 9 |
Why do we want to break down the Deliverables?
|
We break them down into Schedule Actiivites which is necessary to produce those delvierables....
|
|
| 10 |
So explain what is the INPUT to define the Activities?
|
You need as said earlier the Scope Baseline & Project Methodology.
|
|
| 11 |
What is the Scope Baseline made up of? Where do you get this information?
|
The scope baseline is made up of the Scope Statement, WBS & WBS dictionary.
|
|
| 12 |
What does the Schedule Management Plan detail?
|
The plan specifies the extent of our futher decompostion ( if any). will also tell us what...
|
|
| 13 |
What is the reason behind Defining our Activities?
|
The over-view is : We must understand,determine & expose all parts from the Scope Statement...
|
|
| 14 |
The WBS is directly proportional to the Scope Statement? True or False.
|
True. The Activities list that comes from the Scope Statement is only as complex as the Scope...
|
|
| 15 |
So what is the Methodologies to Defining Activities? In other words, how are we to define it?...
|
Decomposition Method- Scope broken into deliverables to our W.P.Rolling Wave Method- Is a process...
|
|
| 16 |
What is Expert Judgment used for?
|
P.M.'s don't know everything so they rely on team members, subject matter experts etc. to help...
|
|
| 17 |
What are the Outputs from Defining the Acivities?
|
Activity List, Activity Attributes and Milestones!
|
|
| 18 |
What is a Activity List?
|
This is a collection of all the work requirments (Parts) to complete the project. This is nothing...
|
|
| 19 |
What is a Milestone?
|
This is a checkpoint.It shows the High level view for executives. They contain little value...
|
|
| 20 |
What are Activiity Attributes?
|
These are th OUTPUTS from defining the activities. They provide further detail on the schedule...
|
|
| 21 |
What does Activity Attributes include?
|
Activity Identifiers, Codes, Work Description,Work Location,Predecessors & successor relationships,leads...
|
|
| 22 |
Does each activity in the activity list, should this be documented?
|
Yes, The document helps with additional planning,risk identification,resources needed etc....
|
|
| 23 |
What do we call when we Update the WBS?
|
This is called Refinements. The refinement ensure that all deliverables are accounted for within...
|
|
| 24 |
We have the Workbreak down structure. Where did this come from?
|
It came from the Scope Baseline.
|
|
| 25 |
What component does the WBS use?
|
It uses the control accounts. This is a Marker which tracks performance. Each floor in a house...
|
|
| 26 |
Explain Control Accounts. What are they used for?
|
The WBS uses a component for project performance call Control Accounts. This is a marker in...
|
|
| 27 |
How many different Milestones are there?
|
You have 2 types of Milestones.
|
|
| 28 |
What is a Mandatory Milestone?
|
This is like the government placing requriements that we must meet by a certain date.
|
|
| 29 |
Optional Milestones?
|
This is based on the OPA or expert judgement.
|
|
| 30 |
What is another name for Logical relationships for an activity?
|
This is called Sequencing the Activities.
|
|
| 31 |
What is Sequencing Activities?
|
This is a Predecessor network or relationship in a Precedence Diagram. We specify the dependencies...
|
|
| 32 |
What Inputs do we need to do Activity Sequencing?
|
We need the Activity List & Attributes and the scope statement.
|
|
| 33 |
How can we develope the different kinds of sequencing?
|
Computer driven,Manual process or Blended which includes both.
|
|
| 34 |
What is meant by computer driven approach?
|
This is software packages that are available. This helps the team determine the actions that...
|
|
| 35 |
What is meant by Manual Process?
|
Especially in smaller projects, It is easier to move around dependencies and activities.
|
|
| 36 |
What is the Blended approach to sequencing?
|
This is just a combo. of the computer and manual approach.
|
|
| 37 |
How do we create the picture for sequence activites?
|
We can use the Precedence Diagramming Method PDM. This is also know as the Activity on Node....
|
|
| 38 |
The Activity on Node, what does the Node represent and then the lines mean?
|
The Node represents the Activity. The lines represent the Logical predecessor relationship....
|
|
| 39 |
When we create the Network Diagram what must we take into account as well?
|
We must take into account the Leads and Lags of the predecessor relationship.
|
|
| 40 |
what does it mean Lead predecessor relationship?
|
Lead slightly alters the relationship between 2 or more work packages. Remember: Lead time...
|
|
| 41 |
What is meant by Lag time?
|
Lag time is positive time that is ADDED to the project schedule. This is normally called waiting...
|
|
| 42 |
What is another name for Accelerated time?
|
This is called Lead time.
|
|
| 43 |
Is activity sequencing a schedule?
|
No, its a network known as network diagramming.
|
|
| 44 |
Are Dependencies considered to be restrictions to the order of sequence or the activitites...
|
Dependencies are restrictions on the order. It is based on relationships.
|
|
| 45 |
What is a Mandatory Dependencies & what is another name for this?
|
Manadatory dependencies is the way the work must flow. Like a oil change case, you cannot...
|
|
| 46 |
How many types of Dependencies are there?
|
You have 4 of them. The first is the Mandatory, Discretionary, External and Milestone.
|
|
| 47 |
Explain what is Discretionary Dependency?
|
These are dependencies the an organization might prefer. Several ways to approach a task in...
|
|
| 48 |
External Dependency is what?
|
This falls into 2 categories. The 1st one involves something outside of the project activities...
|
|
| 49 |
Milestone Dependency is what ?
|
You may have an agreement that a certain part of the project will be done by a certain date...
|
|
| 50 |
Once you described all the activities and have accounted for dependencies, It is time to do...
|
It is time to start you Activity Sequence. Remember this is a graphical representation, not...
|
|
| 51 |
Another name for Network Diagramming is what?
|
Activity on Node or Precedence Diagramming Method.
|
|
| 52 |
Why is Precedence Diagramming Method common to use?
|
Because it allows for different types of relationships or precedence among activities.
|
|
| 53 |
There are 2 terms that is used in Network Diagramming Method, what are they?
|
Predecessor which means the activity before a given task.The other is the Successor which means...
|
|
| 54 |
P.D.M recognizes 4 types of relationships, what are they?
|
Finish to Start, Finish to Finish, Start to Finish, Start to Start. these are related to how...
|
|
| 55 |
What does it mean Finish to Start relationship? (F.S.)
|
This is the most common relationship. A successor cannot begin until the predecessor has finish....
|
|
| 56 |
What does it mean Finish to Finish Relationship? (F.F)
|
A successor cannot finish until the predecessor has been completed. Example: You could jack...
|
|
| 57 |
What is does it mean Start to Start relationship? (S.S)
|
A successor cannot start until a predecessor has started.For example; A painter scraping the...
|
|
| 58 |
What does it mean Start to Finish Relationship? (S.F.)
|
A successor task cannot be completed until a predecessor task is started. Note: This is one...
|
|
| 59 |
What part of the process is Activity Sequencing done?
|
Its part of the planning process group.
|
|
| 60 |
Sequence Activities is what?
|
We establish the sequence of the activities in our project.
|
|
| 61 |
What do we use to sequence the activities?
|
We need the Acitivity List produced from the previous process & THE information about the...
|
|
| 62 |
Activity Resource Estimate what is this about?
|
This is part of the planning process group. Here we identify skills on each activity &...
|
|
| 63 |
In doing the Activity Resource, what level is our schedule activity at?
|
This is at the lowest level of the schedule activities. After we get the estimates for each...
|
|
| 64 |
What is the Input for Activity Resource Estimating?
|
Can't start until we have: Activity List/ Activity Attributes & Calendars (2)). The...
|
|
| 65 |
Where do we find the information on Resource availability?
|
We get this information from the EEF- historical data & OPA-resources consumed on previous...
|
|
| 66 |
What are the 3- tools & techniques we use to determine the activity resource estimate?
|
The tools are : Alternative Analysis- which is seeking other ways to acquire the resources...
|
|
| 67 |
What is the Output you get from the tools and techniques from Resource Estimating Activity?
|
You get the Activity Resource Estimates as well as the Resource Breakdown Structure.
|
|
| 68 |
What is Resource Breakdown Structure?
|
This is a description of the types of resources that the project requires and the total quanatiy...
|
|
| 69 |
What is a Resource Calendar do?
|
It tells you when people are and are not available to work on the project. Also tells you about...
|
|
| 70 |
Can resource calendar change your schedule or refinements to the schedule?
|
Yes, it may produce changes to the schedule activities and activity attributes.
|
|
| 71 |
What is Activity Duration Estimate?
|
This is based on the amount of work effort required to complete the schedule activity.
|
|
| 72 |
What should the Duration Estimate also refect?
|
Any waiting time within the schedule activity. this could make the elapsed time longer than...
|



No comments yet! Be the first to add a comment below!